ML20137Y092

From kanterella
Jump to navigation Jump to search
Notification of 860310 & 11 Meetings W/Util in Salem & Lower Alloways Creek Township,Nj,Respectively,To Discuss Readiness for Low Power Ol.Agenda Encl
ML20137Y092
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 03/05/1986
From: Wagner D
Office of Nuclear Reactor Regulation
To: Adensam E
Office of Nuclear Reactor Regulation
References
NUDOCS 8603120131
Download: ML20137Y092 (3)


Text

rj ---

'NAR 5 BBS Docket No.: 50-354 MEMORANDUM FOR: Elinor G. Adensam. Director-BWR Project Directorate No. 3 Division of BWR Licensing FROM: David H. Wagner, Project Manager BWR Project Directorate No. 3 Division of BWR Licensing

SUBJECT:

FORTHCOMING OFFICE OF NUCLEAR REACTOR REGULATION MANAGEMENT VISIT TO THE HOPE CREEK GENERATING STATION SITE DATE & TIME: Monday, March 10, 1986 4:30 p.m. - 6:30 p.m.

Tuesday, March 11, 1986 8:00 a.m. - 2:30 p.m.

LOCATION: March 10, 1986 - PSE8G Training Center 244 Chestnut Street Salem, New Jersey March 11, 1986 - Hope Creek Site Lower Alloways Creek Township, New Jersey PURPOSE: TodeterminethereadinessofHopeCrgkforalow-power operating license (Agenda enclosed). -

PARTICIPANTS: NRC U""~Eisenhut S. Black R. Bernero D. Wagner E. Adensam W. Borchardt G. Lainas R. Vollmer G. Hulman S. Varga W. Russell PSESG E" Treston, et al.

Odsinal signed by David H. Wagner, Project Manager BWR Project Directorate No. 3 Division of BWR Licensing

Enclosure:

As stated cc: See next page M See footnote 1 of the Agenda

-3: DBL DW (.

-3: fDBL agner/mn EAdprsam 3/5786 3/ 6 /86

$'$o$

A 7

ENCLOSURE AGENDA FOR MANAGEMENT SITE VISIT HOPE CREEK GENERATING STATION Monday, March 10,19861/

4:30 p.m.'- 5:00 p.m. NRC and PSEAG Management Introductions 5:00 p.m. - 6:00 p.m. Simulator Exercise 6:00 p.m. - 6:30 p.m. Training Center Tour Tuesday March 11,19861/

8:00 a.m. - 12:00 p.m. Meeting Discussions / Presentations Construction readiness Organization, staffing, training Operational experience / personnel qualifications Operational readiness / procedures Lessons learned from other operating plant experiences Preoperational Testing /Startup Testing Technical Specification certification status Quality Assurance operation procram implementa11on

  • Performance reviews ( IDVP, INPO, etc.)

12:00 p.m. - 12:30 p.m. Lunch El 12:30 p.m. - 2:00 p.m. SiteTourEl 2:00 p.m. Concluding Remarks by NRC and PSEAG 2:30 p.m. Meeting Adjourned 4

1/ Attendance for the simulator exercise and the site tour is limited to NRC and PSE8G personnel.

El The tour will consist of several groups inspecting various areas of the plant. ,PSE8G should plan to provide an escort for each group.

El PSEAG is requested to provide a room to enable the NRC to conduct a

! working meeting during lunch. Lunch will be available for purchase at a nominal fee.

1 l

l l

o' MEETING NOTICE DISTRIBUTION NRC Participants Local PDR D. Eisenhut PRC System R. Bernero BWD #3 r/f E. Adensam ORAS G. Lainas H. Denton ' G. Hulman OPA W. Russell N. Olson-Attorney, OELD E. Jordan B. Grimes J. Partlow (Emergency Preparedness Only)

Receptionist (Only if meeting is held in Bethesda)

Project Manager D. Wagner E. Hylton bec: Applicant & Service List ,

i

.