Notice of Violation from Insp on 850625-0903
ML20138A702
Person / Time
Site: Callaway, 05000625 Ameren icon.png
Issue date: 09/25/1985
From: Chrissotimos N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20138A698 List:
References
50-483-85-16, NUDOCS 8510080614
Download: ML20138A702 (1)


Text

,

-

.

Appendix NOTICE OF VIOLATION Union Electric Company Docket No. 50-483 As a result of the inspection conducted on June 25 through September 3, 1985, and in accordance with the General Policy and Procedures for NRC Enforcement Actions 10 CFR Part 2, Appendix C, the following violation was identified:

Technical Specification 3.2.1, Axial Flux Difference (AFD), Action a. states, in part:

"With the indicated AFD outside of the required target band and with THERMAL POWER greater than or equal to 90% of RATED THERMAL POWER, within 15 minutes, either: Restore the indicated AFD to within the above required target band limits, or Reduce THERMAL POWER to less than 90% of RATED THERMAL POWER."

Contrary to the above, on August 17, 1985, while at 90% to 100% reactor Thermal Power, the reactor was operated beyond the allowable target band for an accumulated time of 141 minute This is a Severity Level IV violation (Supplement 1).

The inspection showed that licensee action had been taken to correct the violation and to prevent recurrence. Consequently, no reply to this violation is required and we have no further questions regarding this ite Dated VbS/95 $h4cb N. J. Chrisfotimbs, Chief M

Reactor Projects Branch 2 8510080614 850927 PDR ADOCK 05000483 G PDR