Responds to IE Bulletin 85-003, Motor-Operated Valve Common Mode Failure During Plant Transients Due to Improper Switch Settings. Due to Const Delay,Requested Schedules Will Be Provided After Const Restart
ML20141F500
Person / Time
Site: Satsop
Issue date: 04/07/1986
From: Olson P
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO3-86-203, IEB-85-003, IEB-85-3, NUDOCS 8604230049
Download: ML20141F500 (2)


Text

1 Washington Public Power Supply System Box 1223 Elma, Washington 98541 1223 (206)482-4428 m

83 n

April 7, 1986 5

7 J

AE S

Q G03-86-203

-i

?

~

~

=~

3 Docket No. 50-508 Mr. J. B. Martin, Regional Administrator U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement - Region Y 1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Subject:

NUCLEAR PROJECT 3 REQUIRED ACTIONS IN RESPONSE TO IE BULLETIN 85-03

References:

a) NRC IE Bulletin 85-03:

" Motor-0perated Valve Comon Mode Failures During Plant Transients Due to Improper Switch Settings".

b) Letter (G03-86-146 ),

G.

C.

Sorensen to H.

R.

Denton, subject, " Revised Construction Permit Amendment Request",

dated March 10, 1986.

Reference a) requested a written report submitted within 180 days detailing:

1) the results of a review of the design basis for the operation of motor operated valves; and 2) identification of the programs and schedules for implementation of the other action items delineated in the IE Bulletin.

Due to the construction delay at WNP-3, it is not porsible to submit this information at this time. As indicated in Reference b), WNP-3 plans call for a resumption of construction activities in 1994.

Therefore, we plan to provide the requested schedules after construction restart.

&b

?

e

'

  • fj~-6 /

Mr. J. B. Martin, Regional Administrator G03-86-203 Page TWo April 7, 1986 It should be understood that with construction of WNP-3 currently in a long term delay mode, we will not be making any changes prior to restart that will make the impi ion of the requirements of Reference a) more difficult.

W Pau

. Olson (760)

  1. Program Director, WNP-3 MKH/cae cc: Mr. J. A. Adams, NESCO Mr. R. M. Boucher, Pacific Power & Light Company Mr. W. L. Bryan, Washington Water Power Company Mr. J. Crnich, Ebasco - Elma Mr. W. J. Finnegan, Puget Sound Power & Light Company Mr. J. R. Lewis, BPA Mr. N. S. Reynolds, Bishop, Liberman, Cook, Purcell and Reynolds Mr. B. D. Withers, Portland General Electric Company U. S. NRC Document Control Desk

.