ML20138M175

From kanterella
Jump to navigation Jump to search
Final Potential Deficiency Rept (Rdc 144(85)) Re Shop Welds in Containment Penetration Assemblies Mfg by Tube Turns,Inc. Initially Reported on 850731.Item Not Reportable Per 10CFR50.55(e)
ML20138M175
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 10/22/1985
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
(RDC-144(85)), PY-CEI-OIE-0121, PY-CEI-OIE-121, NUDOCS 8510310550
Download: ML20138M175 (5)


Text

,d THE CLEVELAND ELECTRIC ILLUMIN ATING COMPANY P O BOX 5000 - CLEVELAND. OHIO 44101 - TELEPHONE (216) 622-9800 - fLLUMIN ATING BLDG

- 55 PUBLIC SQUARE Ferving The Best t.ocation in the Nation MUFRAY R. EDELMAN VICE PRESIDENT NUCUAR October 22, 1985 PY-CEI/OIE 0121 L Mr. James G.

Keppler Regional Administrator, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE:

Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Tube Turns Nuclear Class I Plued Head Penetrations

[RDC 144 (85)]

Dear Mr. Keppler:

This letter is a final report pursuant to 10CFR50.55(e) concerning potentially deficient shop welds in containment penetration assemblies manufactured by Tube Turns, Inc. of Louisville, Kentucky.

Mr. James McCormick-Barger of your office was notified by telephone on July 31, 1985 by Mr. Paul Martin of The Cleveland Electric Illuminating Company (CEI) that this condition was being evaluated per Deviation Analysis Report 250 Tube Turns, Inc. was also notified.

An interim report was cubmitted on August 29, 1985.

We have determined that this condition does not constitute a significant deficiency por the requirements of 10CFR50.55(o).

Description of Potential Deficiency Flued heads are used to support and anchor proceso piping where it passes through a containment penetration.

For typical configurations, see the attached sketch.

During leak testing of the assemblion installed in Unit 1, leakage indications were identified in two (2) penetration assem-blies (P-410 and P-411).

In both inntances, the indicationn of leakage occurred at or near the ahop weld that the flued head to the proceca pipe.

These penetration connects assemblien, including the weld to the prococo piping, were supplied by Tube Turna, Inc. of Louluville, Kentucky, 8510310550 051022 QC.I 2ad1985 Il PDR ADOCK 05000440 v

6 PDR 1Ed}

Mr. James G. Koppler October 22, 1985 PY-CEI/OIE 0121 L As part of the investigation to determine the source of indications found during leak tests as described above, ultrasonic testing (UT) was used to perform a volumetric examination in the immediate area of concern.

This exam-ination identified ultrasonic indications which were not within acceptance criteria established for this type of examination by ASME Section III.

Because of this, the UT was performed on the flued head to process piping wold on all Class I penetration assemblies which were furnished by Tube Turns, Inc. for Unit 1.

As a result, thirteen (13) i Class 1 penetrations have been found to exhibit ultrasonic indications in excess of ASME criteria.

It must be noted that the applicable Construction Code for these flued head welds, ASME Section III/ Subsection NB, does not require UT examination.

Under the provisions of Subsection NB (Class 1 requirements), this weld is treated as a structural attachment to the piping pressure boundary.

As such, Article NB-5000 of Subsection NB requires that the welds be subjected to a liquid penetrant (LP) or magnetic particle (MP) examination.

UT examination is required by CEI to satisfy augmented In-Service Inspection (ISI) commitments.

This inspection results from a Standard Review Plan requirement (MEB 3-1), and not from an ASME Section XI ISI requirement.

All required ASME Section III examinations (liquid penetrant or magnetic particle testing) were performed by the manufacturer and accepted.

The assemblies are therefore Section III complete and were Code-stamped by the manufacturer.

l Conclusions of Evaluation In an effort to determine the source or cause of indications found during leak tests on penetration assemblien P-410 and P-411, the penetrations were flapper-wheeled and Icak tents were subsequently performed by two different ASME Certifi-cate holders.

Neither test identified any indications of leakage.

In addition, these areas were examined using liquid penetrant, magnetic particle and ultrasonic testing methods.

