ML20138R316

From kanterella
Jump to navigation Jump to search
Memorandum & Order Denying Util 850709 & 0910 Requests for Extension of 851130 Deadline for Environ Qualification of Electric Equipment.Justifications Support Safe Operation Until 860330.Served on 851115
ML20138R316
Person / Time
Site: Brunswick Duke Energy icon.png
Issue date: 11/15/1985
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To:
CAROLINA POWER & LIGHT CO.
References
CON-#485-185 OL, NUDOCS 8511180539
Download: ML20138R316 (3)


Text

,

f, UNITED STATES OF AMERICA IS A9:20 NUCLEAR REGULATORY COMMISSION bic . ..

COPetISSIONERS:

!]lllC" -

Nunzio J. Palladino, Chairman Thomas M. Roberts James K. Asselstine SERB NOV.151,985 Frederick M. Bernthal Lando W. Zech, Jr.

)

CAROLINA POWER AND LIGHT C0. ) 4 oL.

) Docket No.50-32F (Brunswick Steam Electric Plant, )

Unit 2)

MEMORANDUM AND ORDER

^

By letters dated July 9,1985, and September 10, 1985, Carolina Power and Light Company ("CP&L") requests that the Comission grant an extension from the November 30, 1985, deadline for environmental E qualification of electric equipment at the Brunswick Steam Electric Plant, Unit 2. On October 9, CP&L representatives appeared before the Comission to discuss this request further and on October 10 CP&L '

provided additional information in a letter to the Comission. The Comission has reviewed in detail the licensee's submittals, including the October 10 letter, the staff's analysis and recommendation as set forth in SECY-85-321, and the arguments put forth by the licensee at the

October 9 meeting. Based on this review the Comission finds that the 8511180539Bjogg$24 PDR ADOCK O PDR 3501

V 2

licensee has failed to demonstrate exceptional circumstances that would support an extension of the November 30 deadline.

The Comission most recently addressed the environmental qualifica-tion issue in Generic Letter 85-15, issued August 6,1985. In that letter the Comission stated that extensions from the November 30 deadline established in 10 CFR 50.49(g) would be granted "only in rare circumstances." The Comission further stated that extension requests "must clearly identify the exceptional nature of the case, e.g., why, through events entirely beyond its control, the licensee will not be in compliance on November 30; the date when compliance will be achieved; and a justification for continued operation until compliance will be ,

achieved." The Comission also set forth an enforcement policy regarding failure to meet the deadline.

As is apparent from the Comission's previous pronouncements, equipment qualification is a matter of safety significance and the NRC has sought to compel diligent licensee efforts to achieve industry-wide compliance with its requirements in this area. On the basis of the handful of extension requests the Comission has received, it appears that most licensees have completed their programs within the 10 CFR 50.49 schedule. This shows that reasonably diligent efforts comencing when the Comission first ordered industry-wide actions in 1980 have generally enabled licensees to achieve compliance by this time. Yet, for Brunswick Unit 2 approximately fifty items of electric equipment important to safety are not qualified. Moreover, the licensee did not, in the Comission's view, demonstrate that this shortfall was due to circumstances beyond the licensee's control. Although the licensee

e i

4 3 asserts that unique elements of its plant design were a primary cause of the delay in completion of its program, recognition of those elements

.and planning for timely completion of its qualification program in light of those elements were matters within the licensee's control. In fact, the delay in program completion was caused in large part by the licensee's decision to defer equipment qualification work and by the licensee's desire to operate at least one of the Brunswick units at all times. Whatever hardship the licensee may now incur as a result of its failure to achieve compliance must be attributed to its earlier decisions.

The Comission therefore denies the request of CP&L for an extension on Brunswick Unit 2. The staff has reviewed the justifications for continued operation and finds they support safe operation to March 30, 1986. On this basis CP&L may operate the facility from November 30 until March 30, 1986, subject to civil penalty, or may, at its option, cease plant operation on or before November 30 to complete its equipment qualification program.

Comissioner Roberts disapproved this order.

It is so ORDERED.

or the Comission

[

CO. l SAMUEL J.\ CHILK Secretary of the Comission Dated at Washington, D.C.

this Jf @ day of / w 1 % 1985.

l L