Forwards marked-up Const Status Rept for Period Ending 851231
ML20137W369
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 02/14/1986
From: Devincentis J
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
To: Noonan V
Office of Nuclear Reactor Regulation
References
SBN-946, NUDOCS 8602200124
Download: ML20137W369 (7)


Text

.

SEABROOK STATION Engineering Office i

Pub 8c SeMce of New Hampshire Now Hampshire Yonkee Division February 14, 1986 SBN-946 T.F.

B4.4.2 United States Nuclear Regulatory Commission Washington, DC 20555 Attention:

Mr. Vincent S. Noonan, Project Director PWR Project Directorate No. 5

References:

(a) Construction Permits CPPR-135 and CPPR-136, Docket Nos. 50-443 and 50-444

Subject:

Construction Status Report; Seabrook Station, Units 1 and 2

Dear Sir:

Enclosed, please find the Construction Status Report for the period ending December 31, 1985.

Very truly yours, k

t&

John DeVincentis, Direc+.or Engineering and Licerslag

.cc: Atomic Safety and Licensing Board Service List 8602200124 e60214 ADOCK 0 % 4]3 PDR R

\\

D P.O Box 300 Soobrook.NH03874 Torophone(603)474 9521 1

William S. Jordan, III Donald E. Chick Diane Curran Town Manager Harmon, Weiss & Jordan Town of Exeter 20001 S. Street, N.W.

10 Front Street Suite 430 Exeter, NH 03833 Washington, D.C.

20009 Brentwood Board of Sele'etmen Robert G. Perlis RED Dalton Road Office of the Executive Legal Director Brentwood, NH 03833 U.S. Nuclear Regulatory Commission Washington, DC 20555 Richard E. Sullivan, Mayor City Hall Robert A. Backus, Esquire Newbu rypo r t, MA 01950 116 Lowell Street P.O. Box 516 Calvin A. Canney Manc hester, NH 03105 City Manager City Hall Philip Ahrens, Esquire 126 Daniel Street Assistant Attorney General Portsmouth, NH 03801 Augusta, ME 04333 Dana Bisbee, Esquire Mr. John B. Tanzer Assistant Attorney Gene ral Designated Representative of Office of the Attorney General the Town of Hampton 206 State House Annex 5 Morningside Drive Concord, NH 03301 Hampton, NH 03842 Anna Verge, Chairperson Roberta C. Pevea r Boa rd of Selec tmen Designated Representative of Town Hall the Town of Hampton Falls South Hampton, NH 03827 Drinkwater Road Hampton Falls, NH 03844 Patrick J. McKeon Selectmen's Office M rs. Sandra Gavutis 10 Central Road Designated Representative of Rye, NH 03870 the Town of Kensington RFD 1 Carole F. Kagan, Esqui re East Kingston, NH 03827 Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Jo Ann Shotwell, Esquire Washington, DC 20555 Assistant Attorney General Environmental Protection Bureau Mr. Angi Machiros Department of the Attorney General Chairman of the Board of Selectmen One Ashburton Place, 19th Floor Town of Newbury Boston, MA 02108 Newbu ry, MA 01950 Senator Cordon J. Humphrey Town Manager's Office U.S. Senate Town Hall - Friend St reet Washington, DC 20510 Amesbury, MA 01913 (ATTN Tom Burack)

Senator Cordon J. Humphrey Diana P. Randall 1 Pillsbury Street 70 Collins Street Concord, NH 03301 Seabrook, NH 03874 (ATIN: Herb Boynton)

Corctruction St tus Report Paga No. 2-100 I L-S t -of Seabrook Stctin 1 Nuciscr Power Planta Stctua As Cf: 4DF-3JR)f)

Plant Characteristics:

Key Personnel:

Docket No.:

05000443 Corporate

Contact:

R. J. Harrison, President and Chief Executive Officer CP No. and Date Issued:

CPPR-135/07-07-76 Corporate Address:

