Text
O 6
PETER E. KAT7 13altimore Gas and Electric Company Plant General Manager Calvert Cliffs Nuclear Power Plant Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 410 495 4101 March 14,1997 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 February 1997 Operating Data Reports The subject reports are being sent to you as required by Technical Specification 6.6.4.
Should you have any questions, please contact Mr. Kenneth Greene at (410) 495-4385.
Very truly yours, PEK/IIOO/bjd Attachments cc:
D. A. Brune, Esquire R. A. Hartfield, NRC
/
J. E. Silberg, Esquire R. I. McLean, DNR f
kI Director, Project Directorate 1-1, NRC J. It Walter, PSC
.oh A. W. Dromerick, NRC P. Lewis, INPO
(#M H. J. Miller, NRC K. N. Larson, ANI Resident inspector, NRC 9703200122 970228 DR ADOCK 05000317 PDR 200014
@.35555,55555
._._,_._.m...
- p******************************************************************
UNIT 1 OPERATING DATA REPORT Docket No. 50-317 March 14, 1997 Prepared by Herman O. Olsen Telephone i (410) 4 95-6734 OPERATING STATUS
~~~ -~~~~~~~~~~~
- 1. UNIT NAME Calvert Cliffs Unit 1
- 2. REPORTING PERIOD FEBRUARY 1997
- 3. LICENSED THERMAL POWER (MWT) 2700
- 4. NAMEPLATE RATING (GROSS MWe) 918 5.-DESIGN ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM' DEPENDABLE CAP'Y (GROSS MWe) 865
- 7. MAXIMUM DEPENDABLE CAP'Y (NET MWe) 835 8.
CHANGE IN CAPACITY RATINGS NONE 9.
POWER LEVEL TO WHICH RESTRICTED N/A
- 10. REASONS FOR RESTRICTIONS N/A P
Year-Cumulative This month to-Date to Date
- 11. HOURS IN REPORTING PERIOD 672 1,416 191,221 1
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 138,711.5
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
- 14. HOURS GENERATOR ON LINE 641.9 1,385.9 135,872.8
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
'16. GROSS THERMAL ENERGY GENERATED (MWH) 1,699,786 3,700,584 346,428,903
- 17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 570,225 1,240,329 115,005,691
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 546,708 1,190,638 109,538,830
- 19. UNIT SERVICE FACTOR 95.5 97.9 71.1
- 20. UNIT AVAILABILITY FACTOR 95.5 97.9 71.1
- 21. UNIT CAPACITY. FACTOR (USING MDC NET) 97.4 100.7 69.3
- 22. UNIT CAPACITY FACTOR (USING DER NET) 96.3 99.5 67.8
- 23. UNIT FORCED OUTAGE RATE 4.5 2.1 8.4
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION) :
N/A
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
N/A
- =
m--
+y.*,
ypm y-,vy..
9 m.
.m a
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-317 UNIT NAME Calvert ClitTs-UI DATE March 14.1997 COMPLETED BY 11erman O. Olsen TELEPilONE (410)495-6734 REPORT MONTH February 1997 l
l l
! METIIODOF l l
l l SIIUTTING LICENSEE !
l CAUSE & CORRECTIVE i
i I
l DURATION l
[
DOWN EVENT
! SYSTEM COMPONENT i ACTION TO NO.
! DATE !TYPEII (IfOURS) i REASON 2l REACTOR 3 REPORT # i CODE 4 CODES l
PREVENT RECURRENCE 97-001 j 02/15/97 F
j 30,1 A
i 9
N/A AB RTV An increase in the amount of reactor coolant leakage was l
noted. Reactor power was reduced and the unit was l
' removed from the grid. The leakage was determined to i
be from a root isolation valve (1RCl4I) packing gland.
1 l
l l
l The valve was isolated. Investigation into the cause for l
the seal / packing leakage is on going.
I l
t, i
l I
\\
i i
i l
l l
I i
l l
i j
i i
i I
l i
=
I s
1 i
l i
l l
l I
l I
i l
I' 1
i t
i I F: Forced 2 Reason:
3 Method:
4 IEEE Standard 805-1984 S: Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.
C - Refueling 3 - Automatic Scram.
5 IEEE Standard 803A-1983 D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9 - Other G - Operational Error 11 - Other
REFUELING INFORMATION REOUEST 1.
Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No.1.
2.
Scheduled date for next refueling shutdown: March 1998 3.
Scheduled date for restart following refueling: May 1998 4.
Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?
N/A 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
NIA 6.
Important licensing considerations associatcd with the refueling.
N/A 4
7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.
(a) 217 (b) 1494 (Note 2)
- Spent fuel pools are common to Units I and 2.
8.
(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.
(a) 4710 (Note 1)
(b) 0 9.
The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.
March 2007 NOTE 1:
4710 total licensed site storage capacity.
(1830 pool + 2880 ISFSI)
NOTE 2:
360 Spent Fuel Assemblies in the ISFSI.
Includes 92 new Batch 2P fuel assemblies.
Entry has changed since last reported.
AVERAGE DAILY UNIT POWER LEVEL
- cc*********************************************************************
Docket No. 50-317 Calvert Cliffs Unit No. 1 March 14, 1997 Prepared by Herman O. Olsen Telephone: (410) 495-6734 FEBRUARY 1997 Average Daily Power Level Average Daily Power Level Day (MWe-Net)
Day (MWe-Net) 1 868 17 857 2
869 18 862 3
869 19 865 4
869 20 865 5
868 21 867 6
869 22 868 7
868 23 869 8
868 24 868 9
868 25 868 10 868 26 868 11 868 27 868 12 867 28 867 13 867 14 852 15 15 16 237
_._ _ _ _. ~. _.. _...
.. _ _. _. _ =.
- _. _. -.... _. _ _. ~.. _
DOCKET NO. 50-317 CALVERT CLIFFS - UNIT I March 14,1997 i
SUMMARY
OF OPERATING EXPERIENCE Februars 1997 The unit began the month at 100% power.
An increase in reactor coolant system leakage was noted on 02/14/97 at 0330. Power was reduced and a containment entry was performed to identify the source of the leakage. A root isolation valve (IRCl41) was found to have a packing leak. The unit was removed from the grid and the valve was isolated, which eliminated the packing / seal leak. While the unit was removed from service a balance shot was added to the Main Turbine. Repairs were completed on 02/15/97 at 1750 and power was increased. The unit was paralleled to the grid on 02/16/97 at 0927 and returned to 100% on 02/17/97 at 0100.
The unit operated at 100% for the remainder of the month.
i t
1 oco*************************************************************************
i
' UNIT =2 OPERATING DATA REPORT oo**************************************************************************
Docket No. 50-318 March 14, 1997 Prepared by Herman O. Olsen Telephone : (410) 495-6734 OPERATING STATUS
~~~~~~~~~~~~~~~~
1.
UNIT NAME Calvert Cliffs Unit 2
- 2. REPORTING PERIOD FEBRUARY 1997 l
- 3. LICENSED THERMAL POWER (MWT) 2700 i
- 4. NAMEPLATE RATING (GROSS MWe) 911 5.
DESIGN ELECTRICAL RATING (NET MWe) 845 6.
MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 870 7._ MAXIMUM DEPENDABLE CAP'Y (NET MWe) 840 8.
CHANGE IN CAPACITY RATINGS NONE 9.
POWER. LEVEL TO WHICH RESTRICTED N/A
- 10. REASONS FOR RESTRICTIONS N/A Year-Cumulative This month to-Date to Date
- 11. HOURS IN REPORTING PERIOD 672 1,416 174,576
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 672.0 1,416.0 131,258.4
- 13. REACTOR RESERVE SHUTDONN HOURS 0.0 0.0 1,296.6
- 14. HOURS GENERATOR ON LINE 672.0 1,416.0 129,551.0
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,755,847 3,733,960 332,828,344
- 17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 588,448 1,251,012 109,988,426
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 565,385 1,202,261 105,179,444-
'19. UNIT SERVICE FACTOR 100.0 100.0 74.2
- 20. UNIT AVAILABILITY FACTOR 100.0 100.0 74.2
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 100.2 101.1 72.8
- 22. UNIT CAPACITY FACTOR (USING DER NET) 99.6 100.5 71.3
- 23. UNIT FORCED OUTAGE RATE 0.0 0.0 5.3
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):
Refueling 03/14/97 60 days
- 25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
N/A
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-318 UNIT NAME Calven ClitTs-U2 DATE March 14.1997 COMPLETED BY llennan O. Olsen TELEPilONE (410)495-6734 REPORT MONTH Febuary 1997 METilOD OF !
l l
l SIlUTTING l LICENSEE CAUSE & CORRECTIVE
. DURATION l DOWN l
EVENT
! SYSTEM COMPONENT -
ACTION TO l
i REACTOR 3 ! REPORT #
CODE 4 CODES
[
PREVENT RECURRENCE NO.
