ML20134P148

From kanterella
Jump to navigation Jump to search
Nuclear QA Program Manual
ML20134P148
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 07/05/1984
From:
HOUSTON LIGHTING & POWER CO.
To:
Shared Package
ML20134P098 List:
References
ETR-1001, ETR-1001-R08, ETR-1001-R8, NUDOCS 8509060147
Download: ML20134P148 (113)


Text

s-- -- - -- -- - -e ,. a - ---a r _s . -- s a_..- --- -- a,u ----. - - ---- -- n - - --- ---a-.

b EBASCO

! NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL

! ETR-1001 '

'l

O:a:O D

l HOUSTON LIGHTING & POWER COMPANY ELECTRIC GENERATING STATION UNITS 1 & 2 pBP 2868 Si8@p

UNITED STATES NUCLE AR REGULATORY COMMISSION W AS641N G T CN. D. C. 20555 MAY 121975 Mr. Leonard F. C. Reichle Vice President Ebasco Services Incorporated Two Rector Street New York, New York 10006

Dear Mr. Reichle:

We have reviewed and evaluated the Ebasco Services Incorporated (EBASCO)

Nuclear Quality Assurance Program Manual (Ebasco Report ETR-1001, Revision 0, March 14, 1975). We find that it describes an acceptable Quality Assurance Program for the design, procurement, and construction activities which are within the Ebasco scope of work for nuclear power plants.

For the Ebasco Quality Assurance Program, applicants need only reference this Topical Report .in Section 17 of license applications. We do not intend to repeat our review of this Topical Report when it is referenced in an application.

d Should regulatory criteria or regulations change such that our conclusions about this Topical Report are invalidated, we will notify you. You will be given the opportunity to revise and resubmit it should you so desire.

Please include a copy of this letter and our evaluation in each of the reports and resubmit 70 copies to the NRC.

i Sincerely, i

f Richard H. Vollmer, Chief Quality Assurance Branch Division of Reactor Licensing

(

Enclosure:

NRC Topical Report Evaluation of Ebasco Report EIR-1001,Rev. O, 3/14/75 4

40tuiso9 h &

'  ?

o

./ . g. ,. r.

S w . .,+

/

r

. . , . - - .,, - ,-,,.,-n

4 4

, TOPICAL REPORT EVALUATION Report Number: ETR-1001, Rev. O Nonproprietary

, Report

Title:

Ebasco Nuclear Quality Assurance Program Report Date: March 14, 1975 Originating Organization: Ebasco Services Incorporated Reviewed By: Quality Assurance Branch

SUMMARY

OF TOPICAL REPORT Topical Report ETR-1001, Rev. O describes the Quality Assurance (QA)

Program which the Ebasco Services Incorporated (Ebasco) applies to those design, procurement, and construction activities involving safety related structures, systems, and components of nuclear power plants within the Ebasco , scope of work. ETR-1001, Rev. O commits Ebasco to comply with the requirements of Appendix B to 10 CFR Part 50 and to follow the QA guidance provided by the NRC in: -
1. " Guidance on Quality Assurance Requirements During Design and Procurement Phase of Nuclear Power Plants," WASH 1283, Rev.1, May 24, 1974, and
2. " Guidance on Quality Assurance Requirements During the Construction Phase of Nuclear Power Plants," WASH 1309, May 10,1974.

Ebasco has provided for our evaluation a detailed organizational ~'

description of those individuals and groups involved in carrying out activities required by the QA Proiram and a delineation of duties, responsibilities, and authority of those organizational elements involved in the QA Program. ETR-1001, Rev. O contains a description of the measures used to carry out the Ebasco QA Program activities and l describes how applicable requirements of Appendix B will be satisfied by the administration and implementation of. these measures.

SLM1ARY OF REGULATORY EVALUATION We have evaluated the QA Program and the organizations responsible for QA functions as described in ETR-1001, Rev. O. We find that QA policy and direction originate at an acceptably high management level and are ef fectively communicated to other parts of the organization.

I Those performing QA functions have responsibility and authority commensurate with their duties in implementing the QA Program. We also find that measures have been establishec, to be Laplemented by written procedures and instructions, which address each of the criteria of Appendix B and '

demonstr' ate conformance with each criterion.

Based on our review and evaluation of ETR-1001, Rev. O we conclude that:

l

1. The organizations and persons performing QA functions within Ebasco e l have the required independence and autherity to ef f ectively carry out l the QA Program without reservation or undue influence from those directly l

A 2-responsible for costs and schedules, and

2. The Ebasco QA Program contains the necessary requirements, procedures, and controls to demonstrate that quality-related activities will be

, conducted in accordance with the requirements of Appendix B to 10 CFR Part 50.

REGULATORY POSITION 2

It is the staff's position that the Ebasco Nuclear Quality Assurance Program Manual (Ebasco Report ETR-1001, Revision 0, March 14,1975) is acceptable for use in the design, procurement, and construction of nuclear power plants. The Topical Report can be referenced by report ntsnber in Section 17 of future Safety Analysis Reports.

d

,- a , n n , . ~ - r i

~

y

[* "'% ', UNITED STATES NUCLEAR REGULATORY COMMISSION

$ , REGION IV D # $11 RYAN PLAZA DRIVE. SUITE 1000 '

'% , , , , , *#' ARLINGTON. TEXAS 70011 l NAY 04 1984 Docket No. 99900505 Mr. B. E. Tenzer, Vice President Corporate Quality Programs Ebasco Services, Incorporated Two World Trade Center New Ycrk, NY 10048

Dear Mr. Tenzer:

Subject:

NRC Acceptance of Revised Ebasco Quality Assurance Topical Report We have completed our review of Revision 12 to Ebasco Topical Report ETR-1001 submitted through your letters of May 27. July 13 August 5, September 23, October 7. October 31, and November 9,1983, and February 15, 1984. Revision 12 updates the topical report to reflect the current Ebasco Quality Assurance Program.

Based on our evaluation of the proposed changes described in Revision 12, we find that the revised topical report continues to meet the criteria

,of Appendix 8 to 10 CFR Part 50 and is, therefore, acceptable. Should regulatory criteria or regulations change such that our conclusions about

, this topical report are invalidated, we will notify you. You will be given the opportunity to revise and resubmit it should you so desire.

Progrannatic changes by Ebasco to this topical report are to be submitted to NRC for review prior to implementation. Organizational changes are to be submitted r:0 later than 30 days after announcement.

To use this topical report in future license applications, applicants need only reference this topical in Section 17 of the SAR. Should it be referenced in a SAR for a new nuclear power project, the basis of our evaluation will be the acceptance criteria in the latest revision to the Standard Review Plan (SRP) Section 17.1 (currently Revision 2). Appropriate

. changes may, therefore, be necessary.

Please replace our letter of May 17, 1982, with a copy of this letter, renumber ETR-1001 as Revision 12 and forward eight copies to the Document Control Desk and one copy to the Vendor Program Branch, Division of Quality Assurance, Safeguards, and Inspection Programs, U.S. Nuclear Regulatory Conmission, k'ashington, D.C. 20555.

I f

! s .1 a s . .. o e- a n

- e f 9 g l

T Mr. B. E. Tenzer Your submittal should point out the changes by use of a black bar in the margin where a change is made, and the revision number should be adjacent to the bar.

Should you have any questions regarding our review, or if we can provide assistance please contact this office.

Sincerely, r

Mk bA Uldis Potapovs. Chief e

Vendor Program Branch Division of Quality Assurance.

Safeguards, and Inspection Programs l

ESASCO SERVICES INCORPORATED O Two World Trace Center New York.N Y.10048 STATDENT T AlmORITY

'Ibe canagenent of he Services Incorporated recognizes the necessity for a ca prehensive Quality Pr% ian for Nuclear Power Plants. Ebasco Capany Procedure No. N-21 establishes the basic organization, assigns authorities and responsibility for inplementing the Quality Program, and establishes the requirement for a corporate Quality Assurance Manual. Accordingly, this Manual represents Ibasco Quality Progra policy. In this respect, it is to be used as a standard by perscnnel in all h e orgardzational units.

'Ihe primary responsibility for overall inplanentation and adninistration of the Ibasco Quality AssuraT.e Progra rests with the Vice President Corporate Quality Programs as delegated to him by the President. 'Ihe Quality Pr% tan Ccmnittee has been established under the auspices of the President, consisting of representatives of designated Vice Presidents. 'Ihe Ccruittee is pemanent and its Chair-man shall be the Vice President Corporate Quality Programs.

R'S Christesen President June 29,1984 i

I

i l

l l

ESASCO SERVICES INCORPORATED EKO Two World Trade Center.New York N Y.10048 l

l I

EURDORD

'1his manual represents Ebasco Quality Pr@sma policy and requir ments for the design, construction, retrofit and maintenance of nuclear power stations under the jur4= dim tion or in accordance with the requirments of the United States Nuclear Regulatory Cmmission. In this respect, it is to be used as a standard by all Sha m personnel.

'Ibe manual has been prepared by the Quality Assurance organizaticm and approved by the Ibasco Quality Progra Cm mittee. 'Ihe manual reflects official Ibasco policy and has been designed to meet the requirments of the Unitsi States Nuclear Regulatory Camission docment 10 CFR 50, Appendix B (18 Quality Assurance Criteria), and American Naticral Standards Institute docment N45.2, entitled Quality Assurance PrWimn Requirments for Nuclear Power Plants.

'Ihe Ibasco Nuclear Quality Assurance Program Manual has been designed to meet the requirments of 10 CFR 50.34(7) for a quality assurance program description. It will be incorporated into applicable porticms of safety analysis reports by reference as provided by 10 CFR 50.32.

'Ihe primary responsibility for overall ir:pimentation and achinistration of the Ebasco Quality Program rests with the Vice President Corporate Quality Prweano as delegated to him by the President. The Director Quality Assurance is assigned the responsibility and authority to enforce Ebasco Quality Progre requirments and has the ungmlifled support of corporate managment. His decisions may not be overridden by personnel in any division or department, except with the written consent of the Vice President Corporate Quality Programs or the President.

1

ESASCO SERVICES INCORPORATED EKO ,

Two World Trade Center, New York. N Y 10048 l

l

'Ihe Director Quality Assurance shall staff each project to the extent necessary to perfo m Quality Assurance 4 tasks directly and audit departments other than his own in their perfomance of tasks related to Quality Assurance.

'Ibe Director Quality Assurance has the authority to require immarmte correction of any non-ocnfoming activity or condition to caply with ham Quality Prwiau require-ments, or if necessary, to stop work until suitable wit ctive acticn has been taken or a satisfactory resolution reached.

Wtions or questicms regarding the Quality PrWima or the manual shall be referred to the Director Quality Assurance, who shall be responsible for resolution. 'Ihe Ebasco Quality Progra Ccznmittee is responsible for and has the authority to make and approve procedures for any changes to this manual.

'Ihe Quality PrWiau Coordinator, designated by the Chaiman 1 of the ham Quality PrWiau Cmmittee, functions as the Ccamittee's Secretary and publishes to all manual holders an UpdatingStatusMemorande for the manual at least every six m mths. 'Ihe F=murardtzn stamarizes changes made to the manual during the preceding period. 'Ibe Quality Prwtau Coordinator also maintains a listing of individual pages in the manual which indicates the current issue or revision date of each page.

Infomation frran this list can be obtained by addressing inquiries to the Quality Pmpau Coordinator at the Ebasco New York Office.

'Ihe manual is assigned by the Quality PiWiau Coordinator to individuals as required for their exclusive use. However, it rarains the property of Ebasco Servicer Incorporated and shall be returned upon request. It is loaned in confidence and upon the conditicn that neither it nor the infomation contained in it will be repivduced, copied or disclosed in whole or in part.

The material herein is copyrighted and protected by the copy-right laws. 4 a

2

~

ESASCO SERVICES INCORPORATED EKO Two World Trace Center New York.N Y 10048 Should any ciramtance arise under which a holder no langer requires the manual for the specific purpose for which it was assigned, it shall be returned pIntptly to the Quality FrWimu Coordinator. Nuclear Quality Assurance manuals shall not be transferred or loaned to any other individual, position, fim or corporation without the written authorizaticn of the Chaiman of the Ebasco Quality Frwimu Camittee. 'Ihe Quality FrWimu Coordinator shall be infomed pruiptly of any change in the mailing address of a manual holder.

Manual holders are respcmsible to maintain their copies in updated condition, including the proper insertion of new or revised secticms as furnished and the destructicn of all cancella1 or superseded sections. Sections shall not be removed fra manuals except as directed for revision or cancellation.

BE L ~

B E Tenzer V Vice President Corporate Quality Progras June 29,1984 3

ei

. s tos-s istp> s se pace 1 or 2 EBA$CO SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION tNcompomAtto MOU$ TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNIT 31 & 2 g g R7

- . TABLE OF CONTENTS oate 7/5/84

.. . m m . . .y, . .. .. . .. .

y ,

Rev. No. Date Introduction & Scope of Services 5 7/5/84 PART I - General Section Title Rev. No. Date QA-I-l Quality Assurance Program 6 7/5/84 QA-I-2 Organization and Responsibilities 6 7/5/84 QA-I-3 Personnel Indoctrination and Training Program in Quality Assurance 4 7/5/84 QA-I-4 Deleted (not applicable)

QA-I-5 Deleted (not applicable)

QA-I-6 Quality Assurance Records 4 7/5/84 PART II - Engineering Offices l

Deleted (not applicable)

PART III - Construction Site Section Title Rev. No. Date QA-III-1 Instructions, Procedures, and Drawings 4 7/5/84 QA-III-2 Document Control e 5 7/5/84 QA-III-3 Deleted (not applicable)

QA-III-4 Deleted (not applicable)

QA-III-5 Deleted (not applicable)

QA-III-6 Nonconformances 4 7/5/84 QA-III-7 Corrective Action 4 7/5/84 QA-III-8 Control of Special Processes 5 7/5/84

l

. sios <stei s-es pace 2 or- 2 ,

ESA5CO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION

! QNCompORATED MOU5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT I ELECTRIC GENERATING STATION UNIT 51 & 2

+ > 8 me vision l R:

a - N oitecto oupin assuna.ca TABLE OF CONTENTS o.ve 7/5/84 v l 4

PART III - Construction Site (Cont'd)

Section Title Rev. No. Date 0 QA-III-9 Quality Assurance Audits 5 7/5/84 QA-III-10 Identification and Control of Items 3 7/5/84 QA-III-11 Inspection 5 7/5/84 QA-III-12 Test Control 4 7/5/84 1

Control of Measuring and Testing QA-III-13 Equipment 4 7/5/84 QA-III-14 Control of Receiving, Handling, and Storage 5 7/5/84 QA-III-15 Inspection. Test, and Operating Status 3 7/5/84 Appendix I Terms and Definitions 3 7/5/84 i

Appendix II Ebasco Exceptions to US Nuclear Regulatory Guides and ANSI Standards Indicated in Section QA-I-1 4 7/5/84 I

T e sos 4 tsvei se4 nace 1 o, 2 EsA5c0 SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION INCORPORATED MOU5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT I ELECTRIC GENERATING STATION UNITS 1 & 2

> arvision 5 l R7 N

. . mo. g.u .. .. . .. u LNTRODUCTION & SCOPE OF SERVICES o*te 7/5/84 e  !

Introduction The Ebasco Quality Assurance Program to be used on the South Texas Project is described in this Manual. It is based on the Ebasco Nuclear Quality Assurance Program Manual, ETR-1001 Rev. 12, which was accepted by the United States lR7 Nuclear Regulatory Commission on May 4, 1984. ETR-1001 Rev. 12 represents l Ebasco Quality Program policy and requirements for the design and construction of nuclear power stations under the jurisdiction of or in accordance with the requirements of the United States Nuclear Regulatory Commission. In this respect, it is the standard which is used by all Ebasco personnel. Ebasco's commitment to Quality is confirmed in the " Statement of Authority" signed by the President of Ebasco Services Incorporated.

This Manual, as modified for the South Texas Project, is assigned by the Quality Program Coordinator via the Manager Site Quality Assurance to individuals as required for their exclusive use. However, it remains the property of Ebasco Services Incorporated and shall be returned upon request.

It is loaned in confidence and upon the condition that neither it nor the information contained in it will be reproduced, copied, or disclosed in whole or in part, except for its incorporation into applicable portions of Houston Lighting & Power Company safety analysis reports. The material herein is copyrighted and protected by the copyright laws.

