Application for Amend to CPPR-148,extending Const Completion Date Until 860415
ML20137Q834
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 01/31/1986
From: Kaplan A
CLEVELAND ELECTRIC ILLUMINATING CO.
To:
Shared Package
ML20137Q831 List:
References
NUDOCS 8602070043
Download: ML20137Q834 (2)


Text

O January 31, 1986 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Director, Of fice of Nuclear Reactor Regulation In the Matter of )

)

THE CLEVELAND ELECTRIC ) Docket Nos. 50-440 ILLUMINATING COMPANY, _ET _A_L_. ) 50-441 (Perry Nuclear Power Plant, )

Units 1 and 2) )

APPLICATION FOR AMENDMENT OF CONSTRUCTION PERMIT NO. CPPR-148 TO EXTEND CONSTRUCTION COMPLETION DATE The Cleveland Electric Illuminating Company, Duquesne Light Company, Ohio Edison Company, Pennsylvania Power Company, and the Toledo Edison Company

("Permittees") are the co-holders of Construction Permit Nos. CPPR-148 and CPPR-149 authorizing construction of the Perry Nuclear Power Plant ("PNPP"),

Units 1 and 2.

Construction Permit Nos. CPPR-148 and CPPR-149 were issued by the NRC on May 3, 1977. Construction Permit No. CPPR-148 currently specifies November 30, 1985 as the latest date for completion of construction of Unit 1. Construction

! Permit No. CPPR-149 specifies November 30, 1991 as the latest date for com-pletion of construction of Unit 2. These construction completion dates are j extensions of the dates originally specified in the construction permits. The NRC order granting the extension of the construction completion dates for the Perry Nuclear Power Plant, Units 1 and 2 was issued in a letter dated December 29, 1982 from Darrell G. Eisenhut to Murray R. Edelman, t

7 t

Construction of Unit 1 is essentially complete. Preoperational testing is 1

l also essentially complete and programs are in place to assure that the Perry l

Nuclear Power Plant, Unit 1 is ready to load fuel and to achieve subsequent

! operating milestones as they approach.

9602070043 ADOCK D B 440 PDR PDR A

L

9 In order to provide for further time contingencies Permittees respectfully request, pursuant to 10CFR50.55(b), that the NRC amend Construction Permit

~

No. CPPR-148 to specify April 15, 1986 as the latest date for completion of construction of Unt: 1. Extension of the latest date for completion of construction of Unit 2 is not requested at this time, since the construction permit for Unit 2 does not expire until November 30, 1991.

To supplement our earlier requests for extension dated October 29, 1985, November 29, 1985, and December 27, 1985, we hereby request amendment of Construction Permit CPPR-148 to extend the completion date for Unit I to April 15, 1986 based on a reasonable and prudent extension of time which allows for further unforeseen contingencies prior to obtaining the operating license.

THE CLEVELAND ELECTRLC ILLUMLNATING COMPANY By (f. op -

A. Kaplan V Vice President Nuclear Operations Division Svorn to and subscribed before me, this 3/ # day of U 2 flu m s, , 1985 saiu f Nota y Public ihr M Commission Expires:

JANE E. MOTT Notary puote. drats of Ohh my Commission Lxpires February 20,1990 (Recorded in Lake County)