Special Rept 96-03:on 961118,high Range Noble Gas Monitor Declared Inoperable.Caused by Parts Not Being Readily Available.Completed Repairs,Performed Post Maint Testing & Declared Monitor Operable
ML20135A983
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 11/27/1996
From: Bezilla M
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
96-03, 96-3, LR-N96393, NUDOCS 9612040118
Download: ML20135A983 (1)


Text

I I

a Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038-0236 Nuclear Business Unit NOV 2 71996 LR-N96393 1

United States Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555 Gentlemen:

SPECIAL REPORT 96-03 HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NO. NPF-57 DOCKET NO. 50-354 This Special Report is being submitted pursuant to the requirements of Hope Creek Technical Specification 3.3.7.5, ACTION 81 b, due to the North Plant Vent (NPV) high range noble gas monitor being inoperable.

On November 18, 1996, at 0847 hours0.0098 days <br />0.235 hours <br />0.0014 weeks <br />3.222835e-4 months <br />, Technical Specification Action Statements 3.3.7.5 and 3.3.7.11 were entered to perform preventative maintenance on the NPV.

This preventative maintenance included replacement of a power supply for the NPV high range radiation monitoring equipment.

While performing this preventative maintenance, the low range radiation monitor power supply failed.

Since replacement parts were not readily available, the NPV radiation monitoring equipment remained j

inoperable for a period greater than 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, which requires a Special Report.

.On November 21, 1996, repairs to the NPV low range radiation monitor power supply were completed and post maintenance testing was successfully performed.

At 1721 hours0.0199 days <br />0.478 hours <br />0.00285 weeks <br />6.548405e-4 months <br />, with the successful completion of the post maintenance testing, the NPV was declared operable and the Action Statements for Technical Specifications 3.3.7.5 and 3.3.7.11 were exited.

Should you have any questions or comments on this transmittal, do not hesitate to contact us.