Scope of Services Ebasco Services Incorporated's scope of services for the South Texas Project includes construction services as well as quality assurance and quality control appropriate to these services. The design and procurement sections of ETR-1001 Rev. 12 are not applicable to Ebasco Services Incorporated's scope of lR7 services. Those responsibilities are assigned to the Client or his designee.

The remainder of ETR-1001 Rev. 12 has been modified as appropriate for the lR7 South Texas Project and approved in accordance with applicable Company Procedures.

Although Section QA-III-1, " Instructions, Procedures, and Drawings," contains certain requirements relating to control of drawings, the Client or his designee is the Architect / Engineer and will issue all design drawings. Ebasco may, however, from time to time, initiate drawings which are not design documents, when authorized by specifications issued by the Client or his designee.

I .

s tes.s astet s se paog 2 o, 2 ESA$CO SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTioM INComDOmaTED MOUSTON UGHTING AND POWER CowPANY SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 5 l 8 INTRODUCTION & SCOPE OF SERVICES oare 7/5/84 oitecto. ojpur, asso. ca V g Ebasco performs quality trend analysis on a corporate basis as described in Sections QA-I-1, QA-III-6, QA-III-7, and QA-III-9 of this Manual. This trend analysis is a corporate-wide compilation and analysis of quality data generated by the Quality Assurance organization in conjunction with the various projects on which Ebasco is performing nuclear safety-related activities and is not related to the specific South Texas Project trend analysis program. The Client is responsible for the performance of quality trend analysis specific to the South Texas Project.

i 4

)

J l

4

a a

I -

1 s tos4 istpl 5-e4 pact 1 or 20 j ESASCO SERvlCES NUCLEAR QUALITY AS$URANCE PROGRAM MANUAL $ ECTION

sNcompomATEo NOUlTON LIGNTlWG AND PoeER C0aPANY gg.I.1

, SOUTH TEXA5 PROJECT

= ELECTRIC GENERATING STATION UNITS 1 & 2

.g v, ,,o q g g  ;

R7

  • QUALITY ASSURANCE PROGRAM Sat 7/5/84 oinscron ayytin .sso. cc v l 1.0 SCOPE The purpose of this Section is to describe the Quality Assurance Program of

! Ebasco Services Incorporated and its applicability to safety-related activities and services performed by Ebasco in the construction of tne

! South Texas Project. This program has been designed to meet the applicable requirements of the United States Nuclear Regulatory Commission 18 Quality Assurance Criteria of 10 CFR 50, Appendix B. It has also been designed to meet the regulatory position of the following USNRC Regulatory Guides and ANSI Standards, with exceptions and clarifications as stated in Appendix II of this Manual:

Standard Title i ANSI N45.2-1971 Quality Assurance Program R.G. 1.28 (Rev. O, 6/72) Requirements for Nuclear Power Plants ANSI N45.2.1-1973 Cleaning of Fluid Systems and

! R.G. 1.37 (Rev. O, 3/73) Associated Components During (See Appendix II Notes 3 through 5) Construction Phase of Nuclear Power

. Plants ANSI N45.2.2-1972 Packaging, Shipping, Receiving,

R.G. 1.38 (Rev. O, 3/73) Storage, and Handling of Items 4

(See Appendix II Notes 6 through 11) for Nuclear Power Plants (During the Construction Phase)

ANSI N45.2.3-1973 Housekeeping During the

> R.G. 1.39 (Rev. O, 3/73) Construction Phase of Nuclear

> (See Appendix II Notes 12 and 13) Power Plants l

, ANSI N45.2.4-1972 Installation, Inspection, and R.G. 1.30 (Rev. O, 8/72) Testing Requirements for

(See Appendix II Notes 14 and 15) Instrumentation and Electric

, Equipment During the Construction j of Nuclear Power Generating

! Stations i

ANSI N45.2.S-1974 Supplementary Quality Assurance j (See Appendix II Notes 1 and 2) Requirements for Installation, Inspection, and Testing of Structural Concrete and i Structural Steel'During the

4 Construction Phase of Nuclear j Power Plants

l stos4:stplkaa paog 2 ,, 20 EsASCO SERVICES MUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION tNcomponATro MOU5 TON UGHTING AND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

,, g y, ,, o ,, 6 l R7 QUALITY ASSURANCE PROGRAM cart 7/5/84

oaccropaun assou cc 7 g Standard Title ANSI N45.2.6-1973 Qualifications of Inspection, R.G. 1.58 (Rev. O, 8/73) Examination, and Testing Plus Positions C.5, C.6, C.7, Personnel for the Construction C.8, and C.10 of Rev. 1 Phase of Nuclear Power Plants ANSI N45.2.8-1975 Supplementary Quality Assurance R.G. 1.116 (6/76) Requirements for Installation, (See Appendix II Notes 16 through 18) Inspection, and Testing of Hechanical Equipment and Systems for the Construction Phase of Nuclear Power Planta a

ANSI N45.2.9-1974 Requirements for Collection, Storage, R.G. 1.88 (Rev. 2, 10/76) and Maintenance of Quality Assurance (See Appendix Il Notes 19 through 21) Records for Nuclear Power Plants ANSI N45.2.10-1973 Quality Assurance Terms and R.G.1.74 (Rev. O, 2/74) Definitions ANSI N45.2.12-1977 Requirements for Auditing of Quality R.G. 1.144 (Rev. 1, 9/80) Assurance Programs for Nuclear Power (See Appendix II Note 22) Planta ANSI N45.2.23-1978 Qualification of Quality Assurance R.G.1.146 (Rev. O, 8/80) Program Audit Personnel for Nuclear Power Plants i

i Table 1-1.1 provides a matrix which shows the sections of the Ebasco Nuclear

) Quality Assurance Program Manual that correspond to the requirements of

10 CFR 50, Appendix B and USNRC Regulatory Guide 1.28, Rev. O. The Ebasco
Quality Assurance Program is comprised of The Elasco Nuclear Quality

( Assurance Program Manual, written corporate policies, procedures, departmental instructions, and drawings related to quality. Table I-1.2 provides a matrix

! of the principal implementing procedures as they relate to 10 CFR 50, Appendix B criteria. Table I-1.3 is a listing of these procedures by title.

The principal implementing procedures are not necessarily limited to those indicated in the matrix. Implementing procedures will be issuud for South Texas Project use as the need for specific procedures arises due to changes in scope of Ebasco safety-related activities.

l l

i l

l l

. . io. is t m .. ..cc 3 or 20 EsASCO SERvlCES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION

'NCo"Po**TED NOU$ TON UGHTlWG AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-1

{ ELECTRIC GENERATING STATION UNITS 1 & 2 n g v,,,o n 6 g R7'

- QUALITY ASSURANCE PROGRAM cart 7/5/84 v ,

The Ebasco Nuclear Quality Assurance Program Manual has been designed to meet the requirements of 10 CFR 50.34(7) for a quality assurance program description. It will be incorporated into applicable portions of Houston Lighting & Power Company safety analysis reports in whole or by reference as provided by 10 CFR 50.32.

The Ebasco Quality Program for the South Texas Project is in force at the Ebasco home office and Construction operations. The Ebasco home office is an organized unit where project-related support functions are performed.

Construction operations encompass those activities related to the construction of the nuclear power station. Ebasco's responsibility for implementing the Ebasco Quality Program shall begin at the commencement of activities affecting quality and shall end with the turnover of completed systems to the Client or his designee.

Definitions pertaining to the Ebasco Quality Program are listed in Appendix I of this Manual.

2.0 QUALITY ASSURANCE ORGANIZATION l lR7 The Ebasco Quality Assurance organization is responsible for establishing new, I and updating existing, quality assurance requirements. In addition, this organization is responsible to administer and enforce the implementation of lR7 the Ebasco Quality Assurance Manual.

3.0 OUALITY PROGRAM COMMITTEE 3.1 The Ebasco Quality Program Committee is responsible for and has authority to make and approve procedures for any changes to this Manual.

This committee is comprised of representatives of International l Operations, Corporate Engineering and Consulting Services, Advanced l Technology, Project Procurement, Project Management Services, Corporate l Quality Programs, Envirosphere Company, Ebasco Plant Services Inc, and l Ebasco Constructors Inc. These representatives are appointed by the Vice lR7 President of the respective organizational area. l l

The Vice President Corporate Quality Programs is designated by the l President as the Chairman of the Quality Program Committee. A member of l the Quality Assurance organization shall be designated by the Chairman as l Quality Program Coordinator, who shall function as the Quality Program Committee's secretary and be a member of the Committee.

The Director Ouality Assurance is designated by the Vice President l Corporate Quality Programs as a permanent representative of Corporate lR7 Quality Programs on the Quality Program Committee. ,

l

l I

stos4astetFe4 pact 4 o, 20 EBASCO SERVICES HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN INcompoM ATED MOU$TDM UGHTING AND POWER COMPANY QA-I-1

, SOUTH TEXA5 PROJECT

ELECTRIC GENERATING STATloM UNITS 1 & 2 6 g

,g w ,, o q R7

! QUALITY ASSURANCE PROGRAM cave 7/5/84

. .....,,..........e j The Committee shall be responsible for and shall have authority to make I any' changes to the policies and procedures of the Ebasco Quality Program. All changes or revisions to the Ebasco Quality Program shall be processed through the Quality Program Committee by the Quality Program Coordinator.

3.2 Ebasco Quality Program Procedures document the various significant activities of the Quality Program that are the direct responsibility of the Quality Program Committee or the Quality Program Coordinator. These procedures include but are not limited to the following:

3.2.1 Quality Program Procedure No. 4 entitled, QUALITY PROGRAM COORDINATOR - DESCRIPTION OF POSITION, DUTIES, RESPONSIBILITIES.

3.2.2 Quality Program Procedure No. 5 entitled, DEVIATING FROM THE lR7 CORPORATE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL. This l provides for control of such deviations by requiring execution of an

authorization form involving approval of specified authorities to

! assure, among other things, that safety and/or quality will not be sacrificed.

3.2.3 Quality Program Procedure No. 6 entitled, ASSIGNMENT,

DISTRIBUTION AND CONTROL OF THE EBASCO NUCLEAR QUALITY ASSURANCE l PROGRAM MANUAL.

3.2.4 Quality Program Procedure No. 7 entitled, REVISIONS TO THE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL.

4.0 GENERAL i

4.1 Section QA-I-2 of this Manual describes the organizational structure, functional responsibilities, levels of authority, and lines of internal and external communication for management, direction, and

, execution of the Ebasco Quality Assurance Program. By the Statement of Authority at the front of this Manual, Ebasco's President mandates the

. company-wide use of this Manual and its supporting documents which make up the Ebasco Quality Program.

4.2 It shall be the responsibility of each Ebasco department and the

, individual personnel of that department to adhere to the requirements of I this Program. Section QA-III-1 of this Manual requires these departments to develop and control instructions, procedures, and/or drawings which describe the manner in which activities affecting quality are to be accomplished. When documented evidence is required for the satisfactory performance of these activities, checklists, forms, and/or other appropriate means shall provide this evidence. The documents which l contain the procedures listed in Table 1-1.3 and are used to implement

the Ebasco QA Program ares l

N-

. 6 tos-s isTPI s-se PAGE 3_._or 20 EsA$Co SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL $ECTioN INCORPORATED HOU$ TON UGHTING AND POWER COMPANY OA-I-l SOUTH TEXA5 PROJECT d ELECTRIC GENERATING STATION UNIT $ 1 & 2 aa vision 6 l

R7

,, QUALITY ASSURANCE PROGRAM 0^ve 7/5/84 1

4.2.1 Quality Assurance Procedures Manual for South Texas Project l lR7 4.2.2 Site Quality Assurance Procedures Manual for l South Texas Project 4.2.3 Quality Program Procedures Manual 4.2.4 Company Procedures Manual - Nuclear 4.2.5 Quality control Procedures Manual for South Texas Project l lR7 4.2.6 Site Quality Assurance Instructions Manual for l South Texas Project 4.2.7 Construction Procedures Manual - Administrative Site lR7 Procedures for South Texas Project 4.2.8 Construction Procedures Manual - Construction Site lR7 Procedures for South Texas Project 4.2.9 Construction Procedures Manual - Construction Maintenance lR7 Instructions for South Texas Project The above-listed manuals may also contain departmental working procedures which do not describe activities affecting quality and therefore are not governed by the requirements of this Manual. Furthermore, certain implementing procedures may require changes in order to suit unique client requirements; such procedures for the South Texas Project will be included in a project manual of procedures and/or a site manual. In this case, the changed procedure shall be designated a Project Procedure.

These procedures will be subject to controls similar to those applicable to the original documents.

4.3 In addition to the requirements of Section QA-III-1 of this Manual and Paragraph 4.2 above, Section QA-III-8 of this Manual further assures control over quality-related activities by requiring that special processes shall be performed in accordance with written qualified procedures, and that they shall be performed only by qualified

. personnel. All qualifications shall be in accordance with applicable codes, standards, specifications, and other requirements as applicable.

The Ebasco Quality Program provides for the verification,of quality requirements through written policies, procedures, and instructions for the performance of inspections and tests. These inspections and tests 1

] are performed on services provided by Ebasco. All inspections shall be '

performed by individuals other than those who performed the activity.

I

- _ - . . .. - . .. . .. . ~ . . . - - . _ . _~ . - . . - ,.

, l l

i l sio isrei s-e4 nace 6 o, 20 j EsASCO SERvlCEs NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION

mcommon Ateo NOUSTON UGHTING AND POWER COMPANY 4 QA-1 , SOUTH TEXA5 PROJECT g ELECTRIC GENERATING STATION UNITS 1 & 2 6 l R7 :

M QUALITY ASSURANCE PROGRAM oate 7/5/84

ornicron giry assunamCE i V I

i 5.0 INDOCTRINATION AND TRAINING j Section'QA-I-3 of this Manual provides for the company-wide indoctrination and

, training of Ebasco personnel engaged in activities subject to the requirements j of the Ebasco Quality Assurance Program. The objectives of the training program are to familiarize applicable Ebasco personnel with this Quality 4

Assurance Program Manual and the implementing procedures identified in Table I-1.3. Overall responsibility for training as delineated in Section QA-I-3 rests with the Quality Assurance organization. lR7 1

l 6.0 REVIEW OF QUALITY PROGRAM ADEQUACY 6.1 The adequacy of the Ebasco Quality Program is reviewed on a regular j basis. The determination of program adequacy is based on audit results l and trend analyses. . Section QA-III-9 of this Manual provides for the i

performance and follow-up of audits by Site Quality Assurance and home j office Quality Assurance Engineering and of management audits of the

Materials Applications and Quality Assurance functions.

6.2 Audits performed by home office Quality Asaurance Engineering and lR7 i Site Quality Assurance are designed to evaluate the Quality Program l effectiveness on a project basis. When corrective action is necessary, re-audits are scheduled to assure implementation of corrective action.

j Section QA-III-9 of this Manual defines review activities and reports involved in the auditing function.

I j 6.3 Information on audits performed by home office Quality Assurance j Engineering and Site Quality Assurance shall lie submitted to the Quality 3 Assurance Engineering Supervisor of Auditing. He shall make an analysis

of the available quality data with respect to quality trends and report the result at least semi-annually to the appropriate executive level 1 of management for review and assessment in accordance with Quality Assurance Procedure QA-D.3. The Vice President Corporate Quality lR7

. Programs shall be responsible for initiating the implementation of any l l changes or corrective action deemed necessary to improve the j effectiveness of the Ebasco Quality Assurance Program.

t I

h l

1

7 s tos-s tstri koa pace 7 or 20 EBASCO SERVICES HUCLEAR QUALITY A550RANCE PROGRAM MANUAL SECTION INcompomarco HOU$ TON UGHTING AND POWER COMPANY gg_7_y

$0UTH TEXA5 PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 n e vi sio,. 6 l

o rc 7/5/84

[ , , , , , , QUALITY ASSURANCE PROGRAM lR7 1

- TABLE I-1.1 MATRIX OF COMPLIANCE TO USNRC 10 CFR 50 APPENDIX B AND ANSI N45.2 10 CFR 50 ANSI N45.2 Ebasco Nuclear Quality Assurance Appendix B Criteria Paragraph Program Manual Section I 3 QA-I-2 II 2 QA-I-1, QA-I-3 III 4 Not Applicable to Ebasco STP Work Scope IV 5 Not Applicable to Ebasco STP Work Scope V 6 QA-III-1 VI 7 QA-III-2 VII 8 Not Applicable to Ebasco STP Work Scope VIII 9 QA-III-10 IX 10 QA-III-8 X 11 QA-III-11 XI 12 QA-III-12 XII 13 QA-III-13 XIII 14 QA-III-14 XIV 15 QA-III-15 XV 16 QA-III-6 XVI 17 QA-III-7 XVII 18 QA-I-6 XVIII 19 QA-III-9

e sos.e istPt s.e4 esoE 8 o, 20 ESASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCOMPORATED HOUSTON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-1 d ELECTRIC GENERATING STATION UNITS 1 & 2 R E VIss ON 6  :

I C

N oraccron yAir, assuaaact QUALITY ASSURANCE PROGRAM o*TE 7/5/84 lR7 g

v g I

I

.g E-': '5 l 1 y st!g Y

l l

1 I

r.g i l

j:ag!.7 '

It l

}il I 1

=

- s

. . .- l

. 52  ;  ;

! :8 :_

s.: e. . =. *. =. I ,{ .

' l v2*L  ::  ??  ?{  : f I

.. Iu I"IE fil hh hi Y9 h ih! h I l

=

=  !

E 3-:. e i

< - -- . Ta-

.~ ~ - . i 3 Ol'i 7 ~77 :7 /? 7 7 I 3

?h hhh i h i hh ih hi I 4

' - ,a , .. l

~

l'

-e .t

? [?4 {

T 'I t:' l

. gE re;? O # 17 i . / 211 lR7 2

di5}a!lE

=E t i9 i ?h? *? :Y Y ?d I l

!s a * .

l ise rii- V. Y. - -

Y. .i I

22-  ; - - - - , . v.,

2 y v y 1 Y t y tey l 5 1::r!

-4 1 1

  • I

_N ~ ~ _ . -

l 1 . t t t t t

.s a s . .: i I 28:^ 8 V. f. ;.9 i

=:s: f. f. . V.

1::

-JI s g gs

. .T g.

~

T T

s T ITag .

1 l

- l T ada: -2 .

.8 4 /. A at  !

__.- a - 'T.J, 2 .: ass 9.9.$.49._ e_a ,::

~

s s

.t

~

l

- a  ; 22: es 7 . 7 :

_ :: a -

- a .: I

$h'2g

!L . . . .. :r -

  1. 7~7-f ~;.- { t .:

~ ~; * - " *414 -*a a da J Ja ; .:

s 7 ?? ?  ? t7 7 tiv$9ff7 .

? :1 .::  ; 7; 7 77 ;; l I

I
  • 1 4  !

y *g ,4 ".  %. O.

l I

8

_ _ _ = l Si _ = .  : 5  : -  : 55 5: E55 l

r

. s tos-s isTPi s e4 pace 9 o, 20 ESASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN eNCORPORATED MOU57oN LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-1

{ ELECTRIC GENERATING STATION UNIT 51 & 2

, , y, 3, , ,

6 l E

lRs I

=

N QUALITY ASSURANCE PROGRAM cart 7/5/84 g oraccron o,,g.n muunaaca V

TABLE I-1.3 PRINCIPAL IMPLEMENTING PROCEDURES Procedure No. Title NUCLEAR PROCEDURES (N) lR7 N-21 Nuclear Quality Program Authorization and Implementation N-23 Reporting a Defect / Noncompliance to the NRC N-24 Ebasco Management Quality Assurance Audit Committee QUALITY CONTROL PROCEDURES (QCP, NDE, AND QC) lR7 QCP-1.1 Quality Control Organization and Responsibilities QCP-2.1 Indoctrination, Training and Qualification of Quality Control Personnel to ANSI N45.2.6 Requirements

,, QCP-2.2 Indoctrination, Training and Qualification of Quality Control Personnel to ASME Section III, Division 2 Requirements QCP-6.1 Preparation, Review and Approval of Quality Control Procedures i

QCP-6.2 Document Control QCP-6.3 Quality Control Review of Incoming Revisions /

Changes to Bechtel Specifications and Procedures QCP-9.1 Weld Inspection, Piping - ASME QCP-9.3 Inspection of Post-Weld Heat Treatment QCP-9.4 Verification of Weld Filler Material Control i QCP-9.5 Weld Inspection (AWS)

L

c-o

. siew istei s se ..cc 10 o, 20 EsASCO SERVICES HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomaTro MouSTON UGNTING aND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATloN UNIT 51 & 2

, g y, ,, o , 6 l R7

a. QUALITY ASSURANCE PROGRAM oate 7/5/84 v

Procedure No. Title QUALITY CONTROL PROCEDURES (Cont'd) lR7 QCP-10.1 Cadweld Inspection QCP-10.2 Preplacement Concrete Inspection QCP-10.3 Concrete Placement Inspections QCP-10.4 Post-Placement Concrete Inspection QCP-10.5 Inspection of Structural Steel Erection and Bolting QCP-10.6 Stud Welding Inspection QCP-10.7 Miscellaneous Metal Fabrication Inspection QCP-10.8 Protective Coatings Inspection QCP-10.9 General Inspection QCP-10.10 Soils Inspection QCP-10.11 Mechanical Equipment Installation Inspection QCP-10.12 Pipe Support Installation Inspection QCP-10.13 Mechanical Instrumentation Installation Inspection QCP-10.14 System / Subsystem Walk-Down Inspection QCP-10.15 Electrical Equipment Installation Inspection QCP-10.16 Inspection of Electrical Raceways QCP-10.17 Electrical Cable Installation Inspection QCP-10.18 Electrical Cable Termination Inspection QCP-10.19 Inspection of Concrete Expansion Anchors, Rock Bolts, and Core Drilling QCP-10.20 Electrical Penetration Installation Inspection IR7 a_._____

.ie,4 istei s.e4 nace 11 o, 20 Esasco services NUCLEAR QUALITY A550RANCE PROGRAM MANUAL SECTioN encomponATED MOU$ TON UGHTING AND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT i

{ ELECTRIC GENERATING $TATloM UNITS 1 & 2 atvmow 6 l R7

  1. W o "accro. jpu n anu...ca QUALITY ASSURANCE PROGRAM oat: 7/5/84 v I Procedure No. Title QUALITY CONTROL PROCEDlIRES (Cont'd) lR7 QCP-10.21 HVAC Duct / Hanger Installation Inspection QCP-10.22 Receipt Inspection lR7 t QCP-10.23 Waterstop/ Joint Filler / Sealer Material Inspection QCP-10.24 Grouting Inspection QCP-10.25 Inspection of Bending and Fabrication of Reinforcing Steel QCP-10.26 Quality control Verification of Equipment or lR7 Component Interchange l 1

QCP-10.27 Modification / Removal Control Procedure QCP-10.28 Control of Inspection Stamps QCP-11.1 Hydrostatic and Pneumatic Pressure Test Inspection QCP-11.2 Duct and Housing Leak Test Inspection lR7 QCP-12.1 Calibration and Control of Hessuring and Test Equipment QCP-13.1 Storage and Maintenance Inspection / Verification QCP-13.2 Verification of Rigging and Handling Activities QCP-13.3 Housekeeping Inspections QCP-14.1 Status Control QCP-15.1 Identification and Control of Discrepancies and Nonconforming Conditions 4

QCP-15.2 Stop Work Order 1

QCP-15.3 Control and Processing of Transition Phase Deficiencies and Conditions

r stos s astri Ses p a c t _l.1,o r _20 EsASCO SERvlCEs NUCLEAR QUALITY A55URANCE PROGRAM MANUAL SECTION

  1. NcompomATEo MOUST04 UGHTING AND POWER COMPANY OA-I-l SO JTH TEXA5 PROJECT f ELECTRIC C ENERATING STATION UNITS 1 & 2 ng y,s,ou 6 l i

lRe I

QUALITY ASSURANCE PROGRAM oave 7/5/84 g o.recto.jp u n ... ...c6 I

Procedure No. Title QUALITY CONTROL PROCEDURES (Cont'd) lR7 QCP-16.1 Corrective Action QCP-17.1 Quality Assurance Records QCP-17.2 Preparation, Issuance, and Control of ASME Nameplates / Data Reports NDE-002-1 Radiographic Standards for Welds and Components l l

NDE-002-2 Procedure for the Calibration and Operation of the l Radiographic Densitometer l I

NDE-005-1 Ultrasonic Examination (Thickness Measurement) l 1

NDE-005-2 Ultrasonic Examination of Pipe Welds and Components l lR7 NDE-005-3 Ultrasonic Examination of Structural Welds i I

NDE-006-1 Liquid Penetrant Examination l NDE-007-1 Magnetic Particle Examination Procedure NDE-009-1 Visual Examination of NF Welds QC-100 Preparation, Control and Distribution of NDE Procedures (with Addenda A) l SITE QUALITY ASSURANCE INSTRUCTIONS (QAI) lR7 QAI-001 Site QA Organization and Responsibilities QAI-002 Preparatioa, Review, Distribution and Control of Supplements to quality Assurance Procedures QAl-003 Indoctrination,'4 raining, Qualification and Certification of b!te Quality Assurance Audit Personnel QAI-004 Issuance and Processing of Nonconformance Reports l

sics 4 st pi v u nace 13 ,, 20 EBASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION eNCompoMATED MOU$ TON UGHTING AND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

, g y, ,, ,

6 l R;

QUALITY ASSURANCE PROGRAM oave 7/5/84 MN,m . ........

Procedure No. Title SITE QUALITY ASSURANCE INSTRUCTIONS (Cont'd) lR7 QAI-005 Review and Approval of Quality Control and Construction Procedures QAI-006 Audit of Ebasco Site Organization by the Client, Bechtel, Ebasco Home Office, Code or Regulatory Agency

] QAI-007 Reportable Deficiencies QAI-010 Site Quality Assurance Records QAI-011 Corrective Action and Stop Work Authority lR7 QAI-012 General Surveillance Instruction QAI-013 Preparation, Conducting, Documenting and Logging of Audits QAI-014 Quality Assurance Review of Radiographs QAI-015 Procedure for the Calibration and Operation of the Radiographic Densitom2ter QAI-016 Control of Site Quality Records QAI-017 QA Review of Incoming Revisions to Bechtel and Houston Lighting & Power QA Program Documents QAI-018 Quality Assurance Indoctrination and Training Program QAI-019 Safety-Related Documentation Turnover Packages QUALITY ASSURANCE PROCEDURES (QA) lR7 QA-G.1 Preparation and Control of Quality Assurance Engineering Department Procedures QA-G.2 Control and Distribution of Project-Related Hanuals

, - - r- e ne - - -

o ]

stoo a ister s se , ace 14 odO_

EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTlON iNcompomAtto HOUSTON bGHTING AND POWER COMPANY QA-I-l SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 6 l R7

- QUALITY ASSURANCE PROGRAM oatt 7/5/84

.. . ,y . . . . . .. . .. . ,

Procedure No. Title QUALITY ASSURANCE PROCEDURES (Cont'd) lR7 QA-G.3 Qualification of QA Audit Personnel QA-G.3.1 Qualification of Inspection, Examination and Testing Personnel QA-G.4 Quality Assurance Engineering Records QA-D.3 Determination and Analysis of Quality Trends QA-D.4 Resolution of External Audit Findings QA-D.5.2 Site Audit Procedure SITE QUALITY ASSURANCE PROCEDURES (QAS) l l

QAS-1 Planning of Site Quality Assurance Engineering l Activities l I

QAS-2 General Audit Procedure l 1

QAS-3 Processing of Quality Assurance Engineering l Audit Reports l l

QAS-4 Quality Assurance Records Audit i I

QAS-5 Material Receipt Audit l lR7 QAS-6 Material and Component Storage Audit l l

QAS-8 Calibration and Gage Control Audit l l

QAS-9 Document Control Audit l l

QAS-11 System Turnover Audit l l

QAS-12 Civil Activities Audit l I

QAS-13 Structural Steel Audit l l

QAS-14 Reinforcing Steel Audit l

sios-s estai s e4 nace 15 or 20 ESA5C0 SERvlCE5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION eNcompomaTED HOU5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-l

{ ELECTRIC GENERATING STATION UNITS 1 & 2 ng y,g,o, 6 l R:

< QUALITY ASSURANCE PROGRAM o*TE 7/5/84 ci.ccroge.un ano. ca Procedure No. Title SITE QUALITY ASSURANCE PROCEDURES (Cont'd) l l

QAS-15 Protective Coating Audit l l

QAS-16 Welding Material Control Audit l l

QAS-17 Welding Qualification Audit l l

QAS-18 Mechanical and Welding Activities Audit l lR7 QAS-19 Nondestructive Examination Audit l 1

QAS-20 Radiographic Review Audit l l

QAS-21 Electrical Activities Audit l 1

QAS-22 Instrumentation Activities Audit l l

QAS-23 Quality Assurance Instructions l

, ADMINISTRATIVE SITE PROCEDURES (ASP) lR7 ASP-1 Preparation of Site Procedures ASP-2 Organization and Responsibility ASP-3 Material Requisition

ASP-4 Heavy Handling and Rigging ASP-5 Material Control ASP-6 Document Control ASP-7 Field Change Notice Procedure ASP-8 Preparation and Transmittal of Quality Assurance Records ASP-9 Construction Turnover / Release for Test ASP-10 Configuration Control lR7

E' eios-e istm s... nace 16 ,, 20 EaAsco services NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTlON

  1. NconsomaTED MOU$ TON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-l

{ ELECTRIC GENERATING STATION UNITS 1 & 2

,, , 6 l a A QUALITY ASSURANCE PROGRAM care 7/5/84 oiaccron yrv .ssu ca i v g Procedure No. Title ADMINISTRATIVE SITE PROCEDURES (Cont'd) lR7 ASP-11 Field Change Request ASP-12 Development of Construction Field Sketches ASP-13 Start-up Work Request lR7 ASP-14 Impact Review of Bechtel/HL&P Issued Documents ASP-15 Stop Work Procedure ASP-16 Corrective Actions ASP-17 Design Change Package l lR7 ASP-18 Modification of Equipment / Component Tags l ASP-32 Maintenance of Construction Equipment ASP-33 Nonconformances ASP-34 Indoctrination and Training ASP-82 Fire Prevention and Fire Protection CONSTRUCTION SITE PROCEDURES (CSP) lR7 CSP-1 Excavation and Backfill CSP-2 Installation of Permanent Electrical and Mechanical Plant Equipment CSP-3 Control of Lifting Apparatus CSP-4 Concrete Placement CSP-5 Duct and Housing Leak Test lR7 CSP-6 Installation of HVAC Hangera l

, CSP-7 Pipe Support Installation ,

I

(

eice-s isten s.se ..og 17 o, 20 EsasCO $ERVICES HUCLEAR QUALITY A$$URANCE PROGRAM MANUAL SECTION

'NCC"'OR AT E D MOU5 TON LIGHTING AND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNIT 51 & 2

_ g y, o, 6 g

[b

.. . u . . og ,, . . .. . .. .

