PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET P.O. BOX 8699 PHILADELPHIA. PA.19101 (215)841-4000 September 10, 1985 Docket No. 50-277 Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.
20555 Attention:
Document Control Desk Dear Sir Enclosed is the report of the Peach Bottom Atomic Power Station Unit 2 Reactor Containment Building Integrated Leak Rate Test (ILRT) which was conducted during June, 1985.
This report is submitted pursuant to Technical Specification 6.9.3.d and 10 CFR 50, Appendix J, Section V.B.,
with the guidance of Regulatory Guide 10.1.
Y u will note that the first attempted test (June 9, o
1985) was terminated primarily due to leakage through the valve packing of a torus vacuum relief valve, AO-2502B.
Identified leakage sources were repaired and a second ILRT was completed succcessfully on June 10, 1985.
Should there be any further questions, do not hesitate to contact me.
Very truly yours,
?
l
)
0 0509160007 0 277 ADOCK 050 R
W.
M. Alden PDR P
Engineer-In-Charge g
l i
Licensing Section Nuclear Services Enclosures cc:
Dr.. Thomas E. Murley, Administrator, Region I, USNRC l
T. P. Johnson, Fesident Site Inspector
.