DATE ' T) PEII (IIOURS) ' REASON 2!
l l
l l
l l
l l There were no significant power reductions for this l
t j
j I
month.
+
i i
t i
'I i
1 l
i i
i l
i t
i I
i i-l
-f l
i i
i l
}
t i
l l
i i
i j
^
i i
l l
l i
i f
i a
i l
1 i
i t
l l
i I
I i
l l
i i
i
}
[
I I
l I p.
Forced 2 Reason:
3 Method:
4 IEEE Standard 805-1984 S: Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.
C - Refueling 3 - Automatic Scram.
5 IEEE Standard 803A-1983 l
D - Regulatory Restriction 4 - Continued i
E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9 - Other G - Operational Error II - Other r
h
REFUELING INFORMATION REOUEST 1.
Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 2 l
2.
Scheduled date for next refueling shutdown: March 14,1997 3.
Scheduled date for restart following refueling: May 4,1997
- 4.
Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?
- Yes, License Amendment to adopt the requirements of Appendix J, Option B for Type B s.
and C testing.
b.
License Amendment to allow the substitution of a blind flange for the outside purge valve pressure boundary in Modes 1-4.
c.
Deleted.
d.
License Amendment to lower the reactor coolant flow which supports an increased number of steam generator tubes plugged.
c.
Deleted.
f.
License Amendment to allow electrosleeving as a repair method for steam generator tubes.
5.
Scheduled date(s) for submitting proposed licensing action and supportmg information.
a.
November 26,1996 b.
August 1,1996 c.
Deleted d.
January 31,1997 e.
Deleted f.
July 26,1996 6.
Important licensing considerations associated with the refueling.
None.
7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.
(a) 217 (b) 1494 (Note 2)
- Spent fuel pools are common to Units 1 and 2.
8.
(a) 'Ihe present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assembhes.
(a) 4710 (Note 1)
(b)0 9.
The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.
March 2007 NOTE 1:
4710 total licensed site storage capacity.
j (1830 pool + 2880 ISFSI) 1 NOTE 2:
360 Spent Fuel Assemblies in the ISFSI.
Includes 92 new Batch 2P fuel assemblies.
Entry has changed since last reported.
i i
s AVERAGE DAILY UNIT POWER LEVEL COO **************************************************w******************
Docket No. 50-318 Calvert Cliffs Unit No. 2 March 14, 1997 Prepared by Herman O. Olsen Telephone: (410) 495-6734 FEBRUARY 1997 i
Average Daily Power Level Average Daily Power Level Day (MWe-Net)
Day (MWe-Net) 1 853 17 860 2
843 18 852 3
843 19 835 4
842 20 841 5
843 21 831 6
843 22 823 7
842 23 840 8
841 24 828 9
859 25 820
]
10 862 26 813 11 861 27 801 12 861 28 789 13 860 14 857 15 855 16 859
{
1 y
i t
d DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 March 14,1997
SUMMARY
OF OPERATING EXPERIENCE February 1997 The unit began the month at 100% power.
On 02/16/1997 at 2200 a gradual planned reduction in power (fuel coastdown) was commenced, in preparation for the upcomming refueling outage.
Due to the reduced cooling capacity of the main power output transformer (U-22000-22) power was reduced periodically throughout the month, as indicated below, based on the outside ambient temperature.
On 02/02/97 at 1115 power was reduced to 97%. Power was returned to 100% on 02/09/97 at 0330.
On 02/18/97 at 1215 power was reduced to 97%. Power was further reduced to 95% on 02/19/97 at 1810. Power was returned to the fuel coastdown level of 97% on 02/20/97 at 0030.
On 02/21/97 at 1639 power was reduced to 94%. Power was returned to the fuel coastdown level of 97% on 02/22/97 at 1645.
On 02/27/97 at 1930 power was reduced to 90%. Power remained at 90% as necessitated by the fuel coastdown.
The unit operated at 90% power for the remainder of the month.
'