QUALITY ASSURANCE PROGRAM onre 7/5/84 i

Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd) lR7 CSP-8 Cable Terminations and Splices CSP-9 Installation of Duct and Duct. Accessories CSP-10 Erection and Bolt-up of Structural Steel CSP-11 Storing, Installation, Cadwelding, Fabrication and Modification of Rebar CSP-12 General Instructions for Housekeeping During Construction CSP-13 Concrete Core Drilling CSP-14 Control of Material for Temporary Construction lR7 CSP-16 Piping Installation Procedure CSP-17 Hydrostatic and Pneumatic Testing CSP-18 Soil Test Fill Procedure CSP-19 Safety and Non-Safety Related Cable Pulling CSP-20 Construction Survey Activities CSP-21 Field Preparation and Coating of Surfaces Outside the Reactor Containment Building CSP-22 Valve / Pump Work lR7 CSP-24 Reactor Coolant Pump Volute Final Setting CSP-25 Temporary Equipment Site Tagging Procedure CSP-26 Reactor Vessel Final Setting CSP-27 Steam Generator Final Setting CSP-29 Reactor Vessel Internals Handling and Assembly a

. stow estei s.e. nacc 18 o, 20 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION

* c o a a o a

  • T E C HOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-l ELECTRIC GENERATING STATION UNITS 1 & 2 6 g R7 N QUALITY ASSURANCE PROGRAM care 7/5/84 oincronovyp,assu===ca Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd) lR7 CSP-30 Field Preparation and Coating of Surfaces Inside the Reactor Containment Building CSP-31 Piping System Cleanliness CSP-32 Insulation Resistance Testing CSP-33 High-Potential Testing lR7 CSP-34 Control and Verification of Survey Equipment CSP-35 Installation of Post-Tensioning Trumplate Assemblies and Sheathing CSP-36 Data Collection to Support Geotechnical Monitoring Program CSP-37 Crane and Hoist Load Testing CSP-38 Equipment or Component Interchange CSP-39 Vendor's ASME Code Data Plate Modifications CSP-40 EE580 Electrical Installations lR7 CSP-41 Installation of Expansion Type Anchors CSP-43 Installation of Electrical Raceways CSP-44 Installation of Electrical Penetration Assemblies CSP-47 Instrumentation Installation lR7 e

CSP-48 Instrumentation Tubing and Supports Fabrication and Installation CSP-49 Permanent Plant Equipment Site Tagging Procedure ,

CSP-54 On-Site Shop Fabrication lR7 CSP-55 Field Fabrication of Reinforcing Steel

. s ies-s isrei s-es pace 19 0, 20 ESA$CO SERVICES NUCLEAR CUALITY ASSURANCE PROGRAM MANUAL SECTION INCORpORATc0 HOU$ TON UGHTING AND POWER COMPANY QA-I-1 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

, g v, ,, o q 6 l R7 N QUALITY ASSURANCE PROGRAM oate 7/5/84 oingcrom maj4Av assunuct Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd) lR7 CSP-57 Shop Fabrication of ASME Section III Parts, Appurtenances, Piping Subassemblies and Component Supports CSP-60 Rigging for Setting Steam Generator CSP-61 Rigging for Setting Pressurizer CSP-62 Rigging for Setting Reactor Vessel CSP-63 Rigging for Setting Unit #2 Reactor Head CSP-64 Rigging for Setting Unit #2 Reactor Internals CSP-65 Reactor Coolant Pumps Rigging and Installation lR7 CSP-81 Welder Qualification CSP-82 AWS Dl.1 Structural Welding CSP-83 General ANSI B31.1 Welding Requirements for Piping and Hangers CSP-84 General ASME Section III Welding Requirements for Piping and Hangers CSP-85 Post-Weld Heat Treatment CSP-8 6 Repairs of ASME Section III and ANSI B31.1 Piping and Components CSP-87 Welding Procedure Specification Qualification CSP-88 Weld Filler Material Control CSP-89 Field Welding and Repair of Aluminum Bronze ECW [ Essential Cooling Water] Piping CSP-90 Welding Documentation CSP-91 Issuance and Control of Purge Dans

. stos4tsTP)ba4 Pact 20 or 20 EBA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomaTED HOUSTON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-l

{ ELECTRIC GEhERATING STATION UNITS 1 & 2 n t v, ,, o n g g R7

< QUALITY ASSURANCE PROGRAM o*TE 7/5/84 o accron ougrv anumance Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd) lR7 CSP-92 Control of Aluminum Bronze Material for Backing Rings lR7 CSP-93 control of Weld Filler Material For Non-Permanent Plant Maintenance CSP-94 Maintenance, Calibration and Repair Program for Dimetrics Automatic Welding Equipment CSP-95 General Welding Requirements for HVAC CSP-96 Request for NDE CONSTRUCTION MAINTENANCE INSTRUCTIONS (CMI) lR7 CMI-l Caring and Maintenance of Permanent Plant Items QUALITY PROGRAM PROCEDURES (QPP) l lR7 QPP-4 Quality Program Coordinator - Description of l Position, Duties, Responsibilities QPP-5 Deviating from the Corporate Ebasco Nuclear lR7 Quality Assurance Program Manual QPP-6 Assignment, Distribution and Control of the lR7 Ebasco Nuclear Quality Assurance Program Manual QPP-7 Revisions to the Ebasco Nuclear Quality lR7 Assurance Program Manual l

l l

I

4 s ios e istri s.e4 nace 1 or 13 i

i ESASCO SERVICES MUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORPORATED NOU$ TON UGHTING AND POWER COMPANY QA-I-2 SOUTH TEXA5 PROJECT N ELECTRIC GENERATING STATION UNITS 1 & 2

> 6 l R c VISION MMocaceton aujpn muu ca ORGANIZATION AND RESPONSIBILITIES oare 7/5/84 R7-i j 1.0 SCOPE

! This Section of the Manual describes the organizational structure, functional l responsibilities, levels of authority, and lines of internal and external

! communication for management, direction, and execution of the Ebasco Quality ,

< Program. It is recognized that quality assurance is an interdisciplinary function and not the sole domain of a single quality assurance group; for that reason, this Section of the Manual includes organizational and functional descriptions of several departments in addition to that organization whose lR7

sole function is quality assurance.

1 2.0 GENERAL

j. 2.1 The Ebasco operations organization consists of five independent l 3

quality-related principal divisions headed respectively by Group Vice l l Presidents of Engineering, Construction and Plant Services, Advanced I i

Technology and Special Projects, and International Operations; and the 1 3'

Vice President of Corporate Quality Programs. Each of these officers of l the company report to the Ebasco President and Chief Operating Officer. l 4 Quality-related subdivisions or subsidiary companies are headed by l j officers reporting to Group Vice Presidents. Reporting to the l j Engineering Group Vice President are the Senior Vice President of I i

Corporate Engineering and Consulting Services; the Vice Presidents of l  ;

Project Management Services, Project Procurement, and Project Engineering and Design; and the President of Envirosphere Company. Reporting to the Construction and Plant Services Group Vice President are the Presidents of Ebasco Constructors Inc, and Ebasco Plant Services Inc. Reporting to  ; R7 l the Advanced Technology and Special Projects Group Vice President is the l l Vice President of Advanced Technology. l

! I i 2.2 Representatives of the Ebasco Group Vice President International l Operations; of the Ebasco Senior Vice President of Corporate Engineering l 4

and Consulting Services; of the Ebasco Vice Presidents of Advanced l Technology, Project Procurement, Project Management Services, and l Corporate Quality Programs; and of the Presidents of Ebasco subsidiaries l Envirosphere Company, Ebasco Plant Services Inc, and Ebasco Constructors l Inc, comprise the Quality Program Committee which is responsible for l Ebasco Quality Assurance policy. This Committee is shown diagrammatically l in Figure 1-2.1 at the end of this Section. I I

2.3 The Ebasco organizational units most directly involved in the l implementation of the Quality Assurance program for fabrication and installation are Corporate Quality Programs, and Ebasco Constructors Inc. IR7 i

The organizational structures of these are shown in Figures I-2.2 and I-2.4 at the end of this Section. '

lR7 l - __ _. . _ - . _ . = - . . - -. ... -

- sio 4 <srei m ,.or 2 ,, 13

^

EBA5CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECT 10N INcomromATro NOU$ TON UGNTING AND POWER COMPANY QA-I-2 SOUTH TEXAS PROJECT f ELECTRIC GENEP4 TING STATION UNITS 1 & 2 6 l R7 N ORGANIZATION AND RESPONSIBILITIES onre 7/5/84 e,m . 3,o r. ...... .

v i i.

The responsibilities cf the individual Ebasco organizational units for lR7 quality assurance requirements applied'to nuclear power stations are described herein.

3.0 CORPORATE QUALITY PROGRAMS lR7 Primary responsibility for quality assurance rests with the Vice President Corporate Quality Programs who reports directly to the President. l Qualification requirements for the position of Vice President Corporate lR7 [

Quality Programs are: Bachelor of Science Degree in Engineering; 10 to I

l 15 years of experience in qdality-related work or equivalent experience in j the engineering or construction of a nuclear power plant, including at least

10 years experience in responsible managerial project positions; and a l i thorough, knowledge of the Ebasco Quality Assurance Program. The Corporate IR7 Quality Programs unit is comprised of the following organizations, each of I which contributes directly to the implementation of the Quality Program (see Figure I-2.2)

a) Quality Assurance lR7 b) Materials Applications

] c) Vendor Quality Assurance i d) Quality Assurance Consulting Engineer i e) Materials Engineering Laboratory 3.1 Quality Assurance is administered by the Director Quality Assurance l

, who reports to the Vice President Corporate Quality Programs. lR7 Qualification requirements for the position of Director Quality l l

Assurance are: Bachelor of Science Degree in Engineering; 10-15 years I 7 of experience in quality-related work or equivalent experience in the engineering or construction of a nuclear power plant, including at least

, . 5 years experience in responsible managerial project positions; and a thorough knowledge of the Ebasco Quality Assurance Program. Quality I R7

Assurance is responsible to plan implementation of, evaluate, monitor, l and enforce the Ebasco Quality Program. This responsibility is carried out by five functional subdivisions:

I a) Quality Assurance Projects l I

b) Quality Assurance Site Services

~lR7 I

c) Quality Assurance Engineering l

(

[

_ _ . _ _ , _ _ . .. _ _ . , . _ . . , , . - _ . _ . _ . -. .. ._. 1-. . - ---

Y

, sioe4isreisaa pace 3 o, 13 ESA5CO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION eNCORpomATED MOUSTON LIGHTING AND POWER COMPANY QA-I- 2 SOUTH TEXA5 PROJECT .

f ELECTRIC GENERATING STATION UNIT 51 & 2 mtvisio n 6 l a ORGANIZATION AND RESPONSIBILITIES o*Te 7/5/84

, oiaccron oggin assuaa ca l d) Inservice Inspection / Nondestructive Examination Services l I

e) Quality Assurance Consulting lR7 i

Managers in charge of the subdivisions report directly to the Director l

Quality Assurance. Engineers and Specialists are then assigned to l ,

j- specific projects from these subdivisions. The Quality Assurance

!' Organization is shown in Figures I-2.6 and I-2.7 at the end of this l Section. The organization and responsibilities of the four Quality l Assurance subdivisions associated with the South Texas Project are

~

j l described in the following paragraphs. I i 1 3.1.1 Quality Assurance Site Services - The Quality Assurance Site l

, Services subdivision is headed by the Manager Quality Assurance Site l Services who is responsible for all site-related Quality Assurance / lR7 Quality Control activities, including implementation of the site l l phase f,or all Ebasco project quality programs. . A Manager Site l Quality Assurance, who reports to the Manager Quality Assurance Site l Services, and a Quality Program Site Manager, who reports to the l j Director Quality Assurance, are responsible for Quality Program l l implementation for the South Texas Project in accordance with the l following: l l

3.1.1.1 Site Quality Assurance - The Manager Site Quality Assurance, who reports to the Manager Quality Assurance Site R7 Services in New York, is responsible-for the development,

, maintenance, and current status of Site Quality Assurance l Procedures, for providing technical assistance and guidance l to subordinate Quality Assurance Site Supervisors s'ad staff, l

and for distribution and control of quality assurance manuals, as well as changes thereto, for the South Texas-Project. (See Figures I-2.2 and I-2.6.) The Manager Site Quality Assurance has delegated authority to the Quality r' Program Site Manager on the preparation, review, approval, and , distribution control of Site Quality Control Procedures and project-related supplements to the Site Quality Assurance Procedures.

i 3.1.1.2 Site Quality Program - A Quality Program Site Manager is assigned to the construction site on a resident basis forithe purpose of overall planning,-direction, and implementation of the Ebasco Nuclear Quality Assurance IR7 Program Manual. The Quality Program Site Manager, who reports to the Director Quality Assurance, is subordinate to lR7 no individual on site and has the independent authority to i

identify site quality-related prablems, to initiate or ,

s

. stos-a 15Tp) 5-84 pace 4 or 13 EBASCO SERVICES NUCLEAR QUALITY AS$URANCE PROGRAM MANUAL S ECT10N iNeomponATeo HOUSTON LIGHTING AND POWER COMPANY SOUTH TEXAS PROJECT OA-I-2 i ELECTRIC GENERATING STATION UhlTS 1 & 2 at vmoN 6 l

R:

n,,,,,, ORGANIZATION AND RESPONSIBILITIES o*TE - 7/5/84 I

recommend solutions, to control existing nonconformances, to verify implementation of approved dispositions, to direct efforts to obtain ASME Certificates of Authorization for Ebasco as may be required for the South Texas Project, to represent the Ebasco Quality Assurance organization with lR7 regard to South Texas Project activities, such as Client or his designee and/or Ebasco meetings, Client or his designee audits, management audits, and, when necessary, to stop work. He is responsible to assure that all personnel working for him are qualified for their respective positions and properly trained. The Director Quality Assurance has lR7 delegated authority to the Quality Program Site Manager on the preparation, review, approval, and distribution control of project-related supplements to the applicable Quality Assurance Procedures. The Site Quality Program function is divided into three groups: Quality Assurance, Quality Control, and Quality Records, each reporting through a respective supervisor to the Quality Program Site Manager.

(See Figure I-2.6.)

3.1.1.2.1 Site Quality Assurance - A Quality Assurance Site Supervisor and staff of engineers and representatives are assigned the following functions:

a) Review and audit safety-related site lR7 construction and engineering activities and records on a continuing basis.

b) Perfor:n audits and surveillances of construction forces for adherence to prescribed approved procedures.

c) Review and advise on quality control procedures, construction procedures, I and nondestructive examination lR7 procedures for compliance with this l Manual and code and regulatory requirements. When necessary, the Quality Assurance Site Supervisor may request the Manager Site Quality Assurance to assist in the review of l quality control procedures.

! d) Generate records of all reviews and audits performed.

stco s asTPt 5-se Pact 5 o, 13 EBA$CO SERvlCE5 NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION sNeompomarzo NOU5 TON UGHTING AND POWER COMPANY gg_1 2 SOUTH TEXAS PROJECT f

o ELECTRIC GENERATING STATION UNITS 1 & 2

,g g 3, o y 6 l g R., -

=

O ORGANIZATION AND RESPONSIBI'ITIES o*TE -

7/5/84 g o.accron pperv assuaiace e) Review all radiographic film for site-related nondestructive examination.

f) Audit records and documentation prior to turnover to the Client.

g) Develop and implement Quality Assurance Instructions and project-related supplements to Site Quality Assurar::e Procedures and implement applicable Site Quality Assurance Procedures.

h) Perform on-site distribution of those lR7 Quality Assurance procedures which are issued and controlled by the Manager Site Quality Assurance or his designee.

1) The Quality Assurance Site Supervisor has stop work authority.

3.1.1.2.2 Site Quality Control - A Quality Control Site Supervisor and staff of engineers and inspectors are assigned the following functions consistent with the scope of work assigned to Ebasco:

a) Planning and performance of

. inspection activities during the construction phase.

b) Identifying and initiating correction of nonconforming conditions to requirements indicated by drawings, specifications, codes, or procedures, and performance of reinspection to verify corrective action taken.

c) Establishing and enforcing quality control documentation and inspection requirements based upon specifications, codes, standards, and drawings as established by the Client or his designee.

sies4 sre> >e. nace 6 ,, 13 ERASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION iNcompomATro HOU5 TON UGHTING AND POWER COMPANY QA-I-2 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 6 l R7 ORGANIZATION AND RESPONSIBILITIES oare 7/5/84 ointeron 40tv assuauct g d) Performance or monitoring of site NDE, soils, and concrete testing activities.

e) Assisting in organizing and

, administering training seminars as required to assure proper level of training, and engaging in the certification of Quality Control personnel to the required level of qualification.

f) Identification and control of the quality status of items.

g) Development and implementation of applicable Quality Control Procedures, and generation of inspection reports covering mandatory inspection activities at the construction site.

h) The Quality Control Site Supervisor has stop work authority.

The Site Quality Control Group will only be responsible for first-level Quality Control activities for safety-related items and services being performed by Ebasco's forces.

3.1.1.2.3 Site Quality Records - A Quality Records Supervisor and staff of specialists are assigned the following functions:

a) Develop, establish, and implement a system for the collection, storage, and maintenance of quality assurance records at the project construction site.

b) Responsible for review for completeness, control, storage, preservation, and safekeeping of Ebasco site-generated quality lR7 assurance records until turnover to the Client or his designee. .

. .-. - - - . - . =- - . . - .

- -- . .~, . .-. =. . _ .-

I f

I slow tstp> H4 pact or  !

EsASCO SERVICE 5 NUCLEAR QUALITY AS$URANCE PROGRAM MANUAL SECTION mcompom ATro HOUSTON UGHTING AND POWER COMPANY QA-I-2 ,

SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 6 l 1

g lR7 j

l MM o,accro. .n mumca ORGANIZATION AND RESPONSIBILITIES o ve 7/5/84 l

l f

c) Establishment and implementation of a records indexing system to permit proper traceability and retrieval.

d) Establishment of a procedure for access to the records storage area, and removal and retrieval of quality records.

i 3.1.2 Quality Assurance Engineering - The Quality Assurance l Engineering subdivision is headed by the Manager Quality Assurance l 1 Engineering. He is responsible for the following activities which  !

4 are under the direction of supervisors reporting to him and are l performed in accordance with Quality Assurance procedures: l I

a) Administration of training and qualification programs for l Quality Assurance audit and inspection personnel. l ,

l b) Conducting Quality Assurance education, both internal and I _ ,

external to Quality Assurance. Quality Assurance IR7 Education Specialists from Quality Assurance Engineering l j are assigned to the construction site. These specialists l report administratively and functionally to the Quality l Program Site Manager, but receive technical direction l from Quality Assurance Engineering at the Ebasco home l office. ]

l c) Interdepartmental auditing of all individuals or groups I responsible for activities covered by the Quality Program. l l

d) Development and implementation of Trend Analysis programs. I 3.1.2.1 Radiation Safety - Ebasco's Corporate Radiation Safety Officer reports to the Director Quality Assurance R7 through the Manager Quality Assurance Engineering. He is responsible for auditing and enforcing the Ebasco Procedures 4

for radiation safety.

3.1.3 Inservice Inspection / Nondestructive Examination Services - l The Inservice Inspection / Nondestructive Examination Services l subdivision is headed by the Manager of Inservice Inspection / l Nondestructive Examination. He is responsible for the following lR7 activities which are under the direction of supervisors reporting l to him: l

. l l a) Establishment and/or interpretation of NDE requirements l and acceptance criteria for fabricated and erected equipment as required.

i

, - - - - + - .y--_.4~,- - , . - - . - - ~ , , . , .m.- .- - -.yy

. e i m- - , . ,

t i

\ .

61094 (STP) 5-84 8 13 PAGE OF

! EsASCO SERVICE 5 NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION

  1. NcomPomATED HOU5 TON UGHTING AND PteER COMPANY QA-I-2 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNIT 51 & 2 6 l N ORGANIZATION AND RESPONSIBILITIES oart 7/5/84 ointcion 93Orv assuaanct l

I b) Reviewing and commenting on NDE procedures and lR7

, radiographic films submitted by site construction forces and/or clients. l l lR7 c) Advising site construction forces as to proper NDE l procedures, applications, techniques, equipment, and qualifications.

d) Qualification and certification of Ebasco NDE personnel.

1 3.1.4 Quality Assurance Consulting - The Quality Assurance l 3

Consulting subdivision is headed by the Senior Consulting Quality l l Assurance Engineer,:who is responsible for the following activities: l l

l a) Development of Quality Assurance standards and procedures. lR7

1 i b) Interpretation of quality assurance requirements as I specified in national codes, standards, and regulatory l J

documents, and incorporating these requirements in I company documents. l 3.2 Materials Applications, under the supervision of the Chief Materials Engineer, includes two subdivisions: Materials Engineering and Welding lR7 E'gineering.

n A Project Materials Engineer and Project Welding Engineer l i

are assigned to the South Texas Project. These positions may be assigned to the same individual if properly qualified. A Site Welding Superintendent, who reports to the Chief Materials Engineer in New York, lR7 i

is assigned to the construction site and is responsible for the direction, supervision, and administration of a site welding operations staff. Quality-related activities of Fkterials Applications personnel include the.following:

a) Develop material and welding specifications.

b) Develop and qualify welding procedures and fabrication techniques for use by Ebasco site construction forces.

c) Prepare site welding operations implementation procedures for '

Ebasco site construction forces.

. i i d) Advise Ebasco Construction management as to the development and i application of advanced welding techniques which would enhance quality.

1

.x ,.ns _ > ~a..- a -. 2 2 .a-, 2 . a - e - aa a. .- ,aa n ..-.a .

sice4:sim mu pace 9 or 13 ESA5CO SERVICES NUCLEAR QUALITY AS$URANCE PROGRAM MANUAL SECTioN INcompoRATED HOUSTON ListTING AND P9WER COMPANY SOUTH TEXAS PROJECT QA-I-2 l g ELECTRIC GENERATING STATION UNITS 1 & 2 6

,g g, o, l 2 l R, ,-

I< ORGANIZATION AND RESPONSIBILITIES omit 7/5/84 g oimecron oggin ann =ca g

4 1

e) Prepare Process Data Checklists which provide comprehensive requirements for welding process and procedure selection, postweld thermal treatment, and inspection at the construction IR7 l, site. l f) Review specifications and drawings provided by the Client or his designee for compliance with applicable codes and regulatory requirements for proper selection of materials, weld procedures, and joint details.

g) Supervise the welder performance testing program at the i construction site to assure that all code and regulatory requirements have been met.
h) Provide technical assistance as required to resolve problems at the construction site in the areas of welding, materials, beat treatment, and other related areas.
1) Provide technical assistance concerning material properties

, under service conditions involving stress, radiation, temperature, corrosive media, etc, to determine capability of specific materials to perform in such environments.

j) Review, monitor, and provide recommendations for upgrading of Ebasco welder training programs and . welder assignment practices.

k) Prepare and monitor site filler material control procedures.

I

1) Supervise and direct testing and applied research programs j required to resolve site construction materials and welding problems.

4 j 3.3 The Quality Assurance Consulting Engineer reports to the Vice President Corporate Quality Programs. He is responsible for conducting lR7 audits of the Ebasco Quality Assurance function to determine and report its compliance with the Ebasco Quality Program requirements.

3.4 The Materials Engineering Laboratory performs field nondestructive 1

examination services. The Materials Engineering Laboratory is I administered by a Manager who reports to the Vice President Corporate l Quality Programs. The NDE Laboratory Supervisor reports administrative 1y l i to the Materials Engineering Laboratory Manager or his designee and is lR7 responsible for the technical direction of nondestructive examination l 3 activities performed by the Site NDE Laboratory at the construction l site. The NDE Laboratory Supervisor reports functionally to the Quality l Control Site Supervisor or his designee. I i

1

., , , . , - -, - - - - ---,~ s , . . , - - - . - - , , -

o

- s tos-s (sTpt s-se pact 10 o, 13 EBA5CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomATro HOUSTON UGHTING AND POWER COMPANY QA-I-2 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2

,, 6 l b

orascro. n assuna.ca ORGANIZATION AND RESPONSIBILITIES cart 7/5/84 IR7 g

4.0 CONSTRUCTION AND PLANT SERVICES GROUP l l

Primary responsibility for construction and plant services rests with the l Croup Vice President Construction and Plant Services. The Construction l organization has the prime responsibility for the performance of quality l construction on the South Texas Project and is described in the following l paragraphs. l lR7 4.1 The President Ebasco Constructors Inc reports to the Group Vice l President Construction and Plant Services and is responsible for I executive management of all construction activities and services. l (See Figure I-2.4.) l l

4.1.1 The Ebasco Construction Manager reports to the President l Ebasco Constructors Inc and is responsible for overall supervision l and coordination of all construction activities and services. The Ebasco Construction Manager has stop work authority.

4.1.2 The Manager of Construction Quality reports to the President l Ebasco Constructors Inc, and is responsible for development of l Construction Standard Procedures, keeping abreast of NRC and code lR7 requirements, and periodic reporting to Construction canagement of l current Quality Program status and any required corrective actions. l

, 4.1.3 The Site Manager reports to the Ebasco Construction Manager.

The Site Manager has the responsibility for the direction and coordination of all on-site activities related to construction. The Site Manager has stop work authority.

4.1.4 The Project Superintendent reports to the Site Manager and is responsible for performing general site supervision of construction in accordance with drawings, specifications, and contractual obligations. The Project Superintendent has stop work authority.

4.1.5 The Unit Superintendents reports to the Project Superintendent. Each Unit Superintendent is individually responsible for the Ebasco construction operations and activities within his assigned unit of the plant. The Unit Superintendents have stop work authority.

m

eice-s iste> Se4 ..oe 11 o, 13 EBASCO SERVICEL NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION sNcompomATEo MOU$ TON UGHTING AND POWER COMPANY QA-I-2

, SOUTH TEXAS PROJECT

ELECTRIC GENERATING STATION UNITS 1 & 2 6 p g, ,, l R7 As ORGANIZATION AND RESPONSIBILITIES oare 7/5/84 oinscron gun assunact g

4.1.6 The Assistant Superintendents report to the Unit Superintendents. The Assistant Superintendents will manage all phases of construction within disciplines assigned, including field engineering and cost control, to assure that the work accomplished is completed within the budget and in accordance with all applicable installation specifications. The Assistant Superintendents have IR7 stop work authority. l 4.1.7 The Discipline Superintendents report to the Assistant Superintendents. Each Discipline Superintendent will direct, coordinate, and monitor all work performance within the assigned discipline to assure that work proceeds in accordance with approved plans, specifications, and the Quality Assurance Program.

4.1.8 The Labor Relations Representative reports to the Site Manager. The Labor Relations Representative is conversant with the general provisions of the Project Stabilization Agreement. The Labor Relations Representative participates in settlement of local labor disputes, assists in preparation for arbitration proceedings related to operations at the site, and advises the Project Superintendent on local labor relation matters.

4.1.9 The Senior Resident Engineer reports to the Site Manager and is responsible for administering, coordinating, and supervising all Site Construction Engineering and technical activities, for interpretation of design documents and specifications, and for furnishing assistance to Ebasco site personnel as required. The Senior Resident Engineer has stop work authority.

4.1.10 The Construction Indirects Superintendent reports to the

, Project Superintendent. The Construction Indirects Superintendent is responsible for the direction of all support craft forces on the project, and the supply, maintenance, and repair of major project construction equipment. The Construction Indirects Superintendent has stop work authority.

I 4.1.11 The Construction Services Manager reports to the Site Manager and will be responsible for providing and establishing adequate and efficient security, safety, and training and development programs.

l l

l

~

sics.4 isim s-se pace 12 or 13 EBASCo SERVICES HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN tNcompomATED HOU5 TON UGHTING AND POWER COMPANY OA-I-2

, SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 & 2 pa visio 6 l R7

  • ORGANIZATION AND RESPONSIBILITIES oave 7/5/84 oinacion ppurv assuaaact 1

4.1.12 The Safety Supervisor reports to the Site Manager. The Safety Supervisor is responsible for establishing and enforcing the site safety and industrial hygiene programs in accordance with established policy and all federal and state regulations, as well as any other criteria necessary to insure the safety of site personnel.

4.1.13 The Adninistrative Manager reports to the Site Manager.

The Administrative Manager is responsible for providing the necessary accounting, timekeeping, and computer support, as required to support the construction effort.

4.1.14 The Outlying Facilities Superintendent reports to the Project Superintendent and is responsible for supervising and coordinating in an efficient manner all construction activities of all the outlying plant facilities, including the Diesel Generating Building in Unit 1 and Unit 2. The Outlying Facilities Superintendent has stop work authority.

4.1.15 The Site Welding Superintendent reports to the Chief Materials Engineer or bis designee. The Site Welding lR7 Superintendent receives his day-to-day and technical direction from the Materials Applications Department in New York.

4.1.16 The System Completion Superintendent reports to the Project Superintendent and is responsible for systems completion. He ensures construction progress in support of systems completion.

This includes coordination of all prestart-up planning and scheduling, and conducting construction test efforts.

4.1.17 The Second Shift Superintendent reports to the Project Superintendent and is responsible for performing general site

supervision of construction in accordance with drawings, specifications, and contractual obligations for all activities performed on the second shift. The Second Shift Superintendent has stop work authority.

5.0 INTERFACE Interface, as applicable, is so illustrated by Figure I-2.9 at the end of this Section and is explained by appropriate and applicable South Texas Project documents.

w

esos isra, s.e4 p.ac 13 or 13 EBA5CO SERVICES HUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTl0N

, #NcomponATEo HOU5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT OA-I-2 ELECTRIC GENERATING STATION UNIT 51 & 2 n g y, si o ,, 6 l

' R7

  • ORGANIZATION AND RESPONSIBILITIES o^Te 7/5/84 oraterongu ry ...ua ace V I 6.0 ORGANIZATION CHARTS The following figures apply to this Section:

Figure No. Title Revision I-2.1 Operations Organization Showing l Quality Program Committee Representation 5-STP lR7 I

I-2.2 Corporate Quality Programs Organization 6-STP l I-2.3 Deleted -

I-2.4 Organization for Construction 4-STP lR7 l

I-2.5 Deleted -

I-2.6 Quality Assurance Organization 6-STP lR7 I-2.7 Quality Assurance Engineering Quality Assurance Specialists 6-STP lR7 I-2.8 Deleted -

I-2.9 Interface Between Houston Lighting &

Power Company, Bechtel Energy Corporation, and Ebasco Services Incorporated 3-STP lR7

Ebasco Services incorporated OPERATIONS ORGANIZATION SHOWING QUALITY PROGRAM COMMITTEE REPRESENTATION Pf1ESIDE NT I

I I I I GROUP GROUP GROUP VICE PRESIDENT GROUP VICE PRESIDENT VICE PRESIDENT CONSTRUCT 80N ADVANCED VICE PRE 51 DENT gNTERNATIONAL TECHNOLOGY ENGINE E RING OPE R A TIONS & $P C L I I I I I I I I SR V1CE VI PRE SIDE N T VICE PRE $1 DENT EB O VICE PREstDENT COR ATE PR T EB RP TE ENVIROSPHERE MANAGEMENT PROJE CT CONST RUCTOR 5 OVALITY ADVANCED E NGINE ERING "

COMPANY $ERVICES PROCURE MENT INC. PROGR AMS TECHNOLOGY C CONSULTING y*

SERVICES QP OP OP OP OP OP OP OP QP COMM COMM COMM COMM COMM COMM COMM COMM COMM REP REP REP REP REP REP REP REP REP H

<a e C V

$17 5 ."

2

Ebasco Services incorporated CORPORATE QUALITY PROGRAMS ORGANIZATION PRESIDENT I

VICE PRESIDENT CORPORATE QUALITY PROGR AMS I

I l l l CHIEF DIR ECTOR #

CHIEF VENDOR MATERIALS OUALITY OUALITY ASSURANCE MAT R ALS ENGeNE ER ASSUR ANCE R EPR ESE NTATIVE E NGINE ERING LABORATORY I I

" MATERIALS =

I MANAGER MANAGER VENDOR QUALITY ASSUR ANCE ENGINEERS QUALITY ASSUR ANCE OUALITY ASSURANCE = OUALITY ASSURANCE CONSULTING -

PROJECTS E NGINE E RING SUPERVISORS E NGINE ER I I l PROJECT OUALITY ASSURANCE

- WE LDING OUALITY ASSURANCE E NGIN E E RING VENDOR ENGINEERS SUPE R VISOR S. SUPE RVISOR $ & OUALITY ASSUR ANCE ENGINEERS & STAFFS SPECIALISTS REPRESENTATIVES MANAGER OUALITY ASSURANCE A "

fNDE -

SER VICES SE RVICES I I MANAGER SITE ISI/NDE QUALITY ASSURANCE. SUPE R VISOR S SITE SUPERVISORS &

& STAFFS STAFFS L

- $T MANA ER SENIOR CONSULTING SITE SUPERVISORS QUALITY ASSURANCE -

AND STAF FS ENGINEER & STAFF

$ NOT APPLICABLE TO THE STP OUALITY ASSURANCE ORGANIZATlON FIGURE I-2.2 REV . 6-STP

Ebasco Services incorporated ORGANIZATION FORCONSTRUCTION ADAPTED FOR HOUSTON LIGHTING & POWER CohePANV SOUTH TEMAS PROJECT ELECTRIC GENERATigeGSTATION UINTS I & 2 w

ve.u.m.n o. = >

CO.

P ANI512U.CIION S NvEtS &

Co ..ut 14 .

[

-a l ..

~. .-.. . .

N.mVORK .s.W YORK SIIE Si t t I

1 I l l

, , , ,,, ,., ,,. ,= . -

. .... ,, , a,,,,,

. =.:',, '.=

I I I

,,,,,, ,,,,,,, - . . < > - .. .o ,

~...... - . . . . . . . . . . . . .

..u..'. ..

. ~ . .. " . .

I I

..... . . . _. =",,,,

I I gy ,, .. .. .. -

<4 0

. C eQ _._-_.o.

&g . s .o.. .wi n.

