|
---|
Category:GENERAL EXTERNAL TECHNICAL REPORTS
MONTHYEARML20210F8701999-07-22022 July 1999 Rev 1 to PGE-1076, Trojan Reactor Vessel Package Sar ML20209C6531999-07-0606 July 1999 Rev 8 to Defueled SAR, for Trojan Nuclear Plant ML20207J0781999-02-28028 February 1999 Update to Trojan ISFSI Sar ML20202G4511999-02-0202 February 1999 Rev 0 to PGE-1076, Trojan Reactor Vessel Package Sar ML20195J2501998-11-17017 November 1998 Rev 7 to Trojan Nuclear Plant Defueled Sar ML20155E0411998-10-27027 October 1998 Amend 7 to Quality-Related List Classification Criteria for Tnp ML20237B6121998-08-13013 August 1998 Revised Trojan Reactor Vessel Package Sar ML20236Y2691998-08-0808 August 1998 Revised Trojan Rv Package Sar ML20249B4081998-06-17017 June 1998 Rev 6 to Trojan Nuclear Plant Defueled Sar ML20203B0341997-11-26026 November 1997 Rev 5 to Trojan Nuclear Plant Defueled Sar ML20148E8631997-05-31031 May 1997 Amend 6 to PGE-1052, Quality-Related List Classification Criteria for Trojan Nuclear Plant ML20137K5811997-03-31031 March 1997 SAR for Rv Package ML20140D9451997-03-31031 March 1997 Tnp First Quarter 1997 Decommissioning Status Rept ML20135B5241996-11-27027 November 1996 Rev 4 to Trojan Nuclear Plant Defueled Sar ML20135B5341996-11-25025 November 1996 Trojan ISFSI Safety Analysis Rept ML20134F4661996-10-30030 October 1996 Final Survey Rept for ISFSI Site for Trojan Nuclear Plant ML20134P4321996-09-30030 September 1996 Tnp Quarter Decommisioning Status Rept,Third Quarter 1996 ML20137K5321996-09-0505 September 1996 Rev 0 to H Analysis of Residue Protocol ML20137H2841996-06-28028 June 1996 Evaluation of Residual Radionuclide Source Term at Trojan NPP at Start of Decommissioning ML20137K5091996-06-28028 June 1996 Summary Rept Poge Tnp SFP Project ML20149H1771994-11-10010 November 1994 Rev 1 to Trojan Nuclear Plant Defueled Sar ML20059A7041993-10-21021 October 1993 Errata to Rev 0 to Defueled Sar ML20059A7441993-10-0707 October 1993 Defueled SAR for Trojan Nuclear Plant ML17352A8691993-05-31031 May 1993 Technical Rept, Assessment of Aging Degradation of Civil/ Structural Features at Selected Operating Nuclear Power Plants. ML20127N8561993-01-18018 January 1993 Safety Review of Trojan Plant Restart:Steam Generator Deterioration & Interim Plugging Criteria ML20127M1241992-11-30030 November 1992 Rev 0 to IPE Rept for Trojan Nuclear Power Plant in Response to GL 88-20 ML20245E1081988-05-31031 May 1988 Pipe Whip Restraint Gaps Pressurized Surge Line Movement ML20197E3781988-05-29029 May 1988 Pipe Whip Restraint Gaps Pressurizer Surge Line Movement ML20148M9871988-03-15015 March 1988 Safety Evaluation of Emergency Ventilation Sys Design Mods ML20153G2211988-01-31031 January 1988 Toxic Chemical Study ML20236W7681987-10-31031 October 1987 Plant Safety Evaluation for Trojan Nuclear Plant Fuel Upgrade ML20236J5011987-08-31031 August 1987 Amend 4 to Trojan Nuclear Plant Analyses of Pipe Breaks, Outside Containment ML20237H2081987-08-10010 August 1987 Rev 0 to 01-0300-1629, Independent QA Audit & Technical Quality Review of Trojan Nuclear Power Plant Pipe Support Verification Program ML20236B0971987-07-31031 July 1987 Rev 0 to Evaluation of Ultrasonic Exam Indications on RCS Loop B Hot Leg Elbow for Trojan Nuclear Plant ML20236F1681987-07-31031 July 1987 Rev 1 to Summary Rept, Independent Review of Action Plan Items to Resolve Trojan Main Feedwater Piping Restraint Failure Issue ML20236F1531987-07-17017 July 1987 Final Rept Trojan Nuclear Plant SR8 Failure Root Cause Evaluation