Again no indications were found that could be con-I nected to potential leakage.

We have therefore concluded that the original indications of leakage found during Icak testing were false.

Insofar as leak testing is concerned, we consider penetrations P410 and P411 to be acceptable.

The ultrasonic indications identified during the investiga-tion of leak testing results are considered an a separate problem.

Through detailed evaluation of UT data and physical examination of similar discontinuities in a duplicate Unit 2 assembly which was sectioned, we have determined that (1) the UT indications we have identified appear to result from slag inclusions, and, (2) the actual discontinuition are rela-tively small in relationship to the overall wold size.

L

Mr. James G. Keppler October 22, 1985 PY-CEI/OIE 0121 L In dealing with indications identified through performance of an examination over and above Section III requirements, we have chosen to utilize methods typically used for defect evaluation subsequent to construction completion, that is, fracture mechanics and fatigue analysis. This type of analysis is appropriate in this instance given the charac-ter and size of discontinuities and the potential for metallurgical degradation of material properties in effect-ing weld repairs.

This analysis has shown the penetration welds to be acceptable in their present condition.

We consider this approach to be consistent with sound engi-neering and industry practices.

Evaluation of the potentially affected Unit 2 penetrations will be completed on a schedule consistent with Unit 2 construction.

Analysis of Safety Implications As stated above, the thirteen Unit 1 penetration assemblies l

affected by the leakage and/or UT indications are consi-dered to be acceptable in their present condition.

In the case of the UT indications, our design agent, Gilbert Associates, working together with APTECH Engineering has performed fracture mechanics and fatigue analyses which show that the discontinuities identified do not affect the integrity of the flued head penetration assemblies.

Thus, we have concluded that if these problems had gone unde-tected, they would not have been detrimental to the safe operation of the Perry Nuclear Power Plant.

Please call if there are any questions.

Sincerely, its%4 [

Murray Edelman l

Vice President l

Nuclear Group I

HRE:sab j

Attachments i

l i

i i

k 1

i Mr. James G. Koppler October 22, 1985 l

PY-CEI/OIE 0121 L I

i i

cc:

Mr. J. A. Grobe

]

USNRC, Site Office (SBB50) 4 l

1 J. J. Stefano, Project Manager i

Licensing Branch No. 1 1

U.S. Nuclear Regulatory Commission f

Washington, D.C.

20555 i

I Director 4

Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission i

j Washington, D.C.

20555 i

i U.S. Nuclear Regulatory Commission Document Control Desk j

Washington, D.C.

20555

[

Records Center, SEE-IN Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 i

)

Atlanta, Georgia 30339 1

}

6 i

o 4

l l

i i

~!

I i

i L

a i

e o

S i

t

.2..g 1

r N N WDSA-1 mg, t

C..M:-

5'* D*m f1N.. : ', t, _

m_ _Z""'" '"hlO _ M

~

-=

( '

a---,

,-ww m-w-

_ i.

  • +-

~

~ ~ ' * '

', law aa-

~.

,..d..

eu

  • t m-a.a., n_

mas a MW 9M ag w gemmy

.T' h~,t=_

R:iT" - iff e a r"-@r"7,~~~ w.u-so ar mr.-

wm maa.,

n 1

=%

m 3,, 't a4gnm_, - - :=b j < ~r= =

- m l. : : r.

.; i;

\\,

[

~~'~ L - _ J

-a r

I sat Derra.

no,e 1

4

  • ii-fo i

s Weld Process Pipe SkT!"

isas Oswu

-=, w,

FT-iin_cr-g ~ sss ~

.._..__r r,

w r='~

A a/

,m

/

N==

w:

e.

.w..,

y Cont. Sleeve or Guard Pipe x

nsjgr mr

'~** ~

f-r FV.JHead

'"6M T _." '

<em DETAIL

!I I

I

)[

\\

I f 't EIN 5

I g'gygg w I

i I

W L

bI I

I I

I.

J gg ws'f.

i. G w'

su o.un.

A-VY

    • 5 swr rd ART seuCList Poet a PL ANT tal CLtyttamo SLICteeC ettunnematema ComPauf Typical Mech. Fenetration Detalls for Reactor Building Comptes