Notification of Contract Execution,Mod 5,to Review & Evaluation of Comanche Peak Program Plan. Contractor: Teledyne Engineering Svcs
Date released: 06/03/2020 Download: ML20141A416


Mod 5,revising Task (E) Incorporated by Mod 4 & Increasing Obligated Funding,To Review & Evaluation of Comanche Peak Program Plan.
ML20141A479
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 03/19/1986
From: Edgeworth P, Moonan W
NRC OFFICE OF ADMINISTRATION (ADM), TELEDYNE ENGINEERING SERVICES
To:
References
CON-FIN-D-1338, CON-NRC-03-85-067, CON-NRC-3-85-67
Download: ML20141A479 (4)
Notification of Contract Execution,Mod 5,to Review & Evaluation of Comanche Peak Program Plan. Contractor: Teledyne Engineering Svcs
ML20141A412
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 03/19/1986
From: Hawkins D
NRC OFFICE OF ADMINISTRATION (ADM)
To: THOMPSON H, TRAMMELL C
NRC
References
CON-FIN-D-1338, CON-NRC-03-85-067, CON-NRC-3-85-67
Download: ML20141A412 (1)