Steam Condensation-Induced Water Hammer ML20236B1371987-07-0101 July 1987 Rev 5 to Ultrasonic Insp of Statically Cast Stainless Steel Elbow at Trojan Nuclear Power Plant ML20215G6501987-06-30030 June 1987 Evaluation of Displacement at Main Feedwater Restraint SR4 in Trojan Nuclear Plant ML20215B8041987-06-30030 June 1987 Evaluation Rept of Trojan Nuclear Plant Main Steam Pipe Wall Thickness ML20215G6531987-06-11011 June 1987 Trojan Nuclear Plant Evaluation of Main Feed Line Seismic Restraint Failure ML20214A2941986-11-0404 November 1986 Portland General Electric Nuclear Plant Engineering Design Criteria:Extension of Automatic Sprinkler Sys Be (Rdc 84-048) Turbine Bldg Trojan Nuclear Power Plant ML20215N1671986-10-31031 October 1986 Rev 1 to, Leak-Before-Break Evaluation of Reactor Coolant Loop ML20207J6621986-07-31031 July 1986 Rept on Safety-Related Motor-Operated Valve Switch Setting Review & Testing Program for Trojan Nuclear Plant ML20198R9851986-06-30030 June 1986 Rev 0 to Evaluation of Reactor Coolant Loop for Restrained Thermal Expansion,Trojan Nuclear Plant, Summary Rept ML20203D5621986-06-17017 June 1986 Vol 2 of Amend 3 to PGE-1041, Dcrdr Summary Rept for Trojan Nuclear Plant ML20198S0511986-05-23023 May 1986 Interim Rept of Independent Review of Trojan Nuclear Plant Reactor Coolant Loop Thermal Movements Evaluation Program. Supporting Info Encl ML20197E7581986-01-31031 January 1986 Rev 0 to Preliminary Thermal Expansion Evaluation of Reactor Coolant Loop for Trojan Nuclear Plant ML20137H5981985-11-30030 November 1985 Review of Auxiliary Feedwater Sys for Reliability Improvements ML20138H8951985-06-30030 June 1985 Rev 0 to Leak-Before-Break Evaluation of Reactor Coolant Loop, Final Rept ML20136F2941984-06-30030 June 1984 Trojan Nuclear Power Plant Mod & Stress Analysis Rept for Pressurizer Safety & Relief Valve Small-Bore Piping Sys 1999-07-06
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20210F8701999-07-22022 July 1999 Rev 1 to PGE-1076, Trojan Reactor Vessel Package Sar ML20209C6531999-07-0606 July 1999 Rev 8 to Defueled SAR, for Trojan Nuclear Plant ML20206H4501999-05-0505 May 1999 Safety Evaluation Supporting Amend 201 to License NPF-1 ML20206C9351999-04-23023 April 1999 Safety Evaluation Supporting Amend 199 to License NPF-1 ML20206C9751999-04-23023 April 1999 Safety Evaluation Supporting Amend 200 to License NPF-1 ML20207G9881999-03-0303 March 1999 Rev 6 to Trojan Nuclear Plant Decommissioning Plan ML20207J0781999-02-28028 February 1999 Update to Trojan ISFSI Sar ML20202G4511999-02-0202 February 1999 Rev 0 to PGE-1076, Trojan Reactor Vessel Package Sar ML20207C6981998-12-31031 December 1998 1998 Annual Rept for Trojan Nuclear Plant. with ML20195J2501998-11-17017 November 1998 Rev 7 to Trojan Nuclear Plant Defueled Sar ML20155E0561998-10-29029 October 1998 SER Approving Two Specific Exemptions Under 10CFR71.8 for Approval of Trojan Reactor Vessel Package for one-time Shipment to Us Ecology Disposal Facility Near Richland,Wa ML20155E0411998-10-27027 October 1998 Amend 7 to Quality-Related List Classification Criteria for Tnp ML20154R4121998-10-0202 October 1998 Requests Commission Approval,By Negative Consent,For Staff to Grant Two Specific Exemptions from Package Test Requirement Specified in 10CFR71 for Trojan Reactor Vessel Package & to Authorize one-time Transport for Disposal ML20237B6121998-08-13013 August 1998 Revised Trojan Reactor Vessel Package Sar ML20151W5471998-08-13013 August 1998 Rev 22 to PGE-8010, Poge Nuclear QA Program