Rev 1 to CK-MP3-02-02, Sys Requirements List
ML20141E518
Person / Time
Site: Millstone Dominion icon.png
Issue date: 05/16/1997
From: Neri A, Schopfer D
SARGENT & LUNDY, INC.
To:
Shared Package
ML20141E462 List:
References
CK-MP3-02-02, CK-MP3-2-2, NUDOCS 9705210024
Download: ML20141E518 (4)


Text

-

'o

l q

l

. Northeast Utilities l Millstone- Unit 3  !

)

4 1

Independent Corrective Action Verification Program )

(ICAVP) i

, l System Review Checklist CK-MP3-02-02, Rev.1 ,

System Requirements List-Prepared by: A. A. /Jer i 5//3/47 Name Signature ) Date Approved by: 1%.Seb M 1 EdLb _

C-/(,- f y Name Signattle /7 Date s

i IMPLEMENTATION System Signature Date SRG Lead Verifier:

4 ORG Lead Verifier: ,

I SRG Lead:

' ORG Lead:  :

9709210024 970516 5'  !

'ha PDR P

ADOCK 05000423-

  • pm
m. .

Sheet 1 of 4

Northeast Utilities CK-MP3-02-02

Millstone Unit 3 -- System i Sheet of I I

System Requirements List )

Instructions I

. These instructions supplement PI-MP3-02 and shall be used for the development of the system e reference list. Application of this checklist shall be as follows:

- Identification of Reauirements [

L ~ System requirements identified during the review of the FSAR, SAR, Technical  ;

Specifications, MP3 Commitments and Position Papers (if applicable), etc., shall be  !

entered individually on the System Requirements List as follows:

Note: The system requirements list will be developed electronically using an Access 3

Database. The form on page 4 is a sample of the Anal list. The final list will be sorted by the six categories; Design, Functional, Performance, Operational, .

Maintenance and Testing Requirements and several subcategories for each l category including Mechanical, Electrical, I&C, Structural, Piping, EQ/SQ,  ;

Hazards, Station Blackout, Flooding, etc.
a. Enter detailed description of requirement under the appropriate category.  ;
b. Enter source document, section, etc. l
c. Requirements identified under each category shall be automatically numbered i beginning with 0001.
d. Enter the DR number for any conflicting requirements identified during the review.
2. The preparers name will automatically be entered by the Access Database.
3. The Independent Verifier shall indicate his concurrence with a specific entry by completing l the review block on the database. The Applicable Group Lead shall indicate his approval  !

' by completing the Approval block.

l

.. Disposition  !

~

li Disposition of system' requirements shall be entered as follows:

a: - Enter documents reviewed against system requirement. Use description for  !

references from System Reference List (CK-MP3-02-1) for consistency.  :

b. Enter whether document reviewed conforms with system requirement identified in j checklist (SAT or USAT).

j

c. Enter DR No. for USAT documen'ts.  !

l (CK-MP3-02-02, Rev.1, Page 2) ,

C;\CK 0202. DOC : \

i

+ >

w .. - - -

, a , _ , .

CK-MP3-02-02 l Northeast Utilities Millstone Unit 3 System l Sheet of l l

System Requirements List

2. The Preparer's name will be automatically entered by the Access Database. The

. Independent Verifier shall indicate his concurrence by completing the Resiew block of the database. The Applicable Group Lead shallindicate his concurrence by completing the ,

approval block on the database.

Miscellaneous

1. Deviations identified during the preparation or disposition phase shall be processed per PI-MP3-11.
2. Hard copies of the completed list shall be used for final reports and any other external distribution. Hard copies shallinclude the coversheet (Page 1) and a database sort consistent with the format shown on page 4 of this checklist.
3. For hardcopies, the SRG Lead Verifier shall be responsible for assembly of the completed checklist and for completing the checklist coversheet including the identification of system

~

and sheet numbenng. Sheet numbering shall be numerical.

4. The ORG and SRG Lead Verifiers and ORG and SRG Leads shall sign and date the coversheet for all hardcopy distributions.
5. Changes made after ORG and SRG Lead signatures shall be processed as a formal revision to the checklist. New SRG & ORG Verifier and Lead Signatures shall be required.

lCK-MP3 02-02, Rev.1. Page 3)

CSCK.0202. DOC

Mortheast Utilitics CK-MP3-03-02 ..

Millstone Unit 3 . Systens Sheet of' Modification Review Adoniaistrative Checklist REQUIREMENTS DISPOSITION 1

Initinic No. Description Reference (Prep./Rev.) Docunnents Reviewed SAT USAT Initials A. Design Requirements B. Functional Requirements C. ' Perfinmance Requirements D. Operational Requirements E. Maintenance Requirements F. Testing Requirements (CK-MP3-02-02, Rev. O, Page 4) j CSCK-02-02. DOC

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ . - , - . _ _ _ _ _ _ _ , . _ . . . , _ . _ . . _ . _ , _ ._. ., .. . .. . __.- - ._..__ . . . . _ .