Text
7 UB 10 %
Docket No.:
STN 50-455 Mr. Dennis L. Farrar Director of Nuclear Licensing Commonwealth Edison Company Post Office Box 767 Chicago, Illinois 60690
Dear Mr. Farrar:
SUBJECT:
BYRON 2 CONSTRUCTION PERMIT EXPIRING APRIL 1, 1986.
By telephone conversation on January 30, 1986, I discussed with K.
Dinger of your staff that the Construction Permit for Byron Station, Unit 2, will expire on April 1, 1986.
Since your latest fuel load estimate is October 15, 1986, it appears that you will have to file an application for renewal of the Construction Permit.
In accordance with 10 CFR Section 2.109, this renewal application must be filed at least 30 days prior to the expiration of the existing license. Thus, your renewal application for the Byron 2 Construction Permit must be filed no later than March 2, 1986.
Leonard Olshan, Project Manager PWR Project Directorate #5 D; vision of PWR Licensing-A Distribution: -
Docket file NRC PDR Local PDR PD#5 Reading File T. Novak OELD E.~ Jordan B. Grimes J. Partlow L. Olshan M. Rushbrook ACRS (10)
E.
Christenbury
)
AWR-A/PD#5 PWR-A/PD-f g1'01shan VNoonan 7 /(o /86
/g/86 hhk A
5 PDR
p arrg#
0,,
UNITED STATES g'
g NUCLEAR REGULATORY COMMISSION O
j WASHINGTON, D. C. 20555 4....
M 10 m Docket No.:
'STN 50-455 Mr. Dennis L. Farrar Director of Nuclear Licensing Commonwealth Edison Company Post Office Box 767 Chicago, Illinois 60690
Dear.Mr. Farrar:
SUBJECT:
BYRON 2 CONSTRUCTION PERMIT EXPIRING APRIL 1, 1986.
1 By telephone conversation on January 30, 1986, I discussed with K.
Dinger of your staff that the Construction Permit for Byron Station, Unit 2, will expire on April 1,1986.
Since your latest fuel load estimate is October 15, 1986, it appears that you will have to file an application for renewal of the Construction Pennit.
In accordance with 10'CFR Section 2.109, this renewal application must be filed at least 30 days prior to the expiration of the existing license. Thus, your renewal application for the Byron 2 Construction Permit must be filed no later than March 2,
i l
7 WB 10 m Mr. Dennis L. Farrar Byron Station Comonwealth Edison Company Units 1 and 2 cc:
Mr. William Kortier Ms. Diane Chavez Atomic Power Distribution 528 Gregory Street Westinghouse Electric Corporation Rockford, Illinois 61108 Post Office Box 355 Pittsburgh, Pennsylvania 15230 Regional Ac.ministrator, Region III U. S. Nuclear Regulatory Comission Michael Miller 799 Roosevelt Road Isham, Lincoln & Beale Glen Ellyn, Illinois 60137 One First National Plaza 42nd Floor Joseph Gallo, Esq.
Chicago, Illinois 60603 Isham, Lincoln & Beale Suite 840 Mrs. Phillip B. Johnson 1120 Connecticut Avenue, N.W.
1907 Stratford Lane Washington, D. C.
20036 Rockford, Illinois 61107 Douglass Cassel, Esq.
Dr. Bruce von Zellen 109 N. Dearborn Street Department of Biological Sciences Suite 1300 Northern Illinois University Chicago, Illinois 60602 DeKalb, Illinois 61107 Ms. Pat Morrison Mr. Edward R. Crass 5568 Thunderidge Drive Nuclear Safeguards & Licensing Rockford, Illinois.61107 Sargent & Lundy Engineers 55 East Monroe Street Ms. Lorraine Creek Chicago, Illinois 60603 Rt. 1, Box 182 Manteno Illinois 60950 Mr. Julian Hinds U. S. Nuclear Regulatory Commission Byron / Resident Inspectors Offices 4448 German Church Road i
Byron, Illinois 61010 Mr. Michael C. Parker, Chief l
Division of Engineering j
Illinois Department of l
Nuclear Safety 1035 Outer Park Drive l-
. Springfield, Illinois 62704 l
.