for Trojan Nuclear Plant ML20236Y2691998-08-0808 August 1998 Revised Trojan Rv Package Sar ML20249B4081998-06-17017 June 1998 Rev 6 to Trojan Nuclear Plant Defueled Sar ML20203E6291998-02-28028 February 1998 Trojan Nuclear Plant Decommissioning Plan ML20198T1741998-01-0404 January 1998 Rev 5 to Trojan Nuclear Plant Decommissioning Plan ML20248K6891997-12-31031 December 1997 Enron 1997 Annual Rept ML20203J3821997-12-31031 December 1997 Annual Rept of Trojan Nuclear Plant for 1997 ML20248K6931997-12-31031 December 1997 Pacificorp 1997 Annual Rept. Financial Statements & Suppl Data for Years Ended Dec 1996 & 97 Also Encl ML20203B0341997-11-26026 November 1997 Rev 5 to Trojan Nuclear Plant Defueled Sar ML20199F8141997-10-21021 October 1997 Requests Approval of Staff Approach for Resolving Issues Re Waste Classification of Plant Rv ML20216F4291997-07-25025 July 1997 Requests Commission Approval of Staff Approach for Reviewing Request from Poge for one-time Shipment of Decommissioned Rv,Including Irradiated Internals to Disposal Site at Hanford Nuclear Reservation in Richland,Wa ML20141F2311997-06-24024 June 1997 Rev 3 to PGE-1061, Tnp Decommissioning Plan ML20148K3541997-06-0909 June 1997 Safety Evaluation Supporting Amend 198 to License NPF-1 ML20148E8631997-05-31031 May 1997 Amend 6 to PGE-1052, Quality-Related List Classification Criteria for Trojan Nuclear Plant ML20148D2681997-05-23023 May 1997 Safety Evaluation Supporting Amend 197 to License NPF-1 ML20141H3181997-05-19019 May 1997 Safety Evaluation Supporting Amend 196 to License NPF-1 ML20140D9451997-03-31031 March 1997 Tnp First Quarter 1997 Decommissioning Status Rept ML20137K5811997-03-31031 March 1997 SAR for Rv Package ML20136D5591997-03-0606 March 1997 Safety Evaluation Approving Merger Between Util & Enron Corp ML20134B6231997-01-15015 January 1997 Draft Rev 3 of Proposed Change to Trojan Decommissioning Plan ML20217M2381996-12-31031 December 1996 Portland General Corp 1996 Annual Rept ML20217M2471996-12-31031 December 1996 Pacific Power & Light Co (Pacifcorp) 1996 Annual Rept ML20217M2551996-12-31031 December 1996 1996 Enron Annual Rept ML20135C3521996-12-31031 December 1996 Annual Rept of Trojan Nuclear Plant for 1996 ML20132G2831996-12-19019 December 1996 Rev 2 to PGE-1061, Trojan Nuclear Plant Decommissioning Plan ML20132H0011996-12-12012 December 1996 Rev 20 to PGE-8010, Portland General Electric Nuclear QA Program for Trojan Nuclear Plant ML20132B8491996-12-12012 December 1996 Rev 20 to PGE-8010, Trojan Nuclear Plant Nuclear QA Program ML20135B5241996-11-27027 November 1996 Rev 4 to Trojan Nuclear Plant Defueled Sar ML20135B5341996-11-25025 November 1996 Trojan ISFSI Safety Analysis Rept ML20134M3381996-11-20020 November 1996 SER Approving Physical Security Plan for Proposed Trojan ISFSI ML20134K6621996-11-11011 November 1996 Decommissioning Plan,Tnp ML20134F1211996-10-31031 October 1996 Safety Evaluation Supporting Amend 195 to License NPF-1 ML20134F4661996-10-30030 October 1996 Final Survey Rept for ISFSI Site for Trojan Nuclear Plant ML20134P4321996-09-30030 September 1996 Tnp Quarter Decommisioning Status Rept,Third Quarter 1996 ML20137K5321996-09-0505 September 1996 Rev 0 to H Analysis of Residue Protocol ML20137K5091996-06-28028 June 1996 Summary Rept Poge Tnp SFP Project 1999-07-06
[Table view] |
Text
l l
I TROJ AN NUCLEAR PLANT QUARTERLY DECOMMISSIONING STATUS REPORT THIRD QUARTER 1996 l
l l
i l
961129008i 961106 PDR ADOCK 05000344 R paa
~
\
TABLE OF CONTEN.TS
- 1. ABSTRACT .. . . .
