Informs That FEMA Will Present Testimony of Kryter,Per Item 2 of 860116 Order.Kryter Will Answer Questions Re Items 3 & 5.Testimony on Item 6 Will Not Be Provided Due to Lack of Resources to Conduct Analysis
ML20137S050
Person / Time
Site: Harris  Duke Energy icon.png
Issue date: 02/07/1986
From: Johari Moore
NRC OFFICE OF THE EXECUTIVE LEGAL DIRECTOR (OELD)
To: Bright G, Carpenter J, Kelley J
Atomic Safety and Licensing Board Panel
References
OL, NUDOCS 8602130563
Download: ML20137S050 (1)


Text

_

- M jo reg

,y . g[og. UNITED STATES 2 '

e NUCLEAR REGULATORY COMMISSION L j WASHINGTON, D. C. 20555

\.....,/

February 7,1986_

James L. Kelley, Chairman .Dr. Glenn O. Bright Administrative Judge Administrative Judge Atomic Safety and Licensing Board Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555 Washington, DC 20555 Dr. James H. Carpenter Administrative Judge Atomic Safety and Licensing Board U.S. Nuclear Regulatory Commission Washington, DC 20555 In the Matter of Carolina Power and Light Company and North Carolina Eastern Municipal Power Agency (Shearon Harris Nuclear Power Plant, Units 1 and 2)

Docket Non. 50-400 OL and 50-401 OL

Dear Administrative Judges:

In accordance with the schedule confirmed by the Board in its Order of January 24, 1986, this letter identifies the FEMA witness who will testify at the hearing on March 4,1986.

FEMA has informed me that FFMA will present the testimony of Dr. Kryter concerning Item 2 of . the Board's Order. of January .16, 1986. Dr. Kryter .

will be prepared to answer the Board's questions with respect to Items 3 and 5 of that order. FEMA has determined that no testimony on Item 6 will be provided, since FEMA nas not conducted, and lacks the resources to conduct the analysis which suit testimony.would require.

Sincerely, ti ilLKlG_N Janice E. Moore Counsel for NRC Staff cc: Service List kk21 O go G

_ , - . . _ ._ .