Notifies of Commission Approval of 850930 Request for Extension of Time Beyond 851130 to Complete Environ Qualification of Electrical Equipment.Order Detailing Commission Reason for Action Will Be Issued
ML20137B208
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 11/14/1985
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO.
References
NUDOCS 8511260211
Download: ML20137B208 (1)


Text

p+%

SH N TN C 5

..... November 14, 1985 CFFICE OF THE SECRETARY Sf U3 Mr. John F. Opeka Senior Vice President Nuclear Engineering and Operations Connecticut Yankee Atomic Power Company Prst Office Box 270 Hartford, Connecticut 06141

Dear Mr. Opeka:

By letter dated September 30, 1985 in accordance with 10 CFR 50.49, Connecticut Yankee Atomic Power Company requested an extension of time beyond November 30, 1985, to complete environmental qualification of electrical equipment at its Haddam Neck Plant.

Upon consideration of your September 30 letter the Commission has approved your request.

An order detailing the Commission's reasons for its action onyourextensionrequestwilybeissuedinthenearfuture.

S Lncere ,

O -

'l

( .

amuel J. C ilk fSecretary of the Commission l

i B511260211 851114 PDR P ADOCK 05000213 PDR