ML20138B482

From kanterella
Jump to navigation Jump to search
Certifies That Item 1.a of Attachment 1 to License NPF-46 for Initial Entry Into Mode 4 Completed.Surveillance Tests & Preoperational Testing to Demonstrate That Sys Meets Tech Spec Requirements Also Completed
ML20138B482
Person / Time
Site: Palo Verde 
Issue date: 03/10/1986
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-35490-EEVB, NUDOCS 8603250079
Download: ML20138B482 (1)


Text

A HECEIVED N=c Arizona Nuclear Power Project 686 hMR 12 pf; g P O BOX 52034 e PHOENIX, ARIZONA 85072-2034 ANPP-35490-EEVB/JGH-91.03 REG:0uv m March 10, 1986 Mr. John B. Martin Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission - Revion V 1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Subject:

Certification of the Operability of All Required Systems for Initial Entry Into GO-S M Mode 4 File No. 86-056-026

Reference:

PVNGS Unit 2 Operating License NPF-46 Dear Mr. Martins As required by the Palo Verde Nuclear Generating Unit 2 Operating License, NPF-46, I am hereby certifying that item 1.a of Attachment 1 to the license has been completed for the initial entry into Mode 4.

The operability of systems required for Mode 4 has been demonstrated by successfully meeting the acceptance criteria in the PVNGS Technical Specifications.

This has been accomplished by the completion of the applicable surveillance tests or by pre-operational testing, which i

verifies the meeting requirements of the Technical Specification and which were performed within the required surveillance interval or by operability as demonstrated for Modes 5 and 6.

Very truly yours, I

Ch Od E. E. Van Brunt, Jr.

Executive Vice Presidert Project Director EEVB/JRB/1f cc:

R. Zimmerman A. Gehr 8603250079 860310 ga PDR ADOCK 05000529 4