Safety Evaluation Supporting Const of Incinerator & Support Facilities
ML20137R010
Person / Time
Site: Framatome ANP Richland
Issue date: 11/26/1985
From: Bidinger G, Crow W
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To:
Shared Package
ML20137R000 List:
References
NUDOCS 8512050408
Download: ML20137R010 (2)


Text

_

{

+-

s NOV 2 g to85

~

DOCKET NO:

70-1257 APPLICANT:

Exxon Nuclear Company, Inc. (ENC) i FACILITY:

Richland, Washington I

SUBJECT:

SAFETY EVALUATION REPORT, APPLICATION DATED 1

OCTOBER 10. 1985, RE CONSTRUCTION AND OPERATION OF INCINERATOR

Background

ENC intends to modify the Specialty Fuels Building (SFB) so as to permit the

~

incineration of uranium contaminated combustibles. The subject application requests authorization to construct and operate the incinerator (which will be inside the SFB) and support facilities (which will be outside the SFB).

Discussion-t The incinerator will be installed in Room 173 of the SFB. Room 173 is currently licensed for the storage of contaminated equipment which had been used to pro-cess mixed oxide (oxides of plutonium and uranium) fuel. ENC'has initiated a

. plutonium decontamination program for. the room so that, with respect to plutonium, it can be released for unrestricted use. When this has been done, ENC will request that the license be amended to authorize incineration.of uranium-con-taminated combustibles. Construction inside the room will not commence until the NRC has conducted a confirmatory survey, following the ENC decontamination i.

effort.-

i The supporting services for the incinerator will be constructed outside of the

f' SFB adjacent to Room 173. These. services include an air lock-type room for

~

. moving combustibles into, and ash out of, the incinerator room. Other support systems include an exhaust stack. a' boiler and fuel tanks, a cooling tower,

[

storage tanks, and a drum storage-pad.

I Construction' activities should have no adverse effects on the environment.

l The area outside of the SFB is already committed to industrial activities. No i

virgin-land will be affected by this activity.

An operational safety demonstration will be required from_ ENC prior to operation of the facility. In the-demonstration,' ENC will be required to demonstrate the adequacy of technical and administrative controls for nuclear criticality safety and radiological safety.E By_ reducing the plutonium contamination to or below the levels specified in the license, the radiological safety-program will be based on ENC's. existing. radiological. safety-program for uranium.

C51205040s'B51126 ADOCK0700g27 DR 9

e

-+e%e.,ev-4.-

--m--

e-

+-+v-~

-+------wrw=

,<a v===-r em'=

't

  • + - * ' ' ' * "

NOV 2 61985 Exxon Nuclear Company, Inc.

'2 An environmental assessment of the effluent releases will be required.

Effluent limits and controls established in the license will be applicable to the incinerator.

Incineration of the material in about 13,000 drums which are stored outdoors will reduce the potential for an inadvertent environmental release of the material.

i Conclusion / Findings The staff concludes that construction of the facilities will have no adverse effect on the. environment. Operation of the incinerator and support facilities 1

is not expected to have a significant environmental impact. An environmental assessment will be made, however, before operation is authorized.

The staff has no objection to construction of the outdoor facilities. Upon completion of'the plutonium decontamination effort, the staff has no objection to erection of the indoor facilities.

In accordance with 10 CFR 51.22(c)(11),

no Environmental Impact Statement or Environmental Assessment is needed at this time. Pending review of the license amendment application, operation of

.the facility is not authorized.

OriE nal aigned47 i

George H.Bidinger G. H. Bidinger Uranium Process Licensing Section Uranium Fuel Licensing Branch' Division of Fuel Cycle and faned3n Material Safety,'NMSS Approved by: