7, g q Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Dr. East Welch, Minnesota 55089 December 18,1996 U P Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos.50-282 License Nos.DPR-42 50-306 DPR-60 Submittal of Procedure for Unioadina TN-40 Cask Attached for the information of the NRC Staff is a copy of Prairie Island Procedure D95.2, "TN-40 Cask Unloading Procedure", Revision 2. This procedure is being provided to assist you in responding to the numerous questions being addressed to the NRC Staff with respect to unloading a TN-40 cask at Prairie Island.

Please be aware that while procedure D95.2 controls the cask handling activities necessary to unload a TN-40 spent fuel storage cask, it is only one of the procedures necessary to safely unload a cask. D95.2 is used in conjunction with several other site procedures, such as those controlling fuel handling, heavy loads, and radiation protection. Also, several Preventative Maintenance and Surveillance Procedures are  ;

used in the unloading of a TN-40 cask.

In this letter we have made no new Nuclear Regulatory Commission commitments. l If you have any questions related to the attached procedure, please contact Gene Eckholt (612-388-1121). i

/hr Michael D Wadley bN l

Plant Manager 1 ws Prairie Island Nuclear Generating Plant h j 9701030040 961218 1 PDR ADOCK 05000282 l P PDR j J

. 1 l

USNRC NORTHERN STATES POWdR COMPANY December 18,1996  :

Page 2  ;

)

c: Regional Administrator - Region Ill, NRC Senior Resident inspector, NRC NRR Project Manager, NRC NMSS Project Manager, NRC J E Silberg l

Attachment:

Procedure D95.2, "TN-40 Cask Unloading Procedure", Revision 2 4

4 4

l 1

2 a

a

.