Revises Response to Violations Noted in Insp Repts 50-338/84-35 & 50-339/84-35.Extension Requested Until 860401 to Complete Review of QA Dept Activities & Develop Specific Procedural Guidelines Where Appropriate
ML20136J406
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 12/31/1985
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
85-893, NUDOCS 8601130354
Download: ML20136J406 (2)


Text

OM6 O

VIMUINIA ELucTulc Axn l'ownu CoMIwny 1(IC H M O N D, VI HU IN I A 2112 61 JG JAN 7 P12 : 25 w.L.sruw m v,c. r....."'

December 31, 1985 Nortman Ors.arso.

Dr. J. Nelson Grace Serial No.85-893 Regional Adminir.trator NAPS /JHL Region II Docket Nos. 50-338 U. S. Nuclear Regulatory Commission 50-339 Suite 2900 License Nos. NPF-4 101 Marietta St., N.W.

NPF-7 Atlanta, Georgia 30323

Dear Dr. Grace:

' VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNIT NOS. 1 AND 2 REVISED RESPONSE TO NOTICE OF VIOLATION NRC INSPECTION REPORT NOS. 50-338/84-35 AND 50-339/84-35 On November 30, 1984, we sent you our response to the notice of violation identified in Inspection Report Nos. 50-338/84-35 and 50-339/ 84-35. The finding was that management controls had not been established which ensure that appropriate quantitative and qualitative acceptance criteria are provided in all procedures controlling safety-related activities.

Specifically, deficiencies in two areas were identified; the Measuring and Test Equipment (M&TE) Calibration Program and the Procurement Document Control Program were sighted as examples.

We committed to conduct a review of Quality Assurance (QA) Department activities as they relate to specific disciplines and develop individual procedural guidance and/or checklists for each discipline where appropriate by December 31, 1985.

For M&TE and procurement, station administrative procedures have been revised and QA departmental procedures will be revised by the commitment date.

However, because of the rescheduling of the Unit I refueling outage from April, 1986 to November, 1985, we are unable to complete our review and procedure revision for the remaining scope of work by December 31, 1985.

We have determined that an extension until April 1, 1986 is required to complete our efforts to fully address the referenced notice of violation.

If you have any further questions, please contact me.

Very truly yours,

\\

W. L. Stewart 8601130354 851231

- DR ADOCK 05000330 PDR O

y

t VamosuA Etactasc ano Powse Cowrawv to Dr. J. Nelson Grace t

k e

e Mr. Roger D.' Walk'er, Director cc:

Division of Reactor Projects Mr. Lester S. Rubenstein, Director PWR Project Directorate # 2 Division of PWR Licensing - A Mr. M. W. Branch NRC Resident Inspector North Anna Power Station t