1000 Elm Street Mancheater, New Hampshire 03105 CP Erpiration Date:

06-30-86 Corporate Telephone No.: (603) 669-4000 Applicant:

Public Service Of New Hampshire Plant Location:

10 Mi. South of Portsmouth, NH IE Region:

I AE:

United Engineers & Constructors NRC LPM:

V. Nerses NSSS:

Westingho use IE Project Inspector Constructor:

United Engineers & Constructors IE Resident Inspector A. C. Cerne Reactor Type:

PWR DER (NWE):

1198 Fuel Load Date Changes Inspection Status:

As Reported By Utility:

"'****b 8" Octg@

TimePeriod/

JuJ,p 1985 To e--*-

' - 1985 Repor t Beg. Date End Date Report New Reason For Change

--Number Of Insp.

Of Insp.

Date Schedule Reported By Utility

.p.

(~~ 5-0 7-5

-0 8

09-06-77 09-01-82 Delays Due To EPA Reversal of Previous y

I gypMr)hl Approval of Once Through Circulating 8 1 85 07 6-Water System and Subseq. NRC Withdrawal 5-07 0 27 5 8 21

-08 5 7-

-8 Of Const. Permit, and Time Req. to Remobilize 5-7-

-85 07 6-5' 11-0*-73 01-01-83 Schedule Re-evaluation 8 23 08 0 -0

)

04-04-8) 11-30-83 schedule Re-evaluation 11-30-82 09-30-84 Schedule Re-evaluation 09-25-84 04-30-86 Schedule Re-evaluation Inspection Reports Are Available At Local PDRs.

Incorporate Impact Of Construction Suspension And Cash Restrictions in 1984 07-24-85 06-30-86 Schedule Re-evaluation Local Public Document Room:

Exeter Public Library Front Street Exeter, New Hampshire 03883

.4..

8 Og INSERT " A" 4.

REPORT BEGINNING DATE END DATE OF NUMBER OF INSPECTION INSPECTION 85-18 06-10-85 06-14-85 85-24 09-30-85 10-04-85 85-25 08-28-85 10-18-85 85-26 09-23-85 09-27-85 85-27 10-16-85 10-18-85 85-28 10-16-85 10-18-85 85-29 11-04-85 11-08-85 85-30 10-28-85 11-27-85 85-31 10-19-85 12-03-85 85-32 12-09-85 12-13-85 85-33 12-11-85 12-13-85 l

1 i

I l'

T Construction Status Report Page No. 2-120 l E* 3lm65 Seabrook Station 1 Nuclear Power Plants Status As Of: d3RIURUPf4 Construction Status:

Applicant's Current Estimated Fuel Loading Date:

06-30-86 Applicants Construction Completion Estimate As Defined Applicant's Previous Estimated Puel Loading Date:

04-30-86 In CP: (Earliest) February 1979 Applicant's Estimated Fuel Loading Date At (Latest) June 1986 CP Issuance:

08-01-81 Applicant's Current Estimated Commercial Operation Date:

10-31-86 Current Estimated Percent Construction Complete:,$W95*N Comments Regarding Current Construction Status:

Es timated Actual Estimated Actual Estimate Start Start Completion Completion

% Complete Mobilize and Prepare Site:

07-76 08-77 100%

Picce Structural Concrete:

09-77 04-86 99%

Iectall Reactor Pressure Vessel:

05-81 05-81 100%

Icatall Large Bore Process Pipe:

10-79 02-86 98%

Install Large Bore Pipe Hangers, Restraints, and Snubbers:

10-79 02-86 SJ4b 9d */e Inctall Small Bore Pipe:

09-80 02-86 JHHt 917'e lectall Cable Tray:

09-79 02-86 99%

Icctall Exposed Metal Conduit:

04-79 02-86 Set *9STe lectall Power, Control, Instrumentation, and Security Cable:

05-81 02-86 9tt 9ad 9'.

