RO 79-029/01X-0:on 790612,degradation of Primary Containment Integrity Occurred in Violation of Tech Specs 3.7.A.2.While Investigating,Disc in 6-inch Check Valve Was Removed, Violating Containment Integrity.Rept to Follow
ML20136B644
Person / Time
Site: Pilgrim
Issue date: 08/09/1979
From: Fulton J
BOSTON EDISON CO.
To:
References
NUDOCS 7909100072
Download: ML20136B644 (1)


Text

--

~

BOSTON EDlSON CO:!PANY TELECOPY }!ESSAGE 215-337-5272 Datc/ Time: ^"U"

/

To.

Telephone Number To: Director, Region I From: Pilgrim Nuclear Power Station l

Office of Inspection and Enforec=ent RFD #1 Rocky 11111 Road l

U. S. Nuclear Regulatory Commission Plymouth,11A 02360 631 Park Avenue King of Prussia, PA 19406

Subject:

PRO:IPT REPORTABLE dCCURRENCE Docket l'un.ber 50-293; License DPR-35 s

' Assigned LER Number 79-029/01X-0 Event

Description:

On June 12, 1979 while perfoming repcir's on the "A" Core Spray Systen minimum flow line, a degradation of primary contaic=ent integrity occurred.

This is a viola tiou of Tec'h. Spec. 3.7.A.2.

Cause and Corrective Action: While investigating problems with the Core Spray Loop "A" minicten flov line, the disc in the 6" check valve rc. quired repair and was removed and replaced, ' thus violating pricary containment integrity. This occurrence was identified during an unscheduled IE Inspection.

Facility Status:

100

% Thermal I!W c) Routine Startup g) Shutdown d) 1:outin: Shutdo.n h) Refueling o) Steady State X

i) Other f) Load Changing j) !!ot Applicaple

t. uritten follow-up report will be sent within tuo uccht.

NRC person notified

!!r. R. Architect Prep'ared by John M. Fulton 9v

\\

11:11 (2) copies to:

. :.J,,, *, [3 Director Of fico of !an.igement Infortation and Progra: Control va,.u..'ucle:e Regulatory Commission U. S. :

..tuu n.c.

20333 3

7 9Mio o q71~: _ m a,v.,