Monthly Operating Rept for Oct 1985
ML20136C184
Person / Time
Site: Salem PSEG icon.png
Issue date: 10/31/1985
From: White P, Zupko J
Public Service Enterprise Group
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
NUDOCS 8511210049
Download: ML20136C184 (9)


Text

_

AVERAGE DAILY UNIT POWER LEVEL Docket No.

50-311 Unit Name Salem # 2 Date November 10,1985 i

  • Completed by Pell White Telephone 609-935-6000 4

Extension 4455 Month October 1985 Day; Average Daily Power Level Day Average Daily Power Level (MWe-NET)

.(MWe-NET) 1 1101 17 1095

- 2 1080 18 1090 3

1089 19 1083 4

1101 20 1094 5

1101 21 1082 6

1108 22 1103 7

420 23 1080 l

8

'O 24 1103 9

0 25 1104 r

10 874 26 1108 11 1101 27 1109 12 1090 28 1093 13 1106 29 1095 14 1080 30 1042 15 1103 31 911 16 1090-Pg. 8.1-7 R1 r

i a

r i

4 8511210049 851031 PDR ADOCK 05000311 R

PDR

1L6o, i

I OPERATING DATA REPORT Docket No. 50-311 Date November 10,1985 Telephone 935-6000 Completed by Pell White Extension 4455 Operating Status 1.

Unit Name Salem No. 2 Notes 2.

Reporting Period October 1985 3.

Licensed Thermal Power (MWt) 3411 4.

Nameplate Rating (Gross MWe) 1170 5.

Design Electrical Rating (Net MWe) 1115 6.

Maximum Dependable Capacity (Gross MWe)1149 7.

Maximum Dependable Capacity (Net MWe) 1106 8.

If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason N/A 9.

Power Level to Which Restricted, if any (Net MWe)

N/A

10. Reasons for Restrictions, if any N/A This Month Year to Date Cumulative
11. Hours in Reporting Period 745 7296 35521
12. No. of Hrs. Reactor was Critical 711.3 4273.3 19367.9
13. Reactor Reserve Shutdown Hrs.

0 0

3533.6

14. Hours Generator On-Line 686.0 3966.9 18579.0
15. Unit Reserve Shutdown Hours 0

0 0

16. Gross Thermal Energy Generated (B0m) 2306441 12752514 56479550
17. Gross Elec. Energy Generated (MiGI) 766960 4208120 18485770 i
18. Net Elec. Energy Generated (MWH) 734142 3975913 17493749
19. Unit Service Factor 92.1 54.4 52.3
20. Unit Availability Factor 92.1 54.4 52.3

~~

21. Unit Capacity Factor (using MDC Net) 89.1 49.3 44.5
22. Unit Capacity Factor (using DER Net) 88.4 48.9 44.2
23. Unit Forced Outage Rate 7.9 43.0 38.4
24. Shutdowns scheduled over next 6 months (type, date and duration of each)

N/A

25. If shutdown at end of Report Period, Estimated Date of Startup:

N/A

26. Units in Test Status (Prior to Commercial Operation) :

Forecast Achieved Initial Criticality 6/30/80 8/2/80 Initial Electricity 9/1/80 6/3/81 Commercial Operation 9/^1/80 10/13/81 8-1-7.R2

r UNIT SilUTDOWN AND POWER REDUCTIONS DockSt No. 50-311 REPORT MONTH October 1985 Unit Nrme Salem No.2 Date November 10,1985

  • Completed by J.P.

Ronafalvy Telephone 609-935-6000 Extension 4455 Method of Duration Shutting License Cause and Corrective l

l No.

