Text
[pa urgIo,,
UNITED STATES NUCLEAR REGULATORY COMMISSION g
E WASHINGTON, D. C. 20555
\\.....}
DEC d Docket No. 99900871/85-01 Elgar Corporation ATTN: Mr. P. A. Zecos Vice President and General Manager 9250 Brown Deer Road San Diego, California 92121
Dear Mr. Zecos:
This refers to the inspection conducted by Mr. J. J. Petrosino of this office on September 17-19, 1985, of your facility at San Diego, California and to the discussions of our findings with you and members of your staff at the conclusion of the inspection.
The purpose of this inspection was to obtain specific product information concerning 7.5 KVA static inverters, review the recently identified fuse block stud problems, and review the implementation of Elgar's quality assurance program in selected areas.
Areas examined during the inspection and our findings are discussed in the enclosed report. Within these areas, the inspection consisted of an examination of procedures and representative records, interviews with personnel, and observations by the inspector.
During the inspection it was found that the implementation of your QA program failed to meet certain NRC requirements.
Three noncompliances were identified during the inspection. Two of these were revealed during a review of the circumstances surrounding the fuse block stud problem which was identified on Elgar's 25 KVA inverters at the River Bend nuclear station. These noncompliances were in the areas of design data translation and assembly instructions.
The third item of noncompliance involved a lack of quality assurance program requirements within portions of your organization.
The specific findings and references to the pertinent requirements are identified in the enclosures to this letter.
Please provide us within 30 days from the date of this letter a written statement containing:
(1) a description of steps that have been or will be taken to correct these items; (2) a description of steps that have been or will be taken to prevent recurrence; and (3) the dates your corrective actions and preventive measures were or will be completed.
Consideration may be given to extending your response time if good cause is shown.
8601090282 851227 PDR GA999 EMVELGAR 99900H71 PDR s
ft
A
- - +
A_
L.
6'2~ %
Elgar Corporation -
i
~The response requested by this letter is not subject to the clearance procedures of the Office of Management and Budget as required by the Paperwork Reduction Act of 1980 PL 96-511.
In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you, i
Sincerely, Als Gary ech, Chief Vendor Program Branch 1
Division of Quality Assurance, Vendor, and Technical Training Center Programs Office of Inspection and Enforcement
Enclosures:
1.
Appendix A - Notice of Nonconformance 2.
Appendix B - Inspection Report No. 99900871/85-01 3.
Appendix C - Inspection Data Sheets (3 pages) cc w/ enclosures:
See next page cc w/ enclosures:
Mr. J. J. Carey, Vice President Nuclear Group Duquesne Power Post Office Box 4 i
Shippingport, Pennsylvania 15077 Mr. D. Foster, Vice President and Project General Manager Georgia Power Route 2 Pox 299A Waynesboro, Georgia 30830 Mr. W. J. Cahill, Jr., Senior Vice President River Bend Nuclear Group Gulf States Utilities Post Office Box 2951 Beaumont, Texas 77704 1
l DEC 27 'Mi Elgar Corporation l Mr. J. H. Goldberg, Group Vice President, Nuclear Houston Lighting & Power Post Office Box 1700
- Houston, Texas 77001 l
Mr. B. J. Hooten, Executive Director, Nuclear Operations Niagara Mohawk Power 300 Erie Boulevard West Syracuse, New York 13202 i
Hr. J. F. Opeka, Sr. Vice President l
Nuclear Engineering & Operations Northeast Nuclear Energy Post Office Box 270 Hartford, Connecticut 06141 Mr. R. J. Harrison, President and Chief Executive Officer Public Service Company of New Hampshire j
Post Office Box 330 Manchester, New Hampshire 03105 Mr. M. D. Spence, President l
Texas Utilities Generating Company l
400 N. Olive Street, L.B. 81 Dallas, Texas 75201 Mr. D. W. Mazure, Managing Director Washington Public Power Supply System Post Office Box 968 Richland, Washington 99352 i
l l
DEC 2 71985 Elgar Corporation Di W ibution:
A B:lE:09 VPB Reading DQAVT Reading RVollmer JStone GHolahan, NRR EWMerschoff JJPetrosino RStarostecki, Region I RWalker, Region II CENorelius, Region III EJohnson, Region IV DKirsch, Region V REArchitzel, IE JEKonklin, IE JLMilhoan, IE
- See previous concurrences.
VPB:00AVT SC/VPB:00AVT BC/VPB:DQAVT
-Q JPetrosino*
EWMerschoff*
GGZech*
ri es 12/05/85 12/06/85 12/12/85
./2p85
- -