P4 e

  • O .to

1 e

EBASCO SERVICES INCORPORATED OUALITY ASSURANCE ORGANIZATION DIRI C TOR QUAT li y A SSUR ANC E I I --

- -I - -.- -- . I . - - _ I MANAGtR MANAGER MANAGER SI N KJR MANAGIR CONSUL TING OUA L II Y OUAL 11Y OU AL 11 Y ASSUR ANCf ASSUR ANC E A SSUR ANC E 158 NDE OUAlli Y PROJf C15 E NGINE E RING SIIE Si RVICES M RVICE S A A Cf

-. . - - . - - . - ~ ~ - -

g g p

- , --. _1 - . - _ 1 I . . , _I MARAGE Mf NT & MANAGE ME NT & CONSUL TING SLFE RVISBNG SUPT R VestNG MANAGERS (pgAg g y y MANAGER ISS NDE E NGINE E RS E NGINE f RS $N T E RNAituN AL N " '" A "

Siti OUAlliY MANAGf Mf NI & MANAGE MINI & QUALIIY OUAllIV OUAL 61 Y AREA Sa lt M AN AGE R l SIFE RVISORS SUPI R VISORS ASSURANCE ASSURANCE ASSURANCE ASSUR ANC E E NGINE F RS PROJt C T S E NGINE E RING - " - - -

1 I l -_ l -_ __

" " " '

  • AS58SIANI PROJf CT Oual tiv OUAllI V Se it OUALIT Y V' ** I V '#^ " *
  • ASSUR ANC E NAIIIT CON 3 ROL RfCORDS GUALIIY ASSURANCF WAL 88 MW 8 5 & SIII SSI E , ovat g y y E NGINE E RS ,,',"," **

SUPf RVISOR SUPf RVISOR RVMR AS R C

,, SLFI R VISORS p opt a A t arises um e - - - - - - - - - > - - - - - - - - -

uuae e t v me < onos esAsmactestet e TRO seO ANAL Vit$

R AD4 A t eLW SAF 1 i V OUAlli v ASSUR ANC E

---8 l

E NGINE E RS -- - - - - - - - - - - - - - - - - - - - - -- -

Sif E OUAtely REGULATORY OU AL IT Y OU AL IT Y OUALITY RECORDS ASSUR ANCi t INSE R VICE NONDE ST R UCilvt RIOUIR E MI NIS.

ASSUR ANCE ASSUR ANCE CONTROL ENGINE f R$s I NGINt f RS' F NGINE E RS/

E NGINE E RS/ QUALilVCONIROL INSPf CTION f M AMINAIK)N INDUSTRv CODES SPICIAllSf5 SPf CIAllSIS SPf CIALISTS SPECIALIS15 E NGINE E RS/ SPf CIAllSIS SPf CIALIS 15 & ST ANDARDS SPE CIALISTS ADMtNIST R AllON emoi AretatAatt to fue Sir PTj Uuat:1W A55unAseCE OmGAposfATeOm H

O e C l.0 H H I N ra e

h

EBASCO SERVICES INCORPORATED QUALITY ASSURANCE ENGINEERING OUALITY ASSURANCE SPECIALISTS EM AS C f tWI

.O.t s a,A.t.t.T.V .

I I I I

. - ~ . . _ , , , _ . - ~ .

Esset I T V ygg g g GJ AtiIW w a-is .o.. ,'=aga l

..__s i I , I I I 8 .

(mise a e v ne g apeer s 5 rpsat sf v Assiasmaaste (IPE ma f sonens IIe $8 RVs00 8881141 558088 88WG 884SiPt C ItO8e I 18 AM* 4 I8888 & INAlmese ag(operg i **>M e f y agassagg es,s6 g, y RM AW89M U *** maagaq,5 ast fut A55ssflamett Def AWt%#sse telPS Ave 5tspp SJPG Rve50ft w.- .- * ^

~ l I. - I - 1 1 -. 1 1 I I - -

I

{ l l u,<.

W M hE'S

. . . . -- . } , , . ,, , ...

,... 'a ~~ . . . . , . u.

, . . oP .. < =

..u..

..o, ggg i.N M M< R .-- 3 68, i

.t.h.as.

.se.n,&, Ttf 4.A.4 9911 9Pld.tA.8 8%I%

pe

,,s,,,,,tt

,.o.m.a.n.s --

~ es,A,s,sa,6,3.a.s.s.en c , t . .E.teG.eseg

. ... g f6.,,,,

t.___ . _ .J ;. i 1 i 2 1 s rsev,um (H

AgJgje I sees I

I l

I .

e i

.I _

uaam s . I

  • uuntiv, siaan.an.ma ,e,.a,,u,,,i,,n,s,s,i,s v,, ' e v'= u"a"v a ne , "u"n "v*a*c*

i eK nee } ear eAe MNtmatWW 4

s Pel4t.

.. n .t la.s.m.e

, t cacas ta u. n ; k cm<se i a erem I I I I I I I I I I I I l l _ L__

i

} ]  !

.s , l < . .. . t .. i . .o a" un. .. Ps :

"" un "" " " " ' "

l eui .e.e

. s < news l

5"'

l rwere a=ai es.s i j i  ; i

. NOT APPLICAstt IO f tet STP OUALIIT Al$URApsCE OftGAhllAlpD85

% 'T1 m we 4O c

(b WH PI e

't! PJ e

N

l. _ _ _ _ _ _ _ _ _ _ _ _

1 1

l l INTERFACE BETWEEN HOUSTON LIGHTING & POWER COMPANY, BECHTEL ENERGY CORPORATION, AND EBASCO SERVICES INCORPORATED I

PROJE CI OA . . . . . _ _ _ . SII E MANAGE R MANAGER HOUSION LIGHIING & POWE H CO.

e........................... essees ..o .e.eeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeese ....e ee e ee eeee eee e e eee s e s....s e eeeee eeeeee ee e e ee e eeeeee eeeee eee e ee e e e ee eeses se sseeesseesee BECHTE L E NE HGY COHP.

~

CORPOR A T E DE glGN OA I NGINE E RING MANAGEROf CONS T R UC TION PROJE CI OA . . . . _ _ . _

MANAGER DE PUf Y MANAGE R Of CONSIRUCllON

$1 T E E NGINE E RING essesseeeeeeeeeeeeeeeeeeessee eseesseseeessessessessesseesseeseessesseessnesseessessoa s BECHTE L ENERGY CORP.

s e s s e s s es sesses seseessesses s essese+eess eese ss e es seeses s e e seeeeeeeeeeeeeeeeeeeeeeeeeeees.

E8ASCO SE HVICE S INC.

DIR E C TOR PRE SIDE NI

- QU AtlI V - E SASCO A15UR ANCE CONS T RUC T ORS INC CON ST R UC TION OUAE IT Y PROGR AM MANAGER

$4TE MANAGE R = = = = = = = = = = = - = = -

$1TE MANAGE R I yq mH

< C)

  • C w

t.o e4 INTEhFACE He === == = COMMUNICAilON PROJE CT SE NIOR RE SIDE N I

, T E CttNICA L/ADMINIS T R A TIVE SUPE RIN T E NDE NT E NGINE E R c DIR E CTION

T sice4 sipi sse

..cc 1 or 3 EsA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION tNcompoma*zo HO'JSTON UGHTING AND POWER COMPANY QA-I-3 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2 4 l l

[ PERSONNEL INDOCTRINATION AND TRAINING 7/5/84 lR7 I o.4c o. gin .,so. ace PROGRAM IN QUALITY ASSURANCE 0*TE l s l 1.0 SCOPE This Section describes the program for indoctrination and training of Ebasco personnel engaged in activities affecting quality with respect to the requirements of this Manual and its supporting principal implementing procedures. Ebasco personnel shall be indoctrinated and trained, as necessary, to assure that proficiency is achieved and maintained in those parts of the Quality Assurance Program as it applies to the individual's responsibility.

2.0 GENERAL The Indoctrination and Training Program is a combined effort of the Ebasco organizations implementing any portion of this Manual and its principal implementing procedures, and the Quality Assurance organization. The Construction, Materials Applications, and Quality Assurance organizations are responsible to schedule, indoctrinate, and train their personnel, and to record this indoctrination and training, unless otherwise denoted by project commitments.

3.0 PROGRAM REQUIREMENTS 3.1 Preplanned written lessons shall contain the substance of the IR7 indoctrination and training program. These lessons shall address one or more quality-related topics, to achieve one or more stated educational objectives. The training will be conducted by trained supervisors or their designees within the Construction and Materials Applications organizations, and by a Quality Assurance Education Specialist or designee when the need arises. A Quality Assurance Education Specialist will be responsible for training the selected instructors within the other Ebasco organizations in methods of conducting required quality assurance training.

i .

sios4 :srei ses pace 2 o, 3 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCompORATED NOU5 TON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-3 N ELECTRIC GENERATING STATION UNITS 1 & 2 1 > 4 aavmon l

! PERSONNEL INDOCTRINATION AND TRAINING 7/5/84 l R' I oinscron pm .33u...cc PROGRAM IN QUALITY ASSURANCE g

a 3.2 For Construction, Quality Assurance, and Materials Applications, preplanned training lessons are maintained by each organization lR7 '

respectively. The preplanned training lessons relate to activities the l 1

personnel shall be performing. For Construction and Materials Applications, a responsible person within the respective organization shall determine the training requirements for each individual based on that individual's assigned responsibilities and past experience. Within the Quality Assurance organization, a Quality Assurance Education Specialist shall be responsible. for determination of an individual's

training requirements based upon that individual's assigned i responsibilities and past experience, as applicable. Preplanned training IR7 lessons are updated, when required, and reflect any changes in the program. Copies of these preplanned training lessons shall be kept on lR7 file by the respective organization. Quality-affected training will reflect project requirements.

4.0 RECORDS Individual training files for personnel in the Construction, Quality Assurance, and }kterials Applications organizations receiving indoctrination and training in accordance with this program's requirements shall be maintained by each affected organization. These records will indicate, as applicable, the subject matter, the training received, attendance date, time duration, instructor, and special qualifications or restrictions, if any.

5.0 SCEEDULING Scheduling training of applicable organization personnel will be coordinated with a Quality Assurance Education Specialist where necassary. As new personnel are added to the South Texas Project within an organization, appropriate indoctrination and training sessions will be scheduled based on the requirements of this Manual.

6.0 PROGRAM UPDATING

$ This indoctrination and training program is subject to continuous develcpment to broaden and improve its effectiveness. A Quality Assurance Education Specialist will hold periodic discussions with those groups involved with the training program to coordinate recommendations for updating. A Quality Assurance Education Specialist is responsible for updating the program for the Quality Assurance organization.

eios4 sre> >es pace 3 or 3 ESA5CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION tNcomponaTro MOU5 TOM UGHTING AND POWER COMPANY

, SOUTH TEXA5 PROJECT OA-I-3

= ELECTRIC GENERATING STATION UNIT 51 & 2 g a tvision 4 l

! g I o, mo. ag n anu===ce PERSONNEL INDOCTRINATION AND TRAINING oave 7/5/84 lR7 PROGRAM IN QUALITY ASSURANCE l 1

7.0 ADMINISTRATION 7.1 The Quality Assurance Engineering Quality Resources and Training lR7 Management Group shall have overall responsibility for administrating the quality assurance training program. It shall provide technical expertise for developing necessary programs and review existing programs for currency.

7.2 Management of each Ebasco organization is responsible to assure that the appropriate personnel attend the training program (s) for which they are scheduled.

8.0 TRAINING, QUALIFICATION, AND CERTIFICATION OF QUALITY CONTROL PERSONNEL Training, qualification, and certification of Site Quality Control inspection personnel shall be in accordance with written procedures. The Quality Control Site Supervisor or his designee shall coordinate with a Quality Assurance lR7 Education Specialist regarding the training, qualification, and certification of Quality Control personnel. Qualification records for all Quality Control '

personnel assigned to the South Texas Project site shall be maintained by a Quality Assurance Education Specialist at the site. These records will be audited initially by the Director Quality Assurance, or his designee, for lR7 compliance with the qualification requirements, and thereafter on an annual basis by auditors from the Site Quality Assurance organization. Any deficiencies detected shall be reported in writing by the Quality Assurance Site Supervisor, or his designee, to the Quality Control Site Supervisor for resolution. Pending resolution of the deficiency, the individual shall be restrained from performing any Quality Control activities.

9.0 AUDITS Audits of indoctrination and training activities shall be performed to assure conpliance with this Program. Such audits shall be performed in accordance with the requirements of Section QA-III-9 of this Manual.

l l

l l

sico-s istp> s e4 pace 1 or 4 EBASCO SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTioN

  • coaaoaATED NousToM usNTING AND power COMPANY l

i QA-I-6 SOUTH TEXA5 PROJECT g ELECTRIC GENERATING STATION UNITS 1 & 2 4 g .

RT QUALITY ASSURANCE RECORDS o*T, 7/5/84

. . ... y . _. . ,

1.0 SCOPE

, This Section covers the requirements and guidelines for the collection, filing, storage, disposition, and maintenance of lifetime and nonpermanent quality assurance records associated with the construction and maintenance of nuclear power plants.

I i 2.0 RESPONSIBILITY t It shall be the responsibility of Ebasco to maintain quality assurance (QA) records in accordance with the requirements of this Section until such time as those records are turned over to the Client or his designee for permanent storage. The HL&P STP - RMS Sf te Records Center is the principal and final records repository. All QA records shall be accessible to the Client or his designee until such time as they are turned over to the Client or his designee.

j 3.0 QUALITY ASSURANCE RECORDS SYSTEM Each organization within Ebasco (including but not limited to the Construction and Quality Assurance organizations) that participates in the generation, collection, filing, storage, disposition, or maintenance of quality assurance

. records shall establish a written quality assurance record system applicable to the function (s) performed by that organization. These written procedures

shall provide that each completed quality assurance record shall be transmitted by the organization generating the records to the Ebasco Site i Quality Records group for final review and transmittal to the Client or his designee. This systen shall be implemented and enforced in accordance with the requirements of the following paragraphs that apply to the function (s) of that organization.

4.0 GENERATION OF QUALITY ASSURANCE RECORDS 4.1 The QA records to be generated shall be specified in the applicable design specifications, construction, maintenance, test, or inspection procedures, and other documents as necessary.

t 4.2 All QA records shall be dated and signed or otherwise authenticated.

4.3 QA records shall be indexed. The indexing system shall include as a minimum:

i 4.3.1 QA records retention times (retention period begins on date l of satisfactory operation of items).

i

. 1 41094 tstet Fe4 pace 2 or 4 EBASCO SERVICES NUCLEAR QUALITY A55URANCE PROGRAM MANUAL SECTlON INCORPORATEo HOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT OA-I-6

< ELECTRIC GENERATING STATION UNITS 1 & 2 4

7/5/84 lR7 QUALITY ASSURANCE RECORDS oarc

  • ofascion gdbir assuaanct l

4.3.2 Location of storage area.

4.3.3 Location of QA records within storage area.

4.4 All QA records shall be distributed and handled in accordance with written instructions.

4.5 There shall be sufficient information in the QA records to permit identification between the records and the item (s) or activity to which it applies. Identification of QA records may be by purchase order number, system, or any means that permits accurate traceability.

4.6 All QA records shall be classified as " lifetime" or " nonpermanent."

4.7 When QA records are corrected or supplemented they shall be reviewed or approved by the organization that originated the records. All corrections and supplements shall bear dates and authorized signatures or initials traceable to the authorized individual. IR7 4.8 Inspection and test records shall contain the following, as applicable:

a) The type of observation.

b) Evidence of completing and verifying an inspection or test operation.

c) The date and results of the inspection or test.

d) Information related to nonconformances, e) Inspector or data recorder identification.

f) Evidence of the acceptability of '*e results.

5.0 RECEIPTOFQUALITYASSURANCERECORTg 5.1 A system shall be established zor receipt of QA records at the Site which shall include:

5.1.1 A checklist designating the required QA records.

1

sics.s istp> s-e4 nacc 3 ,, 4 ESASCO SERVICES HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION mcompomarco HOUSTON UGHTING AND POWER COMPANY QA-I-6 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l E

l R*'

I QUALITY ASSURANCE RECORDS care 7/5/84 g odscron jphirv assunanct g

5.1.2 A record of QA records received.

5.1.3 Written procedures for receipt and inspection of incoming Site QA records.

These quality assurance records shall be maintained by Site Quality Records and audited by Site Quality Assurance to assure that they are maintained properly until turned over to the Client or his designee.

