DM m. Commonwealth Edison

\\ Byron NuclTrSt:tiin

, / 4450 North Germin Church Rzd

J Byron,lllinois61010 sd PRIORITY ROUTING fdnt.

3econd fykh V

August 11,1985 g@-f I g3

[

pass a

LTR:

BYRON 85-1131 ewA gT-PA0 FILE.. i s Mr. James G. Keppler Regional Administrator Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn,IL 61057

SUBJECT:

Clarification on the Main Steam Isolation Valve Airline Check Valve Test Interval.

REFERENCE:

Byron Letter 85-0997, R.E. Querio to J.G. Keppler, dated July 11,1985

Dear Mr. Keppler:

The purpose of this letter is to eliminate potential confusion in our use of the word "bi-annually"in the referenced letter. Our intention is to test the subject valves on a six month (semi-annual) basis through Unit One's second refueling.

Wi$lc R.E. Querio Station Superintendent Byron Nuclear Power Station REQ /JEL/gt t

ec:

J. Illnds, NRC Res. Insp.

M. Robinson T. Maiman W. Dijstelbergen V. Schlosser D. Elias D. Galle B. Shelton R. Plenlewicz J. Langan

  1. 16/035 8508270154 850811 PDR P

ADOCK 05000454 M@

9 1985

\\

PDR t

gg4 t