ML20138E350

From kanterella
Jump to navigation Jump to search
Confirms Dcrdr Audit for Wk of 860127,per Discussion W/R Frisch Re Rescheduling.Audit Plan Transmitted on 850619 Remains Unchanged.Three Days of Appraisal & Exit Meeting on 860131 Scheduled
ML20138E350
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 12/06/1985
From: Zwolinski J
Office of Nuclear Reactor Regulation
To: Berry K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
References
NUDOCS 8512130426
Download: ML20138E350 (3)


Text

,

w, ' - -

v, ~

y

.  ? ,

t Docket No. 50-155 DEC o 61985 Mr. Kenne.th'T. Berry Directtr, Nuchar Licensing Consur;ers Power Company 1945 West Parnall Road Jackson, Michigan 49201

Dear Mr. Rerry:

1 \

SUBJECT:

IN-PROGRESS AUDIT FOR THE DETAILED CONTROL ROOM DESIGN REVIEW (DCRDR) SCHEDULE Re: Big Rock Point Plant As discussed duhing our telephone conversation with Mr. Ralph Frisch of

'> Consumers Power Company (CPC) on November 19, 1985, this letter serves to confirm that the DCRDR audit, previously scheduled for the week beginning December 2, 1985, as established in our letter to you dated July 26, 1985, has been rescheduled for the week beginning January 27, 1986. Current p plans for the DCRDR audit staff include approximately three days of appraisal P and an exit meeting with the Big Rock Point Plant staff the morning of January 31, 1986. The " audit plan" for the DCRDR, previously transmitted

( by letter to you on June 19, 1985, remains unchanged.

[

If you should have any questions regarding this schedule change, or the general contents of the audit, please contact Mr. T. S. Rotella, Big Rock

, .c 1 <

Point project manager.

Sincerely, a

,l I)( ,' John A. Zwolinski, Director

+ BWR Project Directorate #1 f

3 Division of BWR Licensing cc: See'next page-DISTRIBUTION fr . l E EEeE TITeJA LBeltracchi s NRC PGE SWiess*

^, N" LocalIDR MSrinivasan BWD#1 Rdg

. s HThompson

- OELD Lp pg21 26L852206 EJordan F CK 05000255 a- BGrimes PDR JPartlow TRotella 7 CJamerson

DBL:PD#n b( DBL:PD#1f//, DBL:PD#1 CJamerso TRottlla:tm JZwolinski le 12/$/85 l- 12/(6/85 3, 12/ 6 /85- l

.- j

_ l'

$ .N m *

'o,,. UNITED STATES I

, 8 o NUCLEAR REGULATORY COMMISSION '

% ,, # December 6, 1985 ,

Docket No. 50-155 l

Mr. Kenneth W. Berry ,

Director, Nuclear Licensing Consumers Power Company 1945 West Parnall Road Jackson, Michigan 49201

Dear Mr. Berry:

SUBJECT:

IN-PROGRESS AUDIT FOR THE DETAILED CONTROL ROOM DESIGN REVIEW (DCRDR) SCHEDULE ,

Re: Big Rock Point Plant As discussed during our telephone conversation with Mr. Ralph Frisch of Consumers Power Company (CPC) on November 19, 1985, this letter serves to confirm that the DCRDR audit, previously scheduled for the week beginning December 2,1985, as established in our letter to you dated July 26, 1985, has been rescheduled for the week beginning January 27, 1986. Current plans for the DCRDR audit staff include approximately three days of appraisal and an exit meeting with the Big Rock Point Plant staff the morning of January 31, 1986. The " audit plan" for the DCRDR, previously transmitted by letter to you on June 19, 1985, remains unchanged.

If you should have any questions regarding this schedule change, or tie * ,

general contents of the audit, please contact Mr. T. S. Rotella, Big Rock Point project manager.

Sincerely, fi John . Zwolinski, Director BWR P oject Directorate #1 Division of BWR Licensing cc: See next page 2 e I

s d ' < l

s . .' -

2 8

Mr. Kenneth W. Berry r Consumers Power Company Big Rock Point Plant CC:

Mr. Thomas A. McNish, Secretary i Consumers Power Company 212 West Michigan Avenue Jackson, Michigan 49201 '

Judd L. Bacon, Esquire '

Consumers Power Company 212 West Michigan Avenue Jackson, Michigan 49201 Big Rock Point Plant ATTN: Mr. David P. Hoffman Plant Superintendent Route 3 '

Post Office Box 591 Charlevoix, Michigan 49720 Mr. I. Lee Moerland i

Chairman, Board of Commissioners P. O. Box 218

Charlevoix, Michigan 49720 Office of the Governor ,

Room 1 - Capitol Building Lansing, Michigan 48913 Regional Administrator Nuclear Regulatory Commission, Region III

' 3 799 Roosevelt Road Glen Ellyn, Illinois 60137 Nuclear Facilities and Environmental Monitoring Section Office Division of Radiological Health P. O. Bcx 30035 -

Lansing,yichigan 48909 Resident Inspector >

Big Rock Point Plant i c/o U.S. NRC- s RR #3, Box 600 .

Charlevoix, Michigan 49720 <

, i S

}

1, 1 D } t

'. S

/, ,

s b

X _ - . . _. . . .