ML20137N228

From kanterella
Jump to navigation Jump to search

Ack Receipt of 970317 Submittal Containing Summaries of Criticality Safety Analyses.Initial Administrative Review Completed
ML20137N228
Person / Time
Site: Framatome ANP Richland
Issue date: 04/02/1997
From: Chotoo S
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Maas L
SIEMENS POWER CORP. (FORMERLY SIEMENS NUCLEAR POWER
References
TAC-L30940, NUDOCS 9704080297
Download: ML20137N228 (2)


Text

, _ _ __ _ __ _ _ _ _ _ . _ . _ _ . . _ . . _ . _ _ . _ _ _ _ _ _ _

April-2, 1997 r- .Mr. L. J. Maas Manager, Regulatcry Compliance.

j, -

Siemens Power Corporation ,

2101 Horn Rapids Road Richland3 Washington 99352-0130

~

SUBJECT:

ACKNOWLEDGMENT OF RECEIPT OF CRITICALITY SAFETY ANALYSES

.(TAC NO. L30940)

)

Dear Mr. Maas:

We have received your submittal dated March 17, 1997, containing summaries of criticality safety analyses (CSA's) for the Line 1, 2, and 3 powder preparat- .

ion system and the pelletizing process. This project has been assigned

TAC No. L30940. Please reference this number in any future correspondence associated with this project. Your document has been forwarded to the Project

. Manager, Susan Chotoo, for appropriate action. Ms. Chotoo can be reached on 1 (301) 415-8102.

~

We hav~e completed the initial administrative review of your submittal. During the initial processing no omissions or deficiencies were identified. Please i note that the complete technical review may identify omissions in the  ;

' submittal information or technical issues that may require additional information.

We expect to receive ~ the remainder of your Category II CSA's by April 30, >

1997, according to your schedule submitted December 2, 1996. Based on our

i administrative reviews and projection of current review schedules, we would anticipate completing our review of the Category II CSA's by October 1997. '

1 This date could change depending on the findings of our technical review, urgent assignments, or other factors. We will promptly communicate any

significant changes to this schedule. 1 A copy of your correspondence has been forwarded to our License Fee and Accounts Receivable Branch, Office of the Controller, who will contact you separately if the appropriate license fee has not been submitted for your request, or for billing if your request is subject to full cost fee recovery.

Sincerely, N

SusanD.Chotoo,ActingProjectManagerl[4 <

! Licensing Section 2  !

DO 257 v no e Cycle Safety ()

C PDR ,

and Safeguards, NMSS [l Docket 70-1257 License SNM-1227 g g gg gy DISTRIBUTION: (Control No. 5EOS(FE))  !

.NRC File Center Region IV

' Docket.70-1257' PUBLIC.

NMSS r/f FCSS r/f FCLB r/f CHooker, RIV l KHardin

G:\csaack2.ltr] q OFC FCLB e_ FCLB b FCLS /d h j NAME Schotoo 6 0 0, PShea fLD3 GPa(gbu$n l

DATEi 4/ A /J7_ _ _ 4/SL/97 4/ L /97 4/ /97 U V U V 0 4)

. . - .. . . - - - - . - . . . . ~ . _ . --.. ..- - . - .

'd

[*

.- B

UNITED STATES NUCLEAR REGULATORY COMMISSION .

b l

WASHINGTON. D.C. 2000H001 .!

.,g .

April.2,.1997  ;

l Mr.1 L J. Maas -

Manager, Regulatory Compliance.

.Siemens Power Corporation ,

2101 Horn Rapids Road ,

Richland, Washington .99352-0130 '

1

SUBJECT:

ACKNOWLEDGMENT-0F RECEIPT OF-CRITICALITY SAFETY ANALYSES (TAC _N0. L30940)

Dear Mr. Maas:

I i

4 We have received your submittal dated March 17, 1997, containing summaries'of i

. criticality safety analyses (CSA's) for the Line 1, 2, and 3 powder preparat- i

ion system and the pelletizing process. This project has been assigned.  !

!  ! TAC No. L30940. . Please~ reference this number in any future correspondence ,

i

_ associated with this project. Your document has been forwarded to the Project i Manager, Susan Chotoo, for appropriate action. Ms. Chotoo can be reached on i j (301) 415-8102.

We have completed the-initial administrative review of your submittal. During 1

-the initial processing no omissions or deficiencies were identified. Please

note that the complete technical review may identify omissions in the

submittal information or technical issues that may require additional information.

We expect to receive the remainder of your Category II CSA's by April 30,  !

-1997, according to your schedule submitted December 2, 1996. Based on our i

administrative reviews and projection of current review schedules, we would l anticipate completing our review of the Category II CSA's by October 1997. -

This date could change depending on the findings of our technical review, i urgent assignments', or other factors. We will promptly communicate any i

[ significant changes-to this schedule.

I l . A copy of your correspondence has been forwarded to our License Fee and  !

L Accounts Receivable Branch, Office of the Controller, who will contact you j

. separately if.the appropriate license fee has not been submitted for your '

[

request, or for billing if your request is subject to full cost fee recovery.

3 Sincerely, ,

J Susan D. Chotoo, Acting Project Manager

^

Licensing Section 2  ;

Licensing Branch  ;

Division of Fuel Cycle Safety i and Safeguards, NMSS  !

Docket 70-1257-f

. License SNM-1227-1 l l

i

_ _ _ _ ,_