Iectall Electrical Terminations:

06-81 02-86 4HHb 918f.

Conduct Reactor Cold Hydrostatic Test:

03-85 04-85 100%

Conduct Hot Functional Test:

.14-0S 10-8r 44-efir fi-8 F 4 100 %

Conduct PREOP and Acceptance Testa Necessary For Fuel Load:

11-82

~

04-86 244P 4 8 8/.

?-

Construction Status Report Page No. 2-102 '8 1 - 58 Seabrook Station 2

-Nuclear Power Plants Status As Of: @

Plant Characteristics:

Key Personnel:

Dock 2t No.:

05000444 Corporate

Contact:

R. J. Harrison, President and Chief Executive Officer CP No. and Date Issued:

CPPR-136/07-07-76 Corporate Address:

1000 Elm Street Manchester, New Hampshire 03105 CP Expiration Date:

10-31-88 Corporate Telephone No.: (603) 669-4000 Applicant:

Public Service Of New Hampshire Plant Location:

10 Mi. South of Portsmouth, NH IE Region:

I AEt United Engineers & Constructors NRC LPM:

V. Nerses NSSS:

Westinghouse IE Project Inspector Constructor United Engineers & Constructors IE Resident Inspector A. C. Cerne Reactor Type:

PWR DER (MIE):

1198 Fuel Load Date Changes

, inspection Status:

As Reported By Utility:

Time Period

_N 8185 % betm BG1t 6905' R3 port Beg. Date End Date Report New Reason For Change Number Of Insp.

Of Insp.

Date Schedule Reported By Utility

[15 02 8/16/e5 lope /8f 09-06-77 09-01-84 Delays Due To EPA Reversal of Previous Approval Of Once Through Circulating 6f-03 81/4l85 g)3.l gL Water System and Subseq. NRC Withdrawal Of Const. Permit, and Time Req. To Remobilize 11-08-78 11-01-84 Schedule Re-evaluation 04-04-81

.02-28-86 Schedule Re-evaluation Inspection Reports Are Available At Local PDRs.

11-30-82 12-31-86 Schedule Re-evaluation 06-20-83 04-30-87 Schedule Re-evaluation 10-31-84 N/A Indeterminate Status Locc1 Public Doctment Room:

Ex2ter Public Library Pront Street Ex2ter, New Hampshire 03883 i

I J

Construction Status Report Page No. 2-122 _I E W-08 Seabrook Station 2 Nuclear Power Plants Status As Of: C09-3df-a D -

Construction Status:

Applicant's Current Estimated Puel Loading Date:

Applicants Construction Completion Estimate As Defined Applicant's Previous Estimated Fuel Loading Date:

04-30-87 In CP: (Earliest) January 1981 Applicant's Estimated Fuel Loading Date At 10-01-83 (Latest) October 1988 CP Issusace:

Applicant's Current Estimated Commercial Operation Date:

Current Estimated Percent Construction Complete: 24%

Comments Regarding Current Construction Status:

Indeterminate Estimated Actual Estimated

  • Actual Estimate Start Start Completion Completion

% Complete Mobilize and Prepare Site:

07-76 08-77 100%

Place Structural Concrete:

08-81 69%

Install Reactor Pressure Vessel:

10-83 12-83 100%

Install Large Bore Process Pipe:

09-82 4%

Install Large Bore Pipe Hangers, Restraints, and Snubbers:

09-82 3%

Install Small Bore Pipe:

0%

Install Cable Tray:

0%

Install Exposed Metal Conduit:

0%

Install Power, Control, Instrumentation, and Security Cable:

0%

Install Electrical Terminations:

0%

Conduct Reactor Cold Hydrostatic Test:

0%

Conduct Hot Functional Test:

0%

a Conduct PREOF and Acceptance Tests Necessary For Fuel Ioad:

0%

61:tdeterminate e

mwe 4

^"