Application for Amend to CPPR-148,extending Const Completion Date from 851130 to 860131.Application Should Be Considered Withdrawn If OL Issued by 851231
ML20137Q523
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 11/29/1985
From: Kaplan A
CLEVELAND ELECTRIC ILLUMINATING CO.
To:
Shared Package
ML20137Q521 List:
References
NUDOCS 8512050293
Download: ML20137Q523 (2)


Text

4 November 29, 1985 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Director, Office of Nuclear Reactor Regulation In the Matter of. )

)

'THE CLEVELAND ELECTRIC ) Docket Nos. 50-440 ILLUMINATING COMPANY, ET AL. ) 50-441

)'

(Perry Nuclear Power Plant, )

iUnits'I and 2)' )

APPLICATION FOR AMENDMENT OF CONSTRUCTION PERMIT NO. CPPR-148 TO EXTEND CONSTRUCTION COMPLETION DATE The Clyveland Electric Illuminating Company, Duquesne Light Company, Ohio Edison Company, Pennsylvania Power Company, and the Toledo Edison Company

("Permittees") are the co-holders of Construction Permit Nos. CPPR-148 and CPPR-149 authorizing construction of the Perry Nuclear Power Plant ("PNPP"),

Units 1 and 2.

Construction Permit Nos. CPPR-148 and CPPR-149 were issued by the NRC on May 3, 1977. Construction Permit No. CPPR-148 currently specifies November 30, 1985 as the latest date for completion of construction of Unit 1. Construction Permit No. CPPR-149 specifies November 30, 1991 as the latest date for com-pletion of construction of. Unit 2. These construction completion dates are extensions of the dates originally specified in the construction permits. The NRC order granting the extension of the construction completion dates for the Perry Nuclear Power Plant, Units 1 and 2 was issued in a letter dated December 29, 1982 from Darrell G. Eisenhut to Murray R. Edelman.

. Construction of Unit 1 is essentially complete. Preoperational testing is also essentially complete and programs are in place to assure that the Perry Nuclear Power Plant, Unit 1 is ready to load fuel and to achieve subsequent operating milestones as they approach.

85i2050293 B51129 PDR ADOCK O 4j0

'e In order to provide for further time contingencies Permittees respectfully request, pursuant to 10CFR50.55(b), that the NRC amend Construction Permit No.

'CPPR-148 to specify January 31, 1984 as the latest date for completion of (o

construction of Unit 1. Extension of the latest date for completion of construction of Unit 2 is not requested at this time,'since the construction

. permit.for Unit 2 does not expire until November 30, 1991.

To supplement our earlier request for extension dated October 29, 1985 we hereby request amendment of Construction Permit CPPR-148 to extend the ccepletion-dateforUnit1toJanuary31,198gbasedonareasonableand prudent extension of time which allows for fu ther unforeseen contingencies prior.to obtaining the operating license. Of course, in the event that an operating license is issued for Unit 1 by December 31, 1985, this request should be considered withdrawn.

THE CLEVELAND ELECTRIC ILLUMINATING COMPANY By . ~

A. Kaplan Vice President Nuclear Operations Division Sworn to ag subscri ed before me, this 47 day of adtt , 1985 Nota W$

Public My Commission Expires:

JANE E. MOTT Notary Pub!ic, State of Ohin MF ETE- - 3 Expires February 20,1990 (Recorded in Lake County) g i ls -