Monthly Operating Rept for Nov 1985
ML20137V523
Person / Time
Site: Millstone Dominion icon.png
Issue date: 11/30/1985
From: Newburgh G, Romberg W
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
MP-8479, NUDOCS 8602190599
Download: ML20137V523 (4)


Text

-T ".

tK AVERAGE DAILY UNIT POWER. LEVEL DOCKET NO. 50-245 UNIT Millstone 1 DATE 851210 COMPLETED.BY G. Newburgh TELEPHONE (203) 447-1791 Ext. 4400 MONTH NOVEMBER 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL.

(MWe-Net)

(MWe-Net) 1 S/D 17 S/D 2

S/D 18 S/D 3

S/D 19 S/D 4

S/D 20 S/D 5

S/D 21 S/D G

S/D 22 S/D 7

S/D 23 S/D 8

S/D 24 S/D 9

S/D 25 S/D 10 S/D 26 S/D 11 S/D 27 S/D.

1 12 S/D 28 S/D 13 S/D 29 S/D S' D 14 S/D 30

/

15 S/D 31 N/A 16 S/D 4

INSTRUCTIONS 1

l On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

l 21f& f 5

-$6 a

i \\ -.

/

c.

[s OPERATING DATA REPORT DOCKET NO. 50-245 DATE 851210 COMPLETED BY G. Newburgh TELEPHONE (203) 447-1791 Ext. 4400 OPERATING STATUS 1.

Unit Name: Millstone Unit 1 Notes 2.

Reporting Period: November 1985 3.

Licensed Thermal' Power (MWt): 2011.

4.

Nameplate Rating (Gross MWe): 662 5.

' Design Electrical Rating (Net MWe): 660 6.

Maximum Dependable Capacity (Gross MWe): 684 7.

Maximum Dependable Capacity (Net MWe)i 654 8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, If Any (Net MWe): N/A 10.

Reasons For Restrictions, If Any:

N/A This Month Yr.-to-Date Cumulative

11. Hours In Reporting Period 720 8016 131544 12.

Number Of Hours Reactor Was Critical 0

7065.9 100820.3 13.

Reactor Reserve Shutdown Hours 0

58.7 2834.5 14.

Hours Generator On-Line

~

0 7050.6 97987.1

15. Unit Reserve Shutdown Hours 0

67.2 93.7

16. Gross Thermal Energy Generated (MWH) 0 13870011 180278280
17. Gross Elec. Energy Generated (MWH) 0 4689600 60586296
18. Net Electrical Energy Generated (MWH) 0 4481586 57785746
19. Unit Service Factor 0

88.0 74.5

20. Unit Availability Factor 0

88.8 74.6

21. Unit Capacity Factor (Using MDC Net) 0 85.5 67.2 22.

Unit Capacity Factor (Using DER Net) 0 84.7 66.6 23.

Unit Forced Outage Rate 0

1.4 12.4 24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

N/A 25.

If Shut Down At End Of Report Period, Estimated Date of Startup: December 16, 1985~

26.

Units In Test Status (Prior to Commerciel Operation):

Forecast Achieved' INITIAL CRITICALITY INITIAL ELECTRICITY N/A COMMERCIAL OPERATION L.

DOCKET NO. 50-245 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Millstone 1 DATE 851210 COMPLETED BY G. Newburgh REPORT MONTH NOVEMBER 1985 TELEPHONE (203) 447-1791 Ext. 4400 1

2 No.

Date Type Duration Reason Method of Licensee Systeg Compogent Cause & Corrective (Hours)

Shutting Event Code Code Action to 3

Down Reactor Report #

Prevent Recurrence 9a 851201 S

720 C

4 N/A N/A N/A Refueling Outage.

1 2

3 4

F:

Forced Reason:

Method:

Exhibit G - Instructions S:

Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continued from (NUREG-0161)

E-Operator Training & License Examination previous month F-Administrative 5-Power Reduction 5

G-Oper:tional Error (Explain)

(Duration = 0)

Exihibit 1 - Same Source H-Other (Explain) 6-Other (Explain) e m

O c

General Offices '* Selden Street. Berlin Connecticut J

P.O. BOX 270

.a w on. %.ca,,.

HARTFORD. CONNECTICUT 06141-02/0 a=

(203) 666-6911 g

g g

w =_

December 12, 1985 MP-8479 Director, Office of Resource Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Reference:

Provisional License DPR-21 Docket No. 50-245

Dear Sir:

In accordance with Millstone Unit 1 Technical Specification 6.9.1.6, the following monthly operating data report for Millstone Unit 1 is enclosed. One additional copy of the report is enclosed.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY NA%

W. D. Ro erg Station Superintendent Millstone Nuclear Power Station WDR/GSN:dlc

Enclosures:

(3) cc: Director, Office of Inspection and Enforcement, Region I Director, Office of Inspection and Enforcement, Washington, D. C. (10)

U. S. Nuclear Regulatory Commission, c/o Document Management Branch, Washington, D.C. 20555

'\\'

-,