Forwards Safety Insp & Operational Readiness Assessment Team Insp 50-278/85-41 on 851026-1206.No Violation Noted.Insp Conducted to Verify Establishment & Implementation of Programs to Restore Facility to Design Configuration
Date released: 05/29/2020 Download: ML20136F434


Operational Readiness Assessment Insp Rept 50-278/85-41 on 851026-1206.No Violations Noted.Major Areas Inspected:Mgt Oversight & Corrective Action Tracking,Preoperational Testing & RHR Pump Insps & Repairs
ML20136F438
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 12/27/1985
From: Beall J, Gallo R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
Download: ML20136F438 (31)
Forwards Safety Insp & Operational Readiness Assessment Team Insp 50-278/85-41 on 851026-1206.No Violation Noted.Insp Conducted to Verify Establishment & Implementation of Programs to Restore Facility to Design Configuration
ML20136F430
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 12/31/1985
From: Collins S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: DALTROFF S L
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
References
Download: ML20136F430 (2)