ML20135J018

From kanterella
Jump to navigation Jump to search
Forwards LERs 85-018-00 & 85-019-00
Date released: 05/28/2020 Download: ML20135J018


:on 850821,determined That Seismic Qualification of Governors for turbine-driven Auxiliary Feed Pumps Inadequate for Approx 4 Yrs.Cause Not Stated.Governors as Installed Meet Current Seismic Requirements
ML20135J032
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 09/19/1985
From: Blind A
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
References
REF-PT21-85
Download: ML20135J032 (1)
:on 850820,ESF Actuation Occurred.Caused by Opening of Reactor Trip Breakers During Instrumentation Checks.Surveillance Test Procedure Thp 4030 STP.180 Revised
ML20135J021
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 09/19/1985
From: Blind A
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
References
Download: ML20135J021 (1)
Forwards LERs 85-018-00 & 85-019-00
ML20135J017
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 09/19/1985
From: Will Smith
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
NRC OFFICE OF ADMINISTRATION (ADM)
References
Download: ML20135J017 (1)