Forwards Responses to Listed Items,Comprising Rev 4 to Course of Action Submitted to NRC on 850910.Summary Schedule of Activities to Be Completed Prior to Restart Will Be Submitted Wk of 851201.W/o Encls
ML20137R582
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/16/1985
From: Williams J
TOLEDO EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
1208, NUDOCS 8512060024
Download: ML20137R582 (2)


Text

m

/*

TOLEDO

%m EDISON Docket No. 50-346 JOE WLUAMS, JR.

License No. NPF-3 s,- w. w e 1419]249-2300 Serial No. 1208 November 16, 1985 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation United States Nuclear Regulatory Commission Washington, D. C.

20555

Dear Mr. Denton:

The enclosed materials comprise Revision 4 to the Davis-Besse Course of Action (C0A) submitted to you on September 10, 1985 (Serial No. 1182).

This submittal provides Toledo Edison's responses to:

NRC Maintenance Safety Evaluation Report (SER) dated October 30, 1985 (Log No. 1844)

Request for Additional Information (31 questions) dated October 30, 1985 (Log No. 1844)

NRC Evaluation of Root Cause Findings Reports dated October 30, 1985 (Log No. 1845)

Additional Question (designated Question 32 by Toledo Edison) dated November 7, 1985 (Log No. 1857)

Auxiliary Feedwater Pump Turbine Overspeed concerns stated in NRC letter dated September 6,1985 (Log No.,1813)

NRC Reviewer questions concerning Source Range Nuclear Instrumentation provided in a conference call of October 30, 1985 between Toledo Edison and NRC Staff.

To assist your Staff in the review of this document, a matrix cross-referencing your Staff's questions to the location of the responses in the text and appendix section has been prepared and is included as Attachment 1 to this letter.

Toledo Edison is providing a tracking report of commitments to be completed, both pre-and post-startup, in a revision to Appendix III-1 contained within this document.

During the week of December 1, 1985, Toledo Edison will submit a summary schedule (Level 2) of activities to be completed prior to restart.

8512060024 851116 PDR ADOCK 05000346; PDR

\\

p

.nc evLcuu tu! SON COMPANY

,. EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 b0

Docket No. 50-346

.r, -

Lictnxe No. NPF-3

^

Serial No. 1208 November 16, 1985 Page 2 This submittal also provides additional analyses, information, and evaluations pursuant to Toledo Edison's committments in the C0A. Details concerning the material submitted, and its appropriate placement within the C0A are provided.

Per the request of your Mr. Albert W. DeAgazio, previously controlled NRC copies of the C0A have been redesignated "Information Only" copies.

Ilowever, Copy Numbers 19 (issued to Mr. DeAgazio), 20 and 21 (issued to Mr. I. N. Jackiw), remain controlled copies.

Very truly yours,

,M N,: 1, JW:VJ.lah Enclosures cc: DB-1 NRC Resident Inspector l^