5.2 The system described in Paragraph 5.1 of this Section shall permit lR7 an accurate assessment of the status of the QA records during the receiving process.

6.0 TEMPORARY STORAGE, PRESERVATION, AND SAFEKEEPING 6.1 QA records shall be stored in accordance with a written procedure which shall require or include the following:

6.1.1 Description of storage facility, if other than a dual facility.

6.1.2 Description of filing system to be used.

6.1.3 Method for verifying that QA records received are in agreement with transmittal documents and pre-established records checklist and that the QA records are legible.

6.1.4 Rules governing access to files.

6.1.4.1 A list shall be generated designating those personnel who shall have access to the files.

6.1.5 Method for maintaining control of QA records removed from storage. Such method shall provide for signing out of QA records removed from storage or other appropriate means of maintaining control of the records removed.

6.1.6 Method of filing supplemental information and disposing of obsolete QA records. Supplemental information shall be filed with the original documents whenever practical.

6.2 A custodian (or custodians) shall be designated to implement the requirements of Paragraph 6.1 of this Section. lR7

siow istri m pace 4 or 4 EsASCO SERVICES NUCLEAR QUAUTY A550RANCE PROGRAM MANUAL SECTION iNcompomATED MOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-I-6

{

ELECTRIC GENERATING STATION UNITS 1 & 2 4 g 2 -

I Mb QUALITY ASSURANCE RECORDS o*Te 7/5/84 lRs.

g o4=ccro ym anua cc 6.3 QA records may be stored within a temporary storage facility if they are protected from damage and loss. This shall include:

6.3.1 Storage within fire-resistant cabinets with a four-hour Underwriters' rating or a satisfactory alternative.

6.3.2 Protection from condensation.

6.3.3 Disallowance of loose documents. Records shall be attached

, to binders, placed in folders, or similarly maintained.

6.3.4 Specially processed QA records such as radiographs, microfilm, etc, shall be stored and protected in accordance with the manufacturer's recoumendations.

6.4 A satisfactory alternative to the requirements of Paragraph 6.3 of . l R7 this Section is maintenance of duplicate QA records stored in a separate l

} remote location.

6.5 Audits shall be performed by Site Quality Assurance to assure the effectiveness of the storage system, and shall include:

6.5.1 Verification that QA records which have been processed into 1 i the records facility are available in their proper location and in IR7

' ~

good condition, including those records that have been logged-out l and removed away from the storage system. , l 6.5.2 Audit results shall be documented and discrepancies shall be reaudited to assure their correction.

6.6 The. storage systems shall provide for accurate retrieval of QA records without undue delay. ,

l

, 7.0 DISPOSITION OF QA RECORDS

. 1 Upon transfer of QA records, the Client or his designee shall acknowledge in writing the receipt of the particular QA records.

sics 4 <stm we4 nace 1 or 3

EBA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION Neompomarco MOU$ TON UGHTING AND POWER COMPANY QA-III-l

, SOUTH TEXA5 PROJECT

< ELECTRIC GENERATING STATION UNITS 1 & 2 4

> RevlS80N l R7 INSTRUCTIONS, PROCEDURES, AND DRAWINGS oarc 7/5/84 ointeron yon assumesca g 1.0 SCOPE Activities affecting quality performed at the construction site shall be described in written instructions, procedures, or drawings that have been developed in accordance with the requirements of this Section. Departmental procedures which describe the manner in which activities affecting quality are to be accomplished are part of the Ebasco Quality Program.

2.0 RESPONSIBILITIES 2.1 Where the Ebasco Nuclear Quality Assurance Manual designates an individual or organization with the responsibility of performing quality-related functions at the construction site, such functions shall be performed in accordance with written instructions, procedures, or drawings that have been developed by the organization performing the function. These instructions, procedures, and drawings sht11 establish the manner of performing the activity in accordance with the requirements of the Ebasco Nuclear Quality Assurance Program Manual and of the organization performing the activity.

2.2 When documented evidence is required for the satisfactory perfor=ance of particular activities, checklists, forms, and/or other appropriate means shall be utilized to provide this evidence. Such documents shall be signed and dated by the party performing the activity.

2.3 Ebasco procedures, instructions, or drawings describing activities affecting quality which are qualitative or quantitative in nature (ie, inspections or tests) shall contain or reference criteria for determining that such activities have been satisfactorily accomplished.

3.0 DEVELOPMENT OF INSTRUCTIONS, PROCEDURES, AND DRAWINGS 3.1 Instructions, procedures, or drawings for activities affecting quality at the construction site shall be developed by the Construction and Site Quality Assurance organizations for their respective quality-related functions. The Ebasco Nuclear Quality Assurance Program Manual shall be used as a guideline for their development. In addition, all Site Quality Control Procedures shall include at least the following:

a) Identification of characteristics to be inspected.

b) Identification of the individuals or groups responsible for

! performing the inspection operation.

i l

l I

I

- ....1,.,.. .., 2 ,, 3 1 ESASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION eNCORPORATED HOU$ TON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-1 g ELECTRIC GENERATING STATION UNITS 1 & 2 4 l R7 INSTRUCTIONS, PROCEDURES, AND DRAWINGS oare 7/5/84

< o accron arv *swa ace c) Acceptance and rejection criteria.

d) A description of the method of inspection.

e) Verification of completion and certification of inspection.

f) A record of the results of the inspection operation.

3.2 The Ebasco Engineering Development and Standards Department shall develop company instructions and procedures of categories, such as Nuclear (N), pertaining to quality-related functions.

3.3 Individual departments / disciplines shall be responsible for the development of their own intradepartmental/ discipline instructions, procedures, or drawings that establish the methods for performing quality-related functions. The Ebasco Engineering Development and Standards Department will provide, upon. request, guidance and assistance in developing the documents.

3.4 If so requested by a department, Quality Assurance Engineering shall act in an advisory capacity during the preparation of internal Ebasco procedurcs.

3.5 All procedures, instructions, and drawings for activities affecting quality shall be identified, dated, and shall provide authorized signature (s) of approval.

3.6 To assure that all Ebasco Quality Control and Construction procedures and instructions comply with this Manual, site-specific requirements, and applicable codes and regulatory requirements, they shall be submitted for review and acceptance to Ebasco Site Quality Assurance prior to implementation. When required by the Contract, quality assurance, quality control, special process, and construction procedures and instructions shall also be submitted to the Client or his designee for acceptance prior to implementation.

4.0 DISTRIBUTION AND CONTROL 4.1 Each Ebasco department shall be responsible for maintaining and enforcing a written system for the distribution and control of that

organization's instructions, procedures, and drawings (other than design; ie, rigging drawings) for activities affecting quality. This system shall provide for at least the following

i l

1

. l 61094 (STPI F04 pacg 3 or 3 EsA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION I WC "' RATE HOUSTON UGHTING AND POWER COMPANY gg.III 1 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2 4 l R7 h INSTRUCTIONS, PROCEDURES, AND DRAWINGS caTE 7/5/84 o.accro g aurv assu===ca 4.1.1 Copies of these documents and revisions thereto shall be distributed to all appropriate department personnel in a timely manner.

4.1.2 Outdated and/or superseded documents shall either be collected or shall be clearly marked as superseded to avoid inadvertent use.

4.1.3 A file of the latest revision of these documents shall be maintained. Such a file shall be readily available to all affected personnel.

4.1.4 A log of the documents shall be maintained. The log shall indicate as a minimum:

a) Title of document. .

b) Document identification number.

c) Latest revision number and date of document presently in use.

4.2 A historical file of all revisions and changes to instructions, procedures, and drawings shall be maintained by the applicable IR7 organization responsible for such documents or as may be described in the applicable organization's procedures. lR7 4.3 All approved Ebasco site-generated field sketches, construction procedures, quality control procedures, and special process procedures shall be transmitted to the Client or his designee for distribution and control in accordance with Section QA-III-2 of this Manual.

5.0 CHANGES TO DOCUMENTS Changes to Ebasco documents shall be reviewed and approved by the same organization responsible for the original document when those changes affect the original reviewer, unless delegated in writing by the originating organization to another responsible organization. The reviewing organization shall have access to pertinent background information upon which to base their approval and shall have adequate understanding of the requirements and intent of the original document.

6.0 AUDITS l lR7 Audits shall be performed in accordance with Section QA-III-9 of this Manual I to assure conformance to the requirements of this Saetion. l

s tos4 tsTP) Sea Pact 1 or 4

ESASCo SERVICE 5 HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN 4NCORPORATro MOU$ TON UGHTING AND POWER COMPANY QA-III-2 SOUTH TEXAS PROJECT f ELECTRIC GENERATING STATION UNIT 51 & 2

,,,, 5 l R7 3' DOCUMENT CONTROL cart 7/5/84

< eiecron mjpt,"assuanace 1.0 SCOPE This Section of the Manual establishes the requirements for the control of all project documents used by Ebasco which have an effect on quality-related activities. These requirements apply to those documents such as specifications and drawings, as well as site instructions and site procedures, which control or direct activities affecting quality.

2.0 RESPONSIBILITIES 2.1 The corresponding Department Heads or their designees shall be responsible for furnishing the Client or his designee with the latest of all Ebasco site-generated field sketches, construction procedures, quality control procedures, and special process procedures.

2.2 The Client or his designee shall be responsible for the distribution and control of all construction site design documents, drawings, specifications, construction procedures, quality control procedures, and special process procedures.

2.3 The Quality Assurance Site Supervisor or his designee shall be responsible for the distribution and control of site-generated quality assurance procedures and instructions.

3.0 ISSUANCE OF CONTROLLED DOCUMENTS 3.1 Establishment of Document Control Stations 3.1.1 Document control stations shall be established and maintained by the Client or his designee.

3.1.2 Requests by Ebasco for the establishment of new or deletion of existing document control stations for the distribution of controlled documents shall be submitted by the corresponding Department Head, Unit Superintendents, or Project Superintendent to the Client or his designee.

t 3.1.3 Requests by Ebasco for additions or deletions of documents issued to an established document control station shall be submitted l

to the Client or his designee.

l

1 610 M (STPI H e pAGE OF ESASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompom ATro MOUSTON UGHTING AND POWER COMPANY QA-III-2 SOUTH TEXAS PROJECT I ELECTRIC GENERATING STATION UNIT 51 & 2 5

> m E Vl$40N l R7 NV DOCUMENT CONTROL care 7/5/84 oirdron garv assunau g 3.2 Design Documents, Drawings, and Specifications 3.2.1 The Client or his designee shall furnish, distribute, and control all design documents, drawings, and specifications to the established document control stations in accordance with the Client's or his designee's written procedures.

lR7 3.2.2 Ebasco personnel shall use during their work activities the latest design documents, drawings, and specifications as provided by the Client or his designee at the appropriate document control stations and comply with the approved Ebasco site document control procedure.

3.3 Ebasco Intradepartmental/ Discipline Instructions and Procedures 3.3.1 Intradepartmental/ Discipline instructions and procedures shall be issued and controlled in accordance with Section QA-III-l of this 11anual.

3.3.2 Quality Assurance procedures describing auditing responsibilities of Site Quality Assurance shall be distributed and controlled at the construction site in " book" form. A master file shall be maintained of all procedures and revisions. A master list shall be maintained indicating each person or organization to whom a book of procedures has been issued. New or revised procedures will be issued to each holder of a procedure

" book." A receipt system shall be used which requires written acknowledgment of distributed procedures.

3.4 Ebasco Site-Generated Procedures and Instructions Ebasco site-generated construction, special process, and quality control procedures and instructions shall be transmitted to the Client or his designee for distribution to the established document contro'. stations.

3.5 Field Change Requests 3.5.1 A Field Change Request shall be submitted to the Senior Resident Engineer from applicable site personnel whenever conditions arise which may warrant consideration by the Client or his designee of a change in the specified design.

e s tos-4 tsTP) 5-44 pacg 3 or 4 esAsco stavicts NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN WCORPORATED HOUSTON UGHTING ANO POWER COMPANY QA-III-2 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATICd UNITS 1 & 2

_g _ $ g a

M ointero pDaurv assumanct DOCUMENT CONTROL care 7/5/84 R7 g

3.5.2 The Senior Resident Engineer shall submit the proposed Field Change Request to the Client or his designee for evaluation, disposition, distribution, and control by the Client or his designee in accordance with the Client's or his designee's written procedures.

3.6 Field Change Notice 3.6.1 A " Field Change Notice" shall be generated by the Senior Resident Engineer as is allowed by the design specification and shall be approved, issued, and controlled by the Senior Resident Engineer in accordance with approved site procedures.

3.6.2 A Field Change Notice (FCN) is to provide construction with a method of documenting conditions (not tolerances) that are within criteria allowed by the applicable specifications. An FCN shall not be used in lieu of a Nonconformance Report (NCR) or a Field Change Request (FCR).

3.7 Field Sketches l l

3.7.1 Field sketches shall be prepared, reviewed, and approved by l the Senior Resident Engineer or his designee in accordance l with approved site procedures. Only the following two types I of field sketches shall 'ae permitted to be utilized by field l personnel as a basis for the fabrication, installation, and l inspection of safety-related items: l l

a) Field sketches which have been approved by the Client or I his designee. lR7 I

b) Field sketches which the Senior Resident Engineer has I determined to be within standard detailing parameters l established by specifications prepared by the Client or l his designee. l I

3.7.2 Field sketches shall be transmitted by the Senior Resident l Engineer to the Client or his designee for approval and/or l distribution to the established document control stations by l the Client or his designee. 1 i

l ._. _. ._

i 4109-4 (STPt 5 84 Pact or E5ASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORPOR ATeo HOUSTON LIGHTING AND POWER COMPANY QA-III-2

, SOUTH TEXAS PROJECT

ELECTRIC GENERATING STATION UNIT 51 & 2 5

, , , , , , l R;'

DOCUMENT CONTROL onre 7/5/84

< o necron pn asson==ce g

4.0 CHANGES TO DOCUMENTS Changes to Ebasco documents shall be distributed in the same manner as the original document. Revised documents shall be controlled in accordance with the requirements of this Section and/or written procedures in order to avoid inadvertent use of outdated documents.

5.0 QUALITY ASSURANCE RECORDS Quality Assurance records shall be maintained by Site Quality Records which shall be audited by Site Quality Assurance to assure that they are maintained properly.

5.1 The system for control and retrieval of Quality Assurance records at the site shall be in accordance with Section QA-I-6 of this Manual.

6.0 AUDITS Ebasco Site Quality Assurance shall audit the Client's or his designee's control and distribution of Ebasco generated construction, special process, and quality control procedures and instructions in accordance with the requirements of Section QA-III-9 of this Manual.

4 l

! s tos4 tsTP Fe4 pact 1 or 4 ESA5Co SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SEcTION INcompomaTro HOUSTON UGHTING AND POWER COMPANY QA-III-6 SOUTH TEXAS PROJECT

{ ELECTRIC GENERATING STATION UNIT 51 & 2 4 g M/ W NONCONFORMANCES oAre 7/5/84 o, .u ro.,,nu n ......u i

1.0 SCOPE This Section establishes the requirements for the identification, control, and disposition of items or services found to be in nonconformance with the applicable requirements at the construction site. All activities described in this Section shall be performed in accordance with written instructions and/or procedures.

2.0 CONSTRUCTION SITE NONCONFORMANCES 2.1 Nonconformances at the construction site may be detected by Ebasco Site Quality Control, Site Quality Assurance, or Construction. All nonconformances detected shall be teported to the Quality Assurance Site Supervisor and/or the Quality Control Site Supervisor or their designees.

2.2 Quality Control procedures shall require that all nonconforming items shall be clearly marked or tagged as nonconforming and shall be segregated when possible.

2.3 The Quality Assurance Site Supervisor, the Quality Control Site Supervisor, or their designees shall document nonconformances detected by or reported to them by issuing a South Texas Project Site Nonconformance Report. A preliminary assessment of the severity of the nonconformance shall be made in accordance with Company Procedure N-23 or' approved site procedure. The final responsibility for evaluation of all nonconformances for possible reportability rests with the Client or his designee.

2.4 The Nonconformance Report shall then be reviewed and processed in accordance with Paragraph 4.0 of this Section of the Manual. "

lR7 2.5 After processing of the Nonconformance Report, the Quality Assurance Site Supervisor or his designee shall distribute copies of the reviewed and evaluated report in accordance with internal Site Quality Assurance procedures.