Date Type Hours Reason Down Event System Component Action to 1

2 Reacto r Report Code 4 Code 5 Prevent Recurrence Nuclear Reactor Coolant / Recirculating CB PUMPXX Pumps85-248 1030 F

59.0 A

3 PC PIPEXX Valves and Piping 85-264 1030 F

0.7 A

5 35-266 1030 F

0.3 A

4 PC PIPEXX Valves and Piping 85-268 1030 F

0.3 A

4 PC PIPEXX Valves and Piping PC PIPEXX Valves and Piping 85-270 1030 F

0.8 A

4 85-272 1030 F

1.9 A

4 PC PIPEXX Valves and Piping PC PIFrXX Valves and Piping 85-274 1031 F

0.8 A

4 1

2 Reason 3 Method 4 Exhibit G 5 Exhibit 1 F: Forced A-Equipment Failure-explain 1-Manual Instructions Salem as S: Scheduled B-Maintenance or Test 2-Manual Scram.

for Prepara-Source C-Refueling 3-Automatic Scram, tion of Data D-Regulatory Restriction 4-Continuation of Entry Sheets E-Operator Training & Licensing Exam Previouc Outage for Licensee F-Administrative 5-Load Reduction Event Report G-Operational Error-explain 9-Other (LER) File H-Other-explain (NUREG 0161)

' MAJOR PLANT MODIFICATIONS DOCKET NO.:

50-311 REPORT MONTH OCTOBER 1985 UNIT NAME:

Salem 2 DATE:

November 10, 1985 COMPLETED BY:

J.

Ronafalvy TELEPHONE:

609/339-4455

PRINCIPLE SYSTEM SUBJECT NONE

PSE&G SALEM GENERATING STATION l

SAFETY RELATED WORK ORDER LOG SALEM UNIT 2 i

WO NO DEPT UNIT EQUIPMENT IDENTIFICATION 0G99179458 SMD 2

22MS167 FAILURE DESCRIPTION:

VALVE WILL NOT OPEN FRCM CONTROL RM.

CORRECTIVE ACTION:

REPLACED BYPASS SOLENOID VALVE.

l 8508210728 SMD 2

21 BAT PUMP SEAL FAILURE DESCRIPTION:

THERE IS A SIIAFT SEAL LEAK ON THE PUMP.

A LARGE AMOUNT OF BORON ON THE FLOOR.

CORRECTIVE ACTION:

REPLACED MECHANICAL SEAL.

8509160830 SIC 2

R16 RECORDER FAILURE DESCRIPTION:

THE RECORDER IS NOT FOLLOWING COUNTS CORRECTLY FOR R16.

CORRECTIVE ACTION:

REPLACED BACKPLANE PC BOARD.

i I

8509270082 SMD 2

STNR BACKWASH STOP VALVE FAILURE DESCRIPTION:

THE VALVE WILL NOT CLOSE, THE HANDWHEEL SPINS FREELY.

CORRECTIVE ACTION:

REPLACED BONNET, DIAPHRAGM, INSPECTED, CLEANED AND LUBRICATED O-RINGS.

l

SALEM UNIT 2 WO NO DEPT UNIT EQUIPMENT IDENTIFICATION 8510070270 SCD 2

2PR17 FAILURE DESCRIPTION:

2PR17 WILL NOT MAKE UP ITS CLOSED LIMIT.

CORRECTIVE ACTION:

TROUBLE SHOT CIRCUITRY FOR 2PR17.

PROBLEM FOUND TO BE IN CABLE CONNECTOR AT RACK RC24-7 FOR CABLE 2AC 417/AT.

8510070296 SIC 2

2PR15 FAILURE DESCRIPTION:

2PR15 WILL NOT MAKE UP ITS CLOSED LIMIT.

CORRECTIVE ACTION:

REPLACED BAD CABLE WITH SPARE CABLE.

8510070300 SIC 2

R41 B FAILURE DESCRIPTION:

THERE IS NO SCAN AND NO REMOTE INDICATION FOR R41B.

CORRECTIVE ACTION:

FOUND CHANNEL "FFFEF" LOCKED UP.

POWERED OFF AND ON TO RESET.

VERIFIED SETPOINTS AND CHECKED SOURCE RESPONSE.

8510080046 SIC 2

2PS 3 FAILURE DESCRIPTION:

THE CONTROL AIR REGULATOR IS BLOWING AT PINHOLE ON DIAPHRAGM.

