ML20141B129
| ML20141B129 | |
| Person / Time | |
|---|---|
| Site: | San Onofre |
| Issue date: | 03/28/1986 |
| From: | Chilk S NRC OFFICE OF THE SECRETARY (SECY) |
| To: | Stello V NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO) |
| References | |
| REF-10CFR9.7 M860318, NUDOCS 8604040632 | |
| Download: ML20141B129 (2) | |
Text
.
IN RESPONSE, PLEASE
[digea c8%q%,
REFER TO:
M860318 UNITED CTATES NUCLEAR REGULATORY COMMISSION Mf 3
g W ASHINGTON. D.C. 20$55 y
%,..,.+/
March 28, 1986 OFFICE OF THE SECHETARY MEMORANDUM FOR:
Victor Stello, Jr.
Acting Executive Director for Operations FROM:
Samuel J. Chilk, Secr
SUBJECT:
STAFF REQUIREMENTS.- LRA1:FING.BY SOUTHERN CALIFORNIA' EDISON CO. Ott' GAN ONOFRE-1, 10:00 A.M.,
TUESDAY, M A R C H l'8, 1986, COMMISSIONERS' CONFERENCE ROOM, D.C. OFFICE (OPEN TO PUBLIC ATTENDANCE)
The Commission met with representatives of Southern California Edison (SCE) Co. to discuss the Novetober 21, 1985 loss of power / water hammer event at San Onofre Unit 1.
The following persons participated in this meeting:
David J. Fogarty Executive Vice President, SCE Kenneth P. Baskin Vice President Nuclear Engineering Safety and Licensing, SCE Mark O. Medford, Manager Nuclear Licensing, SCE j
Russ W. Krieger, Manager Operations, SCE Dr. Lawrence Papay Senior Vice President, SCE Jack Rainsberry, Supervisor San Onofre Unit 1 Licensing Commissioner Zech requested staff to advise licensees of the potential generic implications of the age-related cable failure at San Onofre-l.
(NRR)
(SECY Suspense:
4/30/86) 8604040632 860329 PDR 10CFR PT9.7 pp3 h
4 2-Commissioner Zech also requested staff to discuss with INPO and others the generic question of using plant electrical blueprints in operator training to enable operators to pinpoint electrical problems.
(NRR)
(SECY Suspense:
5/30/86)
Chairman Palladino. requested staff to provide information on the design basis for containment energy mitigation in San Onofre-1 and whether the staff is satisfied with the arrangement.
(NRR)
(SECY Suspense:
4/30/86) 4 a
ii cc:
Chairman Palladino Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Zech 1
Commission Staff Offices PDR - Ad /ance d DCS5-2016;iPhillips'S 1
-