Forwards Notice of Consideration of Issuance of Amend to Renew (Possession Only) License DPR-9 & Opportunity for Prior Hearing Re 850517 Request to Extend Expiration Date to 250320
ML20138P670
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 11/01/1985
From: Zwolinski J
Office of Nuclear Reactor Regulation
To: Jens W
DETROIT EDISON CO.
Shared Package
ML20138P672 List:
References
LSO5-85-11-003, LSO5-85-11-3, NUDOCS 8511070318
Download: ML20138P670 (4)


Text

-

Docket No. 50-16 W 011985 LS05-85-ll-003 Mr. Wayne H. Jens, Vice President Nuclear Operations Detroit Edison Company 6400 Porth Dixie Highway Newport, Michigan 48166

Dear Mr. Jens:

SUBJECT:

NOTICE OF OPPORTUfITY FOR PRIOR HEARING De:

Enrico Fermi Atomic Power Plant, Unit No. 1 The Cormission has requested the Office of the Federal Register to publish the enclosed " Notice of Consideration of Issuance of Arrendrent to Fecility Operating License and Opportunity for Prior Hearing." This notice reletes te your application for amendment to License No. DPR-9 dated May 17, 1985. The amendment would extend the expiration date of License No. DPR-9 for approxirately 40 years to March 20, 2025 consistent with the expiration date of the Fenni Unit flo. 2 license. The proposed extension would retain the possess-but-not-operate ccndition of the present license.

Sincerely, un., mal M DJ John A. Zwolinski, Chief Operating Reactors Branch #5 Division of Licensing

Enclosure:

DISTRIBUTION Notice Epocket F11e j JZwolirski flRC PDR OELD cc w/ enclosure:

Local PDR LHarmon See next page ORB #5 Reading OPA, CMiles HThompson ACRS (10)

CJamerson WJenes PErickson

(

DL:0RB#5 E DL: R #5 DL:0PB#5 OELD i CJamerson PErickson:tn J7wolinski CWoocWee l

10/E/85 '

10/3 /85 10/l /85 10/Q/85 8511070318 851101 PDR ADOCK 05000016 W

PDR

,-___.._.w

7590-01 6

j UNITED STATES NUCLEAR REGULATORY COMMISSION DETROIT EDISON COMPANY DOCKET NO. 50-16 NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT f

TO RENEW FACILITY (POSSESSION ONLY) LICENSE AND

^

OPPORTUNITY FOR PRIOR HEARING The Uni _d States Nuclear Regulatory Comission (the Comission) is l

l considering iss ance of an amendment to renew the Facility Possession Only License No. DPR-9 ssued to the Detroit Edison Company (the licensee), for the Enrico Fermi Ato ic Power Plant, Unit No.1, located in Monroe County, Michigan,$he facility h s been permanently shut down since 1973.

The amendment to Facility Lic se No. DPR-9 would renew License No. DPR-9 for a term of up to 40 years or f such lesser term as the Comission determines b,hJt+b

. VA

/

to be appropriate,in y i=

Comission's notice of proposed rulemaking

^

on decomissioning at 50 5600(February 11,1985). The licensee's

)

application for emendment dated May 17, 1985 requested renewal of the license for a full 40 years (to March 20, 202 during which time the licensee a

4 proposes to maintain the plant in the pr sent shutdown, safe storage mode after which all residual radioactivity wou be removed and the license teminated. All fuel has been removed from t facility site. A decommissioning plan for the reactor was filed w th the Atomic Energy Comission in 1973 and revised by current applicati n dated May 17, 1985, a

Prior to issuance of the proposed license renewa the Comission will have made findings required by the Atomic Energy Ac of 1954, as amended (the Act) and Comission's regulations.

i J

l

....~

. _. _ _. - ~.. _ ~..,... -.... - ~...., _.. -.. _ -,._

. -..., ~ _..

p anroy C

UNITED STATES 5

o,j s

. (

NUCLEAR REGULATORY COMMISSION t

.g wAsmNGTON, D. C. 20555 November 1, 1985 Docket No. 50-16 LS05-85-11 -003 Mr. Wayne H. Jens, Vice President Nuclear Operations Detroit Edison Company 6400 North Dixie Highway Newport, Michigan 48166

Dear Mr. Jens:

SUBJECT:

NOTICE OF OPPORTUNITY FOR PRIOR HEARING Re:

Enrico Femi Atomic Power Plant, Unit No.1 The Comission has requested the Office of the Federal Register to publish the enclosed " Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Prior Hearing." This notice relates to your application for amendment to License No. DPR-9 dated May 17, 1985. The amendment would extend the expiration date of License No. DPR-9 for approximately 40 years to March 20, 2025 consistent with the expiration date of the Femi Unit No..? license. The proposed extension would retain the possess-but-not-operate condition of the present license.

Sincer ly, I

9 a

John. Zwolinski, Chief 0,; era ing Reactors Branch #5 Division of Licensing

Enclosure:

Notice cc w/ enclosure:

See next page

i s

Detroit Edison Company cc:

Mr. Harry H. Voigt, Esq.

Ronald C. Callen LeBoeuf, Lamb, Leiby & MacRae Adv. Planning Review Section 1333 New Hampshire Avenue, N. W.

Michigan Public Service Commission Washington, D. C. 20036 6545 Mercantile Way P. D. Box 30221 John Flynn, Esq.

Lansing, Michigan 48909 Senior Attorney The Detroit Edison Company Regional Administrator, Region III 2000 Second Avenue U. S. Nuclear Regulatory Commission Detroit, Michigan 48226 799 Roosevelt Road Glen Ellyn, Illinois 60137 Mr. Dennis R. Hahn, Chief Nuclear Facilities and Environmental Monitoring Section Office Division of Radiological Health P. O. Box 30035 Lansing, Mi:higan 48909 Mr. Robert Woolley Acting Supervisor-Licensing The Detroit Edison Company Fermi Unit 2 6400 No. Dixie Highway Newport, Michigan 48166 Mr. Paul Byron U. S. Nuclear Regulatory Commission Resident Inspector's Office 6450 W. Dixie Highway Newport, Michigan 48166 i

Monroe County Office of Civil Preparedness 963 South Raisinville Monroe, Michigan 48161 4

F n

g------

~.,,,, -.,.

g ----.


+y--

-w---r-

-