Issue date: 03/20/1986
From: Zwolinski J
Office of Nuclear Reactor Regulation
To: Taylor J
DAIRYLAND POWER COOPERATIVE
Shared Package
ML20140D728 List:
References
GL-83-28, TAC-52930, TAC-53766, NUDOCS 8603260444
Download: ML20140D722 (3)


Text

. .

M 20 1986 Docket No. 50-409 l Mr. James W. Taylor General Manager Dairyland Power Cooperative 2615 East Avenue South La Crosse, Wisconsin 54601

Dear Mr. Taylor:

SURJECT: SAFETY EVALUATION FOR GENERIC LETTER 83-28, ITEMS 3.1.1, 3.1.2, 3.2.1, AND 3.2.2 (POST-MAINTENANCE AND RTS FUNCTIONAL TESTING)

(TAC 52930, 53766)~

Re: La Crosse Boiling Water Reactor (LACBWR)

By Generic Letter (GL) 83-28 dated July 8, 1983, you were requested to respond to certain generic concerns that developed from the investigation into the failure of scram circuit breakers at the Salem Nuclear Power Plant, Unit 1.

These concerns are categorized into four areas: (Item 1) Post Trip Review; (Item 2) Equipment Classification and Vendor Interface; (Item 3)

Post-Maintenance Testing; and (Item 4) Reactor Trip System Reliability Improvements. Your response to these four areas of GL 83-28 was provided by a letter dated October 25, 1983.

We have completed cur review of your response to Items 3.1.1, 3.1.2, 3.P.1 and 3.2.2 of GL 83-28 relating to Post-Maintenance Testing. The results of our review are provided in the enclosed Safety Evaluation. Based on our review, we find that your Post-Maintenance Testing and RTS Functional Test requirements meet the requirements of GL 83-28 and are, therefore, acceptable. We consider all of the items addressed in Sections 3.1 and 3.2 of GL 83-28 to be resolved.

Sincerely, G@sa! Wurd by John A. Zwolinski, Director BWR Pro,iect Directorate #1 Division of BWR Licensing

Enclosure:

Safety Evaluation cc w/ enclosure:

See next page DISTRIBUTION

  • Dottet .F11e

~ ~ ' "

-9 ~CJamerson NRC PDR JStang Local PDR JZwolinski 8603260444 G6032 BWD#1 Reading ACRS (10) yDR ADOCK 05000 09 RBernero TETaylor PDR EJordan RBuck BGrimes GHolahan JPartlow OELD M/

W DRL:PD#1 DBL:PD# RL:PD# DBL:PD#1 CJamerso RRuc JStang:tm JZwolinski

$/$/86 3 />6/86 5/Jo/86 $/go/ 86

/ 'o,, UNITED STATES

! o NUCLEAR REGULATORY COMMISSION

E WASHINGTON. D. C. 20655

. . . . . ,f March 20,1986 Docket No. 50-409 Mr. James W. Taylor General Manager Dairyland Power Cooperative 2615 East Avenue South La Crosse, Wisconsin 54601

Dear Mr. Taylor:

SUBJECT:

SAFETY EVALUATION FOR GENERIC LETTER 83-28, ITEMS 3.1.1, 3.1.2, 3.2.1, AND 3.7.2 (POST-MAINTENANCE AND RTS FUNCTIONAL (ESTING)

(TAC 52930, 53766)

Re: La Crosse Boiling Water Reactor (LACBWR)

By Generic Letter (Gli 83-28 dated July 8,1983, you were requested to respond to certain generic concerns that developed from the investigation into the failure of scram circuit breakers at the Salem Nuclear Power Plant, Unit 1.

These concerns are categorized into four areas: (Item 11 Post Trip Review; (Item 2) Equipment Classification and Vendor Interface; (Item 3)

Post-Maintenance Testing; and (Item 4) Reactor Trip System Reliability Improvements. Your response to these four areas of GL 83-28 was provided by a letter dated October 25, 1983.

We have completed our review of your response to Items 3.1.1, 3.1.2, 3.2.1 and 3.2.2 of GL 83-28 relating to Post-Maintenance Testing. The results of our review are provided in the enclosed Safety Evaluation. Based on our review, we find that your Post-Maintenance Testing and RTS Functional Test requirements meet the requirements of GL 83-28 and are, therefore, acceptable. We consider all of the items addressed in Sections 3.1 and 3.2 of GL 83-20 to be resolved.

Sincerely, fI w .

John Zwolinski, Director l BWR Pr ject Directorate #1 '

Division of BWR Licer. sing i

Enclosure:

Safety Evaluation )

i cc w/ enclosure See next page 1 l

i Mr. James W. Taylor Dairyland Power Cooperative La Crosse Boiling Water Reactor cc:

Fritz Schubert, Esquire Clarence Riederer, Chief Engineer Staff Attorney Wisconsin Public Service Dairyland Power Cooperative Commission 2615 East Avenue South Post Office Box 7854 La Crosse, Wisconsin 54601 Madison, Wisconsin 53707 Roy P. Lessy,.1r.

O. S. Heistand Morgan, Lewis & Bockius 1800 M Street, N.W.

7th Floor North Receptionist Washington, D.C. 20036 Mr. John Parkyn, Plant Manager La Crosse Boiling Water Reactor Dairyland Power Cooperative P. O. Box 275 Genoa, Wisconsin 54632 U.S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1, Box 276 Genoa, Wisconsin 54632 Town Chairman Town of Genoa Route 1 Genoa, Wisconsin ~54632 Chairman, Public Service Commission of Wisconsin Hill Farms State Office Building Madison, Wisconsin 53702 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137