Docket Nos. 50-266 September 6, 1985 4
i and 50-301 Mr. C. W. Fay, Vice President Nuclear Power Department Wisconsin Electric Power Conpany 231 West Michigan Street, Room 308 Milwaukee, Wisconsin 53201
Dear Mr. Fay:
In conducting our review of your April 10, 1985 application relating to technical specification changes for the Point Beach Units 1 and 2 reactor coolant pump limiting conditions for operation, we have determined that we will need additional information identified in the enclosure to continue cur review.
In order for us to maintain our review schedufe, your response is requested within 45 days of your receipt of this letter.
I The reporting and/or recordkeeping requirements contained in this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Please contact us if you have any questions concerning this request.
Sincerely,
/S/
Edward J. Butcher, Acting Chief Operating Reactors Branch No. 3 Division of Licensing
Enclosure:
Request for Additional Infonnation cc w/ enclosure:
See next page Distribution:
0 ELD DocketiFile' BGrimes NRC & L PDRs PKreutzer Branch Files TColburn HThompson JGuttman ACRS 10 BSheron EJordan ORB #3:DLF ORB (5[;)b ORB #3 L r
TColburn;ef EBdtcher
/ 5 /85 Q/g'/85 9 / 6 /85 8509170346 850906 PDR ADOCK 05000266 P
_ _, ~ _ _. - _
Mr. C. W. Fay-Point Beach Nuclear Plant Wisconsin Electric Power Company Units I and 2 cc:
Mr. Bruce Churchill, Esq.
Shaw, Pittman, Potts and Trowbridge 1800 M Street, N.W.
Washington, DC 20036 Mr. James J. Zach, Manager Point Beach Nuclear Plant Wisconsin Electric Power Company 6610 Nuclear Road Two Rivers, Wisconsin 54241 Mr. Gordon Blaha Town Chairman Town of Two Creeks Route 3 Two Rivers, Wisconsin 54241 Chairman Public Service Commission of Wisconsin Hills Farms State Office Building Madison, Wisconsin 53702 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Office of Executive Director for Operations 799 Roosevelt Road Glen Ellyn, Illinois 60137 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, Wisconsin 54241 1
4 4
m o
REQUEST FOR ADDITIONAL INFORMATION WITH REGARD TO REACTOR COOLANT PUMP LC0 TECH SPEC CHANGE FOR POINT BEACH UNITS 1 AND 2 (Tac Nos.:
57555 and 57556) 440.1 Section 15.3.1.A.1.a.1 of the proposed revision to the technical specifications permits plant operation at 10% of rated power under an (N-1) loop configuration (e.g., 1 reactor coolant pump out of service).
Provide details of the bases for (N-1) loop operation and the associated modifications to the reactor protection system.
Provide the supporting FSAR transient and accident analyses which justify such operating modes.
440.2 Section 15.3.1.A.1.a.2 of the proposed revision to the technical specifications states that upon loss of one RCP, immediately initiate power reduction to less than 10% of rated power.
Address why a reactor trip would not occur on a low flow or low RPM signal.
How has the plant protection system been modified?
440.3 Section 15.3.1.A.1.a.3 of the proposed revision to the technical specifications states that if both RCPs cease to operate, the reactor shall be shutdown and the reactor trip breakers opened within one hour.
Justify power operation with both loops inoperable.
Justify
r 2
c an hour delay in activating a reactor trip.
Provide Supporting transient and accident analyses.
i 440.4 With regard to Section 15.3.1.A.1.b of the proposed revision to the technical specification, provide the basis for operating at a reactor coolant temperature greater than 350'F with all RCPs deenergized.
Provide transient and accident analyses in support of this mode of operation. Address compliance with the rules and regulations and address consequences of operator error and single failures.
440.5 Page 15-3.1-3a references analytical work in support of one reactor coolant pump operation at an average reactor coolant temperature above 350*F.
Provide this reference document, i