ML20137F305

From kanterella
Jump to navigation Jump to search
Deficiency Rept DER 85-07 Re C-E Instrument Rack.Initially Reported on 850305.Due to Extensive Investigation & Evaluation,Final Rept Delayed Until 850906
ML20137F305
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 08/13/1985
From: Van Brunt E
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-33206-TDS, DER-85-07, DER-85-7, NUDOCS 8508260191
Download: ML20137F305 (2)


Text

r k

Arizona Nuclear Power Project P.O. BOX 52034

  • PHOENIX, ARIZONA 85072-2034 August 13, 1985 ANPP-33206-TDS/TPS gg, U. S. Nuclear Regulatory Conmission Region V 1450 Maria Lane - Suite 210 Walnut Creek, California 94596-5368 Attention: Mr. D. F. Kirsch, Acting Director Division of Reactor Safety & Projects

Subject:

Time Extension for Report - DER 85-07 A 50.55(e) Potentially Reportable Deficiency Relating To CE Instrument Rack Deficiencies File: 85-019-026; D.4.33.2

Reference:

A) Telephone conversation between L. Miller and T. Bradish on March 5, 1985 B) ANPP-32329, dated April 8, 1985 (Interim Report)

C) ANPP-32654, dated May 16, 1985 (Time Extension)

D) ANPP-32828, dated June 13, 1985 (Time Extension)

E) ANPP-33013, dated July 15, 1985 (Time Extension)

Dear Sir:

The NRC was notified of a potentially reportable deficiency in Ref-erence A and an Interim Report was transmitted by Reference B.

Time Extensions were requested by References C, D, and E.

Our last forecast indicated that a final report would be completed by August 12, 1985.

Due to the extensive investigation and evaluation required, it is now expected that this information will be finalized by Septenber 6,1985, at which time a complete report will be submitted.

There is no new infonnation or change to the Interim Report at this time.

Very truly yours, k. ca nLt E. E. Van Brunt, Jr.

Executive Vice President Project Director -

!"3 8508260191 850813 ADOCK 050 g 8 cc: See Page Two PDR s

o

,4

.2T-J7 L

s-ANPP-33206-TDS/TPS August 13, 1985 Mr. D. F. l{irsch DER 85-07 Page '1%

cc:

Richard DeYoung, Director Office of Inspection and Enforcanent U. S. Nuclear Regulatory Connission Washington, D. C.

20555 D. B. Kamer W. E. Ide D. B. Fasnacht A. C. Rogers L. A. Souza D. E. Fcraler T. D. Shriver C. N. Russo B. S. Kaplan J. R. Bynta J. M. Allen D. Canady A. C. Gehr W. J. Stubblefield W. G. Binghan R. L. Patterson R. W. Welcher H. D. Foster D. R. ILTokinson R. P. Zinmerman M. L. Clyde B. T. Parker T. J. Bloom D. N. Stover J. D. Houchen J. E. Kirby Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, GA 30339