Forwards Request for Addl Info Re 851206 Request for Tech Spec Rev to Permit Steam Generator Tube Sleeving in Lieu of Plugging Degraded Tubes.Info Re Maintaining ALARA During Sleeving Program Needed within 7 Days
ML20141N069
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 02/21/1986
From: Frank Akstulewicz
Office of Nuclear Reactor Regulation
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO.
References
NUDOCS 8603030514
Download: ML20141N069 (3)


Text

-. - . , - . . . . ,. .. . -

, February 21g l'986 l

00cket No. 50-213 Mr. John F. Opeka, Senior Vice President Nuclear Engineering and Operations Connecticut Yankee Atomic Power Company P.ost Office Box 270

Hartford, Connecticut 06141-0270 Dear Mr. Opeka-4

SUBJECT:

REQUEST FOR ADDITIONA1. INFORMATION CONCERNING THE PROPOSED STEAM GENERATOR TUBE SLEEVING PROGRAM Re: Haddam Neck Plant By letter dated Deceicer 6,1G85, Connecticut Yankee Atomic Power Company rectested revisicns to the Haddam Neck Plant technical specifications to perstit steem generator tubo sleeving in lieu of pluggir.g degraded tubes.

The staff has reefewed the information contained in the December 6, 1985 ,

letter and the steam generator tube sleeving report provided by .W/o WCAP-11009.WCAP-11008 Withheld (Ref 10CFR2.790)|letter dated January 7,1986]] end concludes that additional information concerning

, the AI. ARA aspects of the sleeving program is needed for us to complete 3

our review.

The two requests for information are enclosed, In or:fer for us to complete our review according to the required schedule surtup, we request that the information be provided within 7 days of receipt of this letter, The information requested effects fewer than 10 respondents, therefore, OMS clearance is not required under P. (..96-511.

Sincerely, ,

4 Original signed by:. F. Akstulewicz -

~

' 03030514 e60221 Francis Akstulewicz, Project Manager fDR ADOCK 0 % 2 3 Integrated Safety Assessnient P Project Directorate Division of PWR Licensing - B DISTRIBUTION

Enclosure:

";0cchet.Fu e u EJordan As Stated ISAPD Reading BGrimes NRC PDR JPartlow cc: See Next Page Local PDR ACRS (10)

NSIC PAnderson FAkstulewicz OELD '

FMiraglia ISAPD:DPL-B IS PL-B -ISAhlfPl!jB f FAkstulewicz:lt P sn CGrlmes 19 02/se/86 02//3 /86 02/g/86 .

,, - -+-- , w w w-- w ' ---w

Mr. John F. Opeka Connecticut Yankee Atomic Power Company Haddam Neck Plan't CC:

  • Gerald Garfield, Esquire Kevin McCarthy, Direr. tor Day, Berry & Howard Radiation Control Unit Counselors at Law Department of Environmental City Place Protection Hartford, Connecticut 06103-3499 State Office Building i Hartford, Connecticut 06106' Superintendent Haddam Neck Plant Richard M. Kacich, Supervisor ROF #1 Operating Nuclear Plant Licensing Post Office Box 127E Northeast Utilities Service Company East Hampton, Connecticut 06424 Post Office Box 270 Hartford, Connecticut 06141-0270 Edward J. Mroczka Vice President, Nuclear Operations Northeast Utilities Service Cempany Post Office Box 270 Hartford, Connecticut 06141-0270 Board of Selectmen Town Hall Haddam, Connecticut 06103 State of Connecticut Office of Policy and Management ATTN: Under Secretary Energy Division 80 Washington Street Hartford, Connecticut 06106 Resident inspector Haddam Neck Nuclear Power Station c/o U.S. NRC East Haddam Post Office East Haddam, Connecticut 06423 Regional Administrator, Region I l U.S. Nuclear Regulatory Commission 631 Park Avenue l King of Prussia, Pennsylvania 19406 e , . . ,

b ENCLOSURE 1 ,

STEAM GENERATOR TUBE SLEEVING PROGRAM REQUEST FOR ADDITIONAL INFORMATION

'I. Provide a table showing the collective occupational dose estimate for the steam generator sleeving program. Include all occupational dose resulting from sleeving operations, including all site ar.d contractor support personnel. This information should include a breakdown of rach task by estimated dose rates and person-hours that coincide with the person-rem estimates in your December 6, 1985 technical sper'fication revision letter. The data should be in sufficient detail to permit unambiguous calculation of the project person-rem dose likely to result.

2. Describe any provisions for special local ventilation in the steam generator repair area.