Forwards Amend 106 to License DPR-21 & Safety Evaluation. Amend Deletes App B in Entirety & Provides New Tech Spec Sections Defining Limiting Conditions for Operation & Surveillance Requirements for Radioactive Liquid
ML20138R188
Person / Time
Site: Millstone Dominion icon.png
Issue date: 10/01/1985
From: Zwolinski J
Office of Nuclear Reactor Regulation
To: Opeka J
NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML20136G192 List:
References
LSO5-85-10-005, LSO5-85-10-5, NUDOCS 8511180483
Download: ML20138R188 (4)


Text

-_

/

UNITED $TATES 8

[g NUCLEAR REGULATORY COMMISSION s

WASHINGTON, D. C. 20655

,o

' October 1,1985 Docket No. 50-245 LS05-85-10-005 Mr. John F. Opeka, Senior Vice President Nuclear Engineering and Operations Northeast P!uclear Energy Company Post Office Box 270 Hartford, Connecticut 06141-0?70

Dear Mr. Opeka:

SUBJECT:

RADIOLOGICAL EFFLUENT TECHNICAL SPECIFICATIONS Re:

Millstone Nuclear Power Station, Unit No. 1 The Commission has issued the enclosed Amendment No.106 to Provisional Operating License No. DPR-21 for the Millstone Nuclear Power Station, Unit No. 1.

This amendment is in response to your application dated May 29, 1985.

This amendment deletes Appendix B in its entirety and provides new Appendix A Technical Specification sections defining limiting conditions for operation and surveillance requirements for radioactive liquid and neseous effluent monitoring; concentration, dose and treatment of licuit, and caseous wastes; and total dose.

It revises the Radiological Effluent Technical Specifications (RETS) to assure continuing compliance with Appendix I of 10 CFR Part 50. The procedures to be followed and the bases.

supporting the operation and surveillance requirements are identified in the licensee's Radiological Effluent Monitoring and Offsite Dose Calculation Manual (REMODCM) frevised by NNEC0 letters dated June 19 and August 13, 1985) accompanying the RETS. Also acceptable on an interim basis (until a staff position is established on 10 CFR Part 61) for use with the Millstone-1 Technical Specifications-is the reference document " Process Control Program" delineating the waste solidification process provided with the May 29, 1985 licensee submittal.

A Notice of Consideration of Issuance of Amendment to License and Proposed No Significant Hazards Consideration Determination and Opportunity for Heering related to the requested action was published in the Federal Register on August 14, 1985 (50 FR 32798). No coments or requests for hearing were received.

For administrative convenience we are enclosing a revised page 4 of DPR-21 showing the change made by the amendment.

P

v

.. t Mr. John F. Opeka

- 2.-

October 1,1985 A copy of our related Safety Evaluation along with the Technical Evaluation Report prepared in Franklin Research Center is enclosed. This action will appear in the Commission's hiweekly notice publication in the Federal Register. The license amendnert is effective on January 1, 1986.

Sincerely, John

i. Zwolinski, Chief Operauing Reactors Branch #5 Division of Licensing

Enclosures:

1.

Amendment No. 106 to License No. DPR-21 2.

Safety Evaluation cc w/ enclosures:

See next page 4

i 9

h l

g:

Mr..dehn F, Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. I cc:

Gerald Garfield, Esquire Kevin McCarthy, Director Day, Berry & Howard Radiation Control Unit Counselors at Law Department of Environmental City Place Protection 1

Hartford, Connecticut 06103-3499 State Office Building Hartford, Connecticut 06106 Edward J. Preczka Vice President, Nuclear Operations Northeast Utilities Service Company Post Office Box 270 Hartford, Connecticut 06141-0270 State of Connecticut Office of Policy and Management ATTN: Under Secretary Eneroy Division 80 Washington Street Hartford, Connecticut 06106 Peofonal Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Northeast Nuclear Energy Company ATTN: Superintendent Millstone Nuclear Power Station P. O. Box 128 Waterford, Connecticut 06385 Resident Inspector c/o U.S. NPC Pillstone Nuclear Power Station P. O. Box 811 Niantic, Connecticut 06357 First Selectman of the Town of Waterford Hall of Records 200 Boston Post Road i

Waterford, Connecticut 06385 i

,