1 II. OCCUPATIONAL RADIATION EXPOSURE , . . . .2 III. COSTS (Based on the decommissioning cost estimate) .4 IV. SCHEDULE OF ACTIVITIES .
.7 i
l t i-l I. ABSTRACT 1 :
4 1
r .
- i During the first quarter of 1996, the majority of the activities at Trojan Nuclear Plant centered i around preparation and submittal of the license application under 10 CFR 72 for the Independent - l j Spent Fuel Storage Installation (ISFSI). The ISFSI license application was submitted to NRC by .
1- letter dated March 26,1996. - l 3 I f
l Decommissioning planning activities continued during the second and third quarters of 1996.' The 6
. primary focus was on preparing the site, including removing components, in preparation for other 4
decommissioning activities. The preparations included performing a radiation release survey for i j .- the future Independent Spent Fuel Storage Installation during the third quarter of 1996. l b . The State of Oregon Energy Facility Siting Council approved the Trojan Decommissioning Plan 1 !
I by Order dated March 14,1996. The Order Approving Trojan Decommissioning Plan contained !
! : nine conditions. Submittal of quarterly reports on the actual versus projected status of ' :
decommissioning satisfies Condition No. 2 of the Order. ;
j
~
I 4
i 6
)
h
~
r a
l 1
I l
l
}.
1
\
\
\
i II. OCCUPATIONAL RADIATION EXPOSURE :
l l
t N
2
l TABLE II-l OCCUPATIONAL RADIATION EXPOSURE (Through Third Quarter 1996)
Total Man-Rem Decommissioning Activity (Based on Decommissioning Plan Table 2.2-1) Actuallll %
Projected (Cummulative)
Steam Generators and Pressurizer Removal [2] 138 53.96 39.1 Reactor Vessel Internals Removal / Dismantlement 85 0 0.0 Dismantlement Activities (NSSS, BOPS, 282 35.234 12.5 Stnictures, Miscellaneous)
Spent Fuel Racks Dismantlement 19 0 0.0 Normal Plant Operations 9 2.978131 33.1 Fuel Transfer to ISFSI 58 0 0.0 591 92.172 15.6 Total I
Actuals are based on self-reading dosimeter results.
2 Large Component Removal Project completed November 1995.
3 Includes 0.632 person-rem from Security Personnel dostmeters.
1 3
1 l
l III. COSTS (Based on the decommissioning cost estimate) i O
I 4
TABLE 111-1 .
Trojan Nuclear Plant Actual Versus Projected Costs Through September 30,1996 Based on the Decommissioning Cost Estimate (Nominal S x 1000)
Year NRC Decommissioning Nonradiological Decommissioning Spent Fuel Management Financing Activity Combined Expenditures Expenditures Expenditures Expenditures Expenditures Projected Actual Projected Actual Projected Actual Pmjected Actual Projected Actual 1993 - - - - -
1994 7,595 7,386 0 7,595 7,386 1995 17,680 15,144 0 19.158 20,938 36,838 36,082 1996 12,595 5,667 301 6 24,484 11,348 37,380 17,021 1997 28,203 4,133 35,500 67,836 1998 40,163 506 25,592 316 66,577 1999 69,026 1,615 4,068 442 75,151 2000 62.327 1,676 4,257 1,986 70,246 2001 2,624 1,907 4,515 3,45I I2,497 2002 1,097 4,682 3,149 8,928 2003 991 4,851 2,818 8,661 2004 455 5,020 2,131 7,606 2005 472 5,189 1,244 6,905 2006 490 5,356 231 6,077 2007 509 5,519 17 6,045 2008 528 5,676 2 6,206 2009 548 5,826 6,374 Page 1 of 2
. - .. .. .. ~ ~ -. . - - . .. - .
