MONTHYEARML19311C3272019-10-25025 October 2019 Enclosure 12: Holtec International - Affidavit Project stage: Request ML20097E1902020-04-14014 April 2020 Request for Additional Information for the Review of the Model No. HI-STAR 100MB Package Project stage: RAI ML20136A4442020-05-14014 May 2020 Submittal Date for Responses to NRCs Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 Project stage: Request ML20205L5472020-07-23023 July 2020 Revised Submittal Date for Responses to NRCs Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 Project stage: Request ML20258A0522020-09-11011 September 2020, 14 September 2020 International Submittal of RAI Reponses for the Review of the Model No. HI-STAR 100MB Package License Amendment Request Project stage: Request ML20258A0542020-09-11011 September 2020 International - Submittal of RAI Reponses for the Review of the Model No. HI-STAR 100MB Package License Amendment Request Project stage: Request ML20258A0582020-09-11011 September 2020 Enclosure 3: HI-2188080, Revision 4, Safety Analysis Report on the HI-STAR 100MB Package Project stage: Other ML20258A0562020-09-14014 September 2020 Enclosure 1: Holtecs RAI Responses Project stage: Other ML20258A0682020-09-14014 September 2020 Enclosure 11: Affidavit Pursuant to 10 CFR 2.390 to Withhold Information from Public Disclosure Project stage: Other ML20258A0572020-09-14014 September 2020 Enclosure 2: Summary of Proposed Changes (Sopc) HI-STAR 100 Mb Transport LAR 9378-1 Project stage: Request ML21014A5032021-01-14014 January 2021 International, Submittal Date for Responses to NRCs Second Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1 Project stage: Request ML21120A1422021-04-29029 April 2021 Enclosure 9 - Affidavit of Kimberly Manzione Project stage: Other ML21120A1342021-04-30030 April 2021 Enclosure 2 - Holtecs Responses to Second RAIs Project stage: Other ML21120A1352021-04-30030 April 2021 Enclosure 3 - HI-2188080, Revision 5, Safety Analysis Report on the HI-STAR 100MB Package Project stage: Other ML21120A1322021-04-30030 April 2021 International Submittal of the Second RAI Reponses for the Review of the Model No. HI-STAR 100MB Package License Amendment Request Project stage: Request ML21133A2712021-05-20020 May 2021 Certificate of Compliance No. 9378, Revision 1 Project stage: Other ML21133A2702021-05-27027 May 2021 Cover Letter - Certificate of Compliance No. 9378, Revision No. 1, for the Model No. Hi-Star 100mb Package Project stage: Other 2020-09-14
[Table View] |
Text
KPS Technology Campus, 1 Holtec Blvd, Camden, NJ 08104 Telephone (856) 797-0900 Fax (856) 797-0909 Doc. I.D.: 5026005-NRC Page 1 of 1 May 14, 2020 Pierre Saverot, Project Manager - Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No.:
Docket No. 71-9378 (HI-STAR 100MB Model)
EPID: L-2019-LLA-0242
Subject:
Submittal date for Responses to NRCs Request for Additional Information (RAI) for HI-STAR 100MB Transport Package License Amendment Request 9378-1
Reference:
Request for Additional Information for the Review of the Model No. HI-STAR 100MB Package (Letter from Pierre Saverot (NRC) to Brian Seawright (Holtec) dated April 14, 2020)
Dear Mr. Saverot,
By letter dated April 14, 2020 (referenced), NRC staff documented their requests for additional information (RAI) that is required to complete the detailed technical review of the HI-STAR 100MB transport package amendment request 9378-1. NRC requested that Holtec provide additional information by May 30, 2020.
Due to the need for additional testing and benchmarking of material required to appropriately respond to NRCs request, Holtec is unable to submit additional information by May 30, 2020.
The RAI responses will be submitted to NRC staff on or before July 31, 2020.
If you have any questions, then please contact me at 856-797-0900, ext. 3931.
Sincerely, Brian Seawright Licensing Engineer Holtec International cc:
Andrea Kock, USNRC