MONTHYEARIR 05000097/19992011999-08-0404 August 1999 Insp Repts 50-097/99-201 & 50-157/99-201 on 990426-30.No Violations Noted.Major Areas Inspected:Onsite Review of Selected Aspects of Operations Program,Organizational Structure & Review & Audit Program IR 05000097/19970011997-05-0505 May 1997 Insp Repts 50-097/97-01 & 50-157/97-01 on 970407-10.No Violations Noted.Major Areas Inspected:Operations, Operational Status of Facilities & Equipment,Operations Procedures & Documentation & Operator Training IR 05000157/19970011997-04-24024 April 1997 Correction to Insp Rept 50-157/97-01 Issued Incorrectly as 50-197/97-01 ML20128N3831996-10-0707 October 1996 NRC Operator Licensing Exam Rept 50-157/OL-96-01 (Including Completed & Graded Tests) for Tests Administered on 960926. Candidate Passed Exam & Requirement to Take Written Exam Waived,Per 10CFR55.47 ML20059K8901993-12-23023 December 1993 Exam Rept 50-097/OL-93-02 & 50-157/OL-93-02 on 931004-06. Exam Results:Three SRO Passed Exams IR 05000157/19930021993-12-0101 December 1993 Insp Rept 50-157/93-02 on 931108-10.No Violations Noted. Major Areas Inspected:Implementation of Emergency Plan, Procedures,Facilities & Equipment & Drills IR 05000157/19900031990-11-19019 November 1990 Exam Rept 50-157/90-03OL on 901023-24.Exam Results:All Candidates Passed All Portions of Exam IR 05000157/19890011989-05-11011 May 1989 Insp Rept 50-97/89-01 & 50-157/89-01 on 890425-26.No Violations Noted.Major Areas Inspected:Operation & Records of Triga & Zpr Reactors IR 05000097/19870011987-10-28028 October 1987 Insp Repts 50-157/87-01 & 50-097/87-01 on 870923-24.Major Areas Inspected:Operation & Records of Reactors.Problems Continued Re Licensed Operator Requalification Exams & Annual Operations Audit.Annual Audit Needed to Be Upgraded IR 05000157/19860011986-11-25025 November 1986 Exam Rept 50-157/86-01 on 861015-16.Exam Results:Candidate Passed Both Written & Oral Exams IR 05000097/19850011985-09-18018 September 1985 Safety Insp Repts 50-097/85-01 & 50-157/85-01 on 850422-24. Violation Noted:Licensed Operator Requalification Testing Not Given on Annual Basis.Unresolved Items Noted Involved Annual Emergency Drill & Operations Audit ML20138D1931985-09-18018 September 1985 Notice of Violation from Insp on 850422-24 IR 05000097/19850021985-06-14014 June 1985 Insp Repts 50-097/85-02 & 50-157/85-02 on 850520-23.No Violation Noted.Major Areas Inspected:Radiation Protection & Radwaste Mgt Programs,W/Emphasis on Exposure Control, Training & Procedures & Equipment 1999-08-04
[Table view] |
Text
_
APPENDIX A NOTICE OF VIOLATION Cor nell University Docket No. 50-157 Ward Laboratory of Nuclear Engineering License No. R-80 As a result of the inspection conducted on April 22-24, 1985, and in accordance with the NRC Enforcement Policy (10 CFR 2, Appendix C), the following violation was identified:
10 CFR 55, Appendix A requires that research reactors shall have requalifica-tion programs for licensed senior reactor operators. The licensee's Requali-fication Program for. Licensed Operators states that an annual written requali-fication test will be given.
Contrary to the above, on April 2;2, 1985, written requalification tests had been given to one senior operator on February 28, 1982 and April 22, 1985, and to another senior operator on February 26, 1982 and December 20, 1983.
These frequencies exceed the required annual test frequency.
This is a Severity Level V Violation (Supplement I.D).
Pursuant to the provisions of 10 CFR 2.201, Cornell University is hereby required to submit to this office within thirty days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including: (1) the cor-rective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full com-pliance will be achieved. Where good cause is shown, consideration will be given to extending this response time.