NPDES Noncompliance Notification:On 851117,pH of Discharge Point Sample Exceeded Permit Limit.Caused by non-neutral Overflow from Neutralizing Tank.Acid Added to Settling Basin & Personnel Training Planned
ML20136G383
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 12/30/1985
From: Ullrich W
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
PENNSYLVANIA, COMMONWEALTH OF
References
NUDOCS 8601080157
Download: ML20136G383 (2)


Text

i $~

PHILADELPHIA ELECTRIC COMPANY  !

2301 MARKET STREET l P.O. BOX 8699 l l

PHILADELPHIA, PA.19101 I (21510414000 December 30, 1985 Department of Envi?.onmental Resources Burea.u of Water Quality Management One Ararat Blvd.

Harrisburg,.PA 17110

SUBJECT:

Noncompliance with NPDES Permit Peach Bottom Atomic Power Station Permit No. PA 0009733 Gentlemen:

DESCRIPTION OF NONCOMPLIANCE:

The pH of a sample from discharge point 301 (Wast ewa tur Settling Basin) exceeded the permit limit.

Date Samples Taken 11/17 Date Results Received: 11/17 Results of Analysis: 11.1 Permit Limitation: 6.0 to 9.0 CAUSE OF NONCOMPLIANCE:

The cause of the noncompliance was a Neutralizing Tank overflow before it was neutralized.

DURATION OF NONCOMPLIANCE:

The duration of noncompliance was approximately three hours.

(12:00 PM '3:00 PM)

CORRECTIVE ACTION:

Acid was added to the settling basin to bring the pH within the allowable range.

PREVENTION OF FUTURE OCCURRENCES l

The mechanisms have been in place which should preclude this

~

l event from occuring. The systems procedures provide for t neutralizint of tanks prior to release and inline pH meters on the discharge pumps and the raw water sump assure the water pH is

, within range prior to discharge to the settling basin.

8601080157 851230 PDR ADOCK 05000277 "7fjI S pop l

c -, >

Our investigation of this event has not identified the specific cause of this event. The possibility exists that the water pH meter was in bypass at the time of the neturalizing tank overflow. Remedial training of operations personnel responsible for these operations will be conducted during the first quarter of 1986.

Very truly yours, b

$$$*v W. T. Ullrich Superintendent Nuclear Generation Division

JAV/WTU
ala.-

! cc: Environmental Protection Agency Water Permits Branch Pennsylvania Section 3WM52 841 Chestnut Building Philadelphia, Pennsylvania 19107 Director Office of Nuclear Reactor Regulation US Nuclear Regulatory Commisssion Washington, DC.20555

' Administrator Region I Office of Inspection and Enforcement

, US Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 l