~
Trojan Nuclear Plant ' '
Actual Versus Projected Costs Through September 30,1996 Based on the Decommissioning Cost Estimate (Nominal $ x 1000)
Year NRC Decommissioning Nonradiological Decommissioning Spent Fuel Management Financing Activity Expenditures Combined Expenditures Expenditures Expmhtures Expenilitures Projected Actual Projected Actual Projected Actual Projected Actual Projected Actual 2010 569 5,967 6,536 201I 591 6,094 6,685
.t 2012 613 6,325 6,938 2013 637 6,565 7,202 2014 661 6,815 7,476 2015 686 7,074 7,760 2016 712 7,343 8.055 2017 739 7,622 8,361 2018 26,557 53,903 80,460 2019 35,224 35,224 2020 827 827 2021 2,069 2,069 2022 2.129 2,129 2023 8,318 8,318 Total 240,213 28,197 95,561 6 267,401 32,286 15,787 -
618,962 60,489 Page 2 of 2
IV. SCHEDULE OF ACTIVITIES l l
Transition Period activities continued on schedule during the third quarter of 1996. l l
l Decontamination and removal activities, which are providing experience and information helpful to planning, continued with the removal of the Positive Displacement Pump.
Various components and structures were removed associated with configuring the plant for decontamination, packaging, and ease of movement of materials during full scale decommissioning. These included removing an area cooler and knockout panels on lower elevations of the Auxiliary Building. Work commenced on a new access through the north wall of the Auxiliary Building.
Component removal inside the Containment Building continued with removal of Reactor Coolant System piping and surrounding interferences. The primary purpose of component removals in the Containment is to reduce general area radiation levels. The reactor coolant pumps will be removed, packaged as their own shipping containers, and shipped to the U.S. Ecology site near lianford, Washington, during the fourth quarter of 1996.
Licensing activities continued in support of the Independent Spent Fuel Storage Installation (ISFSI) schedule. Responses to the State of Oregon's questions on the 10 CFR Part 72 license application submittal and the 10 CFR Part 50 License amendment submittal were completed. A radiation release survey commenced for that portion of the site on which the ISFSI will be located.
Design and analysis activities associated with shipment of the reactor vessel and the reactor internals as one package continued. A revision to the Decommissioning Plan will be submitted for EFSC approval during the fourth quarter of 1996.
The diesel fuel oil tanks were excavated and removed during the third quarter.
7
. . . . .- __ . - . . - . - ~
EARLY EARLY 1996 ACTIVITY ID START FINISH Jm i FEB l MAR I APR MAY JUN i JUL I AlfG SEP l OCT I NOV l DEO 3 Decommissioning Applications i l .*
DA1200 6 MAR 96A 27 jut 196A Punst T rerte nPetTeneTre .mmrurt einra a DA1280 8MAY96A 19DEC96
~
DA1330 IJUL96A 21tJOV96 ' " " '"
Facil,ofFutureDecom.Ahtivities i l 1 i FA1305 15JMJ96A Pun w T - W mt. swww uo? smP *newat I 16MAY96A Pira[F T - sw ahFI 90TIDTNG I FA1201 22JAt196A SSEP96A FunST T - MNTaippsFNt/Stormnat. I l 5 FA1260 1APR96A 190EC96 i l Pense TT'amTvTTTrs i i l i FA1400 9APR96A 27NOV96 { _ _ _,_
! l !
l FA1265 18NOV96 19DEC96 i S/G's SVPPORT ST E URES (PARMAL RDe,rALS)
Source Term Removal
{
SR100 1MAY96A 7.7JUtJ 96A "'
SR190
- a SR200 8JUL96A 30SEP96A Pt::r.it_.ES_I1E.1:12_t2_11nh131Lwall
, l SR300 10CT96A 11DEC96 P e TCPS f4)
, i SR400 11tJOV96 12DEC96 F Dry Storage Area Site Relpase dify 'n 21dg. to Accept P.adweste DS2150 26FEB96A 28 MAR 96A j l [
DS2390 P-v. w . rna er m t,t . 914, , stad a netitete, 1APR96A 1AUG96A DS2349 20MAY96A 25JUL96A p.- val er itPw P' H4 s Stab DS3050 SAUG96A 100CT96A i DFO Tank Removal DF1035 5AUG96A 15AUG96A E "****
Plot Date 11CET96 ==**n=r w a=5 ==**
Data cate 90cT96 H C** ".y"*' Trojan Nuclear Plant Portland General Electric Coppany Project Start IJAN94 O<* "* **n-ea, mes ane, Date Red don hkod hoM Project Finish 30SEP19 Quarterly Decom. Status Report (c) Primavera Systems, Inc.
3rd Quarter 1996
. _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . _ _ _ _ _ - _ _ _ _ _ _ _ _ _ -