Discusses Results of 851025 Meeting at Region I Ofc to Review Status of Order Modifying License Based on Final Radiation Protection Oversight Committee Rept.Committee Will Continue to Function During 1986 Outage & Rept Monthly
ML20137S983
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 11/22/1985
From: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Selman M
CONSOLIDATED EDISON CO. OF NEW YORK, INC.
References
NUDOCS 8512060345
Download: ML20137S983 (2)


Text

___ _ _ _ _ . _ _ _ _ _

NOV 2 21985 Docket No. 50-247 Consolidated Edison Company of New York, Inc.

ATTN: Mr. Murray Selman Vice President Indian Point Station Broadway and Bleakley Avenue Buchanan, New York 10511 i

Gentlemen:

On October 25, 1985, a meeting was held at the NRC Region I office between you and members of your staff, and Dr. R. Bellamy, Chief, Emergency Preparedness and Radiological Protection Branch and representatives of this office. The purpose of this meeting was to review the status of Order Modifying License issued Septem'era 27, 1984, in light of your Final Radiation Protection Over-sight Committee Report dated September 11, 1985. This report was addressed in our letter dated October 22, 1985, which also identified the agenda for the meeting.

Based on our discussions, we understand the following:

1. The Radiation Protection Oversight Committee (RP0C) will continue to function throughout the duration of the 1986 Outage and will continue to report at least monthly to the Vice President - Nuclear, who will provide the reports to the Regional Administrator on a monthly basis.
2. Efforts have been initiated to amend the charter of.the Radiation Safety Sub-Committee (RSSC) to function in a manner similar to the RP0C. Such 0.ction is expected to be completed by June 1986.
3. A plan for maintaining the effectiveness of the radiation protection upgrade program as described in the meeting will be documented and submitted to the Regional Administrator prior to the commencement of the outage.
4. The independent review of program status and capability as performed by Impell Corporation will be made available for NRC review upon completion of the report. Such report completion is expected by November 22, 1985.

If our understanding is not correct, please notify this office within seven (7) days from the date of this letter.

8512060345 851122 l' d PDR ADOCK 05000247 F PDR

'f' 0FFICIAL RECORD COPY ,

. i

F.

, t" Consolidated Edison Company of 2 New York, Inc.

It is our intent to perform an in-depth appraisal of your radiation protection program upon completion of the 1986 outage. The results of this appraisal will be used as a basis for determining the success of your efforts relative to the Order Modifying License.

Thank you for your cooperation.

Sincerely, Origrnal signed by Tho:nas E. Murler Thomas E. Mud ey Regional Administrator t

cc:

J. D. O'Toole, Vice President, Nuclear Engineering, Quality Assurance and Reliability M. Blatt, Director, Regulatory Affairs F. Hatra, Resident Construction Manager R. L. Spring, Nuclear Licensing Engireer Brent L. Brandenburg, Assistant General Counsel P. Kokolakis, Director, Nuclear Licensing Public Document Room (PDR) local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector State of New York E. McGrath, Executive Vice President, Central Operations bcc:

Region I Docket Room (with concurrences)

DRP Section Chief e- _

RI: l oS RI:DRS 1/[ RI b S RI JR$S W L Shanb y Bellamy Ma in 11 /85 11////85 11/W/85 11//9/85

DRP R M TA /

Norrholm All Murley p.

11/9/85 11/ 85 11/JO/85 0FFICIAL RECORD COPY