CORRECTIVE ACTION:

REPLACED REGULATOR WHICH IS SUPPLY REG FOR VALVE POSITIONER TO 2PS3.

BENCH SET REGULATOR PRESS.

t L

I I

SALEM GENERATING STATION MONTHLY OPERATING

SUMMARY

- UNIT NO. 2 OCTOBER 1985 SALEM UNIT NO. 2 The Unit began the period operating at full power.

On 10/07/85 at 1001 hours0.0116 days <br />0.278 hours <br />0.00166 weeks <br />3.808805e-4 months <br />, the Unit tripped coincident with a safety injection as a result of a voltage spike on the 2C Vital Instrument Bus.

The voltage spike was caused by the use of an improperly wired 115V receptacle.

On 10/09/85 at 2106 hours0.0244 days <br />0.585 hours <br />0.00348 weeks <br />8.01333e-4 months <br />, with the completion of investigations and repcirs, the Unit was placed on line and was returned to 100% power.

On 10/30/85 at 1515 hours0.0175 days <br />0.421 hours <br />0.0025 weeks <br />5.764575e-4 months <br />, the weld upstream of valve 2SJ168 was discovered to be leaking.

The repair involved tagging out both flowpaths to the Boron Injection Tank and entering Action Statement 3.0.3.

In accordance with the Action Statement, a unit shutdown was commenced at 2001 hours0.0232 days <br />0.556 hours <br />0.00331 weeks <br />7.613805e-4 months <br />.

Sub sequently, the repairs were completed and the shutdown terminated on 10/31/85 at 0056 hours6.481481e-4 days <br />0.0156 hours <br />9.259259e-5 weeks <br />2.1308e-5 months <br />.

At 0917 hours0.0106 days <br />0.255 hours <br />0.00152 weeks <br />3.489185e-4 months <br />, Unit 2 was restored to full power where it remained for the rest of the period.

I REFUELING INFORMATION DOCKET NO. :

50-311 COMPLETED BY:

J. Ronafalvy UNIT NAME:

Salem 2 DATE:

November 10, 1985 TELEPHONE:

609/935-6000 EXTENSION:

4455 Month October 1985 1.

Refueling information has changed from last month:

YES NO X

2.

Scheduled date for next refueling:

September 20, 1986 3.

Scheduled date for restart following refueling: November 19, 1986 4.

A)

Will Technical Specification changes or other license amendments be required?

YES NO Not determined to date B)

Has the reload fuel design been reviewed by the Station Operating Review Committee?

YES NO X

If no, when is it scheduled?

August 1986 5.

Scheduled date (s) for submitting proposed licensing action:

August 1986 if required 6.

Important licensing considerations associated with refueling:

NONE 7.

Number of Fuel Assemblies:

A)

Incore 193 B)

In Spent Fuel Storage 140 8.

Present licensed spent fuel storage capacity:

1170 Future spent fuel storage capacity:

1170 9.

Date of last refueling that can be discharged to spent fuel pool assuming the present licensed capacity:

March 2003 8-1-7.R4 t --

F O >SEG PubUc Service Electric and Gas Company P.O. Box E Hancocks Bridge. New Jersey 08038 Salem Generating Station Director, Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555

Dear Sir:

MONTHLY OPERATING REPORT SALEM NO. 2 DOCKET NO. 50-311 In compliance with Section 6.9, Reporting Requirements for the Salem Technical Specification, 10 copies of the following monthly operating reports for the month of October 1985 are being sent to you.

Average Daily Unit Power Level Operating Data Report Unit Shutdowns and Power Reductions Major Plant Modification Safety Related Work Orders Operating Summary Refueling Information Sincerely yours,..

g J. M.

Zupko, Jr.

General Manager - Salem Operations JR:sbh cc:

Dr. Thomas E. Murley Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA 19406 Director, Office of Management Information and Program Control U.S. Nuclear Regulatory Commission Washington, DC 20555 Enclosures 8-1-7.R4

/