2.6 The Quality Assurance Site Supervisor and the Quality Control Site Supervisor or their designees from the Site Quality Assurance organization shall verify by audits, reinspections, or other appropriate means that the necessary corrective actions are taken.

~

siew istpi m pace 2 o, 4 EsASCo SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTloH

  1. NCompoRATED houston UGHTING AND POWER COMPANY SOUTH TEXAS PROJECT QA-III-6

{ ELECTRIC GENERATING STATloN UNITS 1 & 2 4 g

< NONCONFORMANCES o*Ts 7/5/84 mrero ppen assumu 3.0 REINSPECTION 3.1 For nonconformances detected at the construction site, the Quality Control Site Supervisor or his designee shall assure that reinspection is performed on all items and services reported as nonconforming.

Reinspection shall be performed in accordance with the requirements of the governing code (s) and in accordance with requirements at least as stringent as those by which the nonconformance was detected. He shall document the satisfactory correction or resolution of all nonconformances on the dispositioned Nonconformance Report. This documentation shall provide sufficient detailed information for as-built records.

3.1.1 Nonconformances not corrected in accordance with the requirements of the approved disposition to the Nonconformance Report shall not be accepted by Site Quality Control. Items or services shall not be accepted by Site Quality Control until such time as the appropriate corrective action has been accomplished.

4.0 REVIEW OF NONCONFORMANCE REPORTS 4.1 Upon receipt or initiation of a Nonconformance Report, the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall perform the following functions in accordance with QA procedures and/or instructions:

4.1.1 Log-in the report and record a unique identifying number on the report.

4.1.2 Route the report to the Client or his designee who shall l disposition and approve the report. l I

4.1.3 Receive the report from the Client or his designee following i approval of the dispositioned report. lR7 1

4.1.4 Upon receipt of the approved Nonconformance Report from the l Client or his designee, the Quality Assurance Site Supervisor or his l designee shall log-in the results of the review and distribute l copies of the report for implementation of the approved disposition l as necessary in accordance with approved procedures.

l

sicM tsten we pact 3 o, 4 EBA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION tNeompomAree HOU$ TON UGHTING AND POWER COMPANY Qg_III_6

, SOUTH TEXAS PROJECT

ELECTRIC GENEMATING STATION UNITS 1 & 2 4 R7 NONCONFORMANCES care 7/5/84 ointeron pV ury assonanct 4.2 Dispositions for all nonconformances to the design specifications or lR7 other documents originally requiring review and approval of the Client or his designee, must have the review and approval of the Client or his designee prior to implementation unless otherwise permitted by approved procedures.

4.3 The Quality Assurance Site Supervisor or his designee shall perform l a final review for closure of Nonconformance Reports generated in lR7 accordance with the requirements of this Section. l 4.4 The Quality Assurance Site Supervisor or his designee shall maintain on file, copies of all open Nonconformance Reports generated in accordance with the requirements of this Section.

5.0 DEFICIriCY NOTICES 5.1 Deficiencies in the quality of items and services which either l violate the restrictions of Paragraphs 5.2 and 5.3 of.this Section of the lR7

!!anual or are detected during final inspection at the construction site, I and which can be corrected by reworking or by standard repair procedures l (approved by the Client or his designee) during the normal course of construction, shall be documented on a Deficiency Notice. Copies of all Deficiency Notices shall be transmitted to the Quality Control Site Supervisor or his designee who will initiate Nonconformance Reports based on inf ormation given in the Deficiency Notices when he determines that this action is necessary. In this case, the Deficiency Notice becomes a part of the Nonconformance Report and only the Nonconformance Report is required to be resolved.

5.2 Items discovered to be out-of-tolerance or not to specification at routine checkpointe of an inspection process shall not be considered as a nonconformance, provided:

a) The condition is corrected prior to acceptance of the work.

b) The work does not proceed beyond the checkpoint until the correction is made.

c) The out-of-tolerance condition does not reflect on work previously accepted.

d) No violation of procedures or code is evident.

Damage which would affect the integrity of an item shall be classified as l a nonconformance and processed accordingly.

i l

I

~

e sos 4 tstPi sse PAGE OF 4 ESASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL S ECT10N INCOR POR AT ED HOUSTON UGHTING AND POWER COMPANY SOUTH TEXAS PROJECT QA-III-6

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l E

I MM# NONCONFORMANCES cart 7/5/84 lR g

ointeron a piv assonanct 5.3 An unacceptable ASME Code weld found during the normal l welding / inspection process shall be processed and reported on a l

" Process Data Checklist" form in accordance with approved Site Quality lR7 Control procedures. Any unacceptable weld found after the normal l welding / inspection process is completed shall be documented as l nonconforming in accordance with this Section of the Manual. l 5.4 The processing of Deficiency Notices shall be detailed in approved Site Quality Control procedures.

6.0 TREND ANALYSIS OF NONCONFORMANCE REPORTS AND DEFICIENCY NOTICES 6.1 Ebasco's Corporate Trending Copias of Nonconformance Reports from the sources mentioned above shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. The Quality Assurance Engineering Supervisor of Auditing subsequently receives the Nonconformance Report and makes an analysis of the available data with respect to quality trends. lR7 The trend analysis and distribution of subsequent reports shall be made in accordance with the requirements of Quality Assurance Procedure QA-D.3.

6.2 Client's Trending Copies of Nonconformance Reports (NCR's) and Deficiency Notices (DN's) from the sources mentioned above shall be transmitted to the Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Project Trend Program activity in accordance with their procedure (s).

7.0 RECORDS Nonconformance Reports shall be maintained in accordance with Section QA-I-6 of this Manual and/or approved Site Quality Assurance Instructions.

i I

~

stos4 sTri bes pace 1 or EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomaTro MOU$ TON UGHTING AND POWER COMPANY QA-III-7 SOUTH TEXA5 PROJECT N ELECTRIC GENERATING STATION UNITS 1 a 2 4

> mew sion I R7

[M oistcTom ap6tv assunanct CORRECTIVE ACTION oarc 7/5/84 g

1.0 SCOPE This Section establishes the requirements for the identification, analysis, and implementation of corrective action for safety-related items and services. The Section applies to activities performed at the construction site.

2.0 GENERAL 2.1 Corrective action shall be required for identified and documented nonconformance(s) associated with safety-related items and services.

2.2 The need for corrective action may be identified from the following sources:

a) Inspection activities performed by Site Quality Control.

b) Site Quality Records document reviews.

c) Quality Assurance audits performed by the Quality Assurance organization in accordance with Section QA-III-9 of this Manual.

d) Audits of Ebasco performed by the Client or his designee or regulatory bodies.

e) Nonconformances detected at the construction site as described in Section QA-III-6 of this Manual.

f) Audits of the Quality Assurance and Materials Applications organizations performed by the Management Audit Committee.

g) Surveillances performed by Site Quality Assurance.

2.3 Determination and review of corrective action items shall be made as early as possible in order to preclude the possible repetition of deficiencies.

2.4 During the review of all corrective action items, consideration shall be given to the training of personnel if it is determined that this was a cause of the deficiency.

2.5 Dissemination of corrective action information to responsible individuals shall be performed in a minimum length of time.

e tos.s asTP) kes Pact or EsASCo SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTlON INCORPORATED MOU$ TON UGHTING AND POWER COMPANY QA-III-7 SOUTH TEXAS PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l 2 lR#'

l 4

M CORRECTIVE ACTION oave 7/5/84 g batcTpVmaurv assunuct g

2.6 At the discretion of the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization, for corrective '

action items identified per Paragraph 2.2 of this Section, a lR7 corrective action document may be issued. This document shall be used when deficiencies detected are not isolated cases and when they are of sufficient magnitude to warrant a documented supervisory review in accordance with approved Quality Assurance procedures or instructions.

This document goes beyond the stendard audit action response required by audit reports. ,

2.7 For programmatic deficiencies detected by Site Quality Assurance, the maximum length of time for corrective action response shall be 20 working days fron the receipt of notice of deficiency or nonconformance.

Nonconformance reports shall be initiated and processed in accordance lR7 with Section QA-III-6 of this Manual. The maximum implementation time I shall be 20 working days from the acceptance of corrective action response, unless otherwise approved by the Director Quality Assurance lR7 or his designee from the Quality Assurance organization. l 2.8 It shall be the responsibility of the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization to assure that all required corrective action is implemented in a timely manner.

2.9 A preliminary assessment of the severity of deficiencies and nonconformances detected shall be made in accordance with Company Procedure N-23 or approved site procedures. The final responsibility for

, evaluation of all nonconformances for possible reportability rests with the Client or his designee. Reporting of nonconformances in accordance with 10 CFR 50.55e and its subsequent evaluation will be the responsibility of the Client or his designee.

3.0 DETERMINATION AND IMPLEMENTATION METHODS 3.1 Nonconformance Reports Generated at the Construction Site 3.1.1 Site Quality control shall perform direct inspection of activities at the construction site as required by Section QA-III-11 of this Manual.

3.1.2 Nonconformances noted during these inspection activities shall be documented on a Nonconformance Report in accordance with Section QA-III-6 of this Manual. Site Quality Control shall verify that the corrective action which has been stipulated on the completed form is implemented. Site Quality Control shall maintain a log of all required corrective action and shall review this periodically to assure the resolution of deficiencies and implementation of required corrective action.

esos-s ism s.e4 pace 3 or 4 ESA$Co $ERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomaTEo HoW5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-7 f ELECTRIC GENERATING STATION UNITS 1 & 2 4 g R7

  • CORRECTIVE ACTION oaTE 7/5/84 matcTongaurv assunanct 3.2 Site Quality Assurance Audits Site Quality Assurance shall perform audits of activities performed at the construction site as required by Section QA-III-9 of this Manual. Site Quality Assurance shall also perform follow-up action as described in Section QA-III-9 to assure that corrective action, if required, has been accomplished. If disagreement about the type or effectiveness of corrective action exists, the problem shall be reviewed by successively higher levels of management until satisfactory resolution is obtained.

3.3 Client or His Designee, or Regulatory Agency Audits Audits of construction site activities may be performed by the Client or his designee and/or appropriate regulatory agencies. If corrective action is required as a result of one of these audits, the Quality Assurance Site Supervisor or his designee from the Quality Assurance organization shall be responsible for obtaining a response from the cognizant individual (s) for submittal to the auditing body.

4.0 FINAL VERIFICATION OF CORRECTIVE ACTION IMPLEMENIATION In addition to his other duties, overall responsibility for verification of the implementation of required corrective action rests with the Quality Assurance Site Supervisor or his designee from the Quality Assurance organization. He shall be responsible for performing this verification for all items indicated in Paragraph 3.0 of this Section, and shall assure that lR7 the corrective action is implemented and in a timely manner. In the event that there is a disagreement between those individuals who detect a deficiency and those responsible for the function found to be deficient, the Quality Assurance Site Supervisor shall contact successively higher levels of management as necessary until resolution is obtained.

i

- .-n.- - - .- -e - - - - - , - - - . - , , - , , - . . , - - - , , -- - - + - - ,

sics-4 tsTen 5-64 PAGE or EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORPORATED HOU5 TON LIGHTING AND POWER COMPANY QA-III-7 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2 4 l lR7

< CORRECTIVE ACTION oarr 7/5/84 g o =acrogaurv anomancs g

5.0 DETERMINATION AND ANALYSIS OF QUALITY TRENDS 5.1 Ebasco's Corporate Trending In order to prevent the recurrence of quality problems, Ebasco has developed a method for the determination and analysis of quality trends. Copies of audit reports and Nonconformance Reports (or other appropriate documentation) mentioned above shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. The Quality Assurance Engineering Supervisor of Auditing subsequently receives all reports and makes an analysis of the available data lR7 with respect to quality trends. The trend analysis and distribution of subsequent reports shall be made in accordance with Quality Assurance Procedure QA-D.3.

5.2 Client's Trending Copies of Nonconformance Reports (NCR's), Quality Finding Reports (QFR's), and Management Corrective Action Requests (MCAR's) shall be transmitted by the Site Quality Assurance organization to the Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Project Trend Program activity in accordance with their procedure (s).

i I

L .- -.

^

\

l s tos-a istri s se ,,cg 1 or ESASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompom4TED HOUSTON UGHTING AND POWER COMPANY QA-III-8 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 5 l R7 M CONTROL OF SPECIAL PROCESSES care 7/5/84 oinicron my0n assunames l

1.0 SCOPE This Section of the Quality Assurance Manual establishes the requirements for the control of special processes at the construction site. Included herein are provisions for the establishment of critical process parameters, qualification of the processes, and training and qualification of personnel who perform the functions covered by this Section.

2.0 RESPONSIBILITIES 2.1 The Quality Assurance organization shall be responsible for the following:

2.1.1 Developing and implementing Site Quality Control procedures and for qualifying personnel to perform inspection of special processes.

2.1.2 Providing technical assistance for procedure review and development as required.

2.1.3 Qualifying personnel performing nondestructive examination.

2.1.4 Performance of audits in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.

2.2 The Materials Applications organization shall be responsib;e for the followings a) Development and qualification of welding procedures.

b) Providing technical assistance for procedure review and development as required by Site Quality Assurance and Site Quality Control.

c) Qualification of welders and welding operators.

d) Development of heat treating procedures.

2.3 The Construction organization shall be responsible for the following:

2.3.1 Implementing welding and heat treating procedures.

-_...v_ ,-,-- 1- _ _.

61094 ISTPl >04 pacg 2 o, 3 EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORPORATED HOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-8

{ ELECTRIC GENERATING STATION UNITS 1 & 2 5 l R7 l

'Nhd**1e CONTROL OF SPECIAL PROCESSES oat 7/5/84 oiaccion graurv assu===ct g

2.3.2 Developing and implementing procedures for other activities classified as special processes (eg, cadwelding, chemical cleaning, flushing) and for qualifying personnel to perform those functions.

2.4 The Ebasco Site NDE Laboratory, an extension of the Materials Engineering Laboratory, is responsible for developing and implementing nondestructive examination procedures.

3.0 METHODS FOR CONTROL OF SPECIAL PROCESSES 3.1 Site Special Process Procedures 3.1.1 Nondestructive examination procedures used at the construction site shall be developed by the Site NDE Laboratory and shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee, to assure compliance to the requirements of all applicable codes and standards, as a minimum. Conformance to these procedures and qualification requirements shall be verified through audits and surveillances performed by Site Quality Assurance.

3.1.2 All welding procedures used at the construction site shall be prepared by the New York Materials Applications organization. The weld procedures test material shall be prepared either at the home office or the construction site according to instructions for qualification provided by the New York Materials Applications organization.

3.1.3 Construction procedures for site implementation of welding and heat treating requirements shall be developed by the Site Welding Superintendent or his designee.

3.1.4 All welders installing safety-related components shall be qualified according to appropriate codes and standards. Welder qualification shall be performed by the Site Welding Superintendent or his designee. Verification of conformance to procedure and operator qualification requirements shall be performed in accordance with site procedures by Site Welding Superintendent (or his designee) surveillance, Site Quality Control inspection, and/or Site Quality Assurance audit and surveillance functions.

l I

~

l s tos4 is?Pt s-se pang 3 op 3 f

ESA5CO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTloN l INCORPORATED MOU5 TON LIGHTitlG AND POWER COMPANY QA-111-8 50UTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNIT 51 & 2 Rs VISiC N 5 l R7'

< CONTROL OF SPECIAL PROCESSES oars 7/5/84 oi.ccron a r n asm =ce g

3.1.5 All Construction procedures for site implementation of requirements for welding, heat treating, and other special processes shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee. All comments resulting from such reviews shall be resolved prior to procedure implementation.

4.0 RECORDS I

Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

l i

i i

I I

stos41sipt See pact I or 0 EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompom ATro MOU5 TON UGHTING AND POWER CoWPANY QA-III-9

, SOUTH TEXA5 PROJECT g ELECTRIC GENERATING STATION UNIT 51 & 2 5

,, l R7 QUALITY ASSURANCE AUDITS oare 7/5/84

.. . u ,. . ,40 - ..... . a ,

1.0 SCOPE Quality-related activities at the construction site and Ebasco home office are independently audited by the Quality Assurance organization. This Section establishes the requirements and guidelines for the preparation, performance, reporting, and follow-up of quality assurance audits as performed by Site Quality Assurance, home office Quality Assurance Engineering, and the Ebasco Management Audit Committee.

2.0 RESPONSIBILITIES 2.1 The Ebasco Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall assign qualified Site Quality Assurance personnel to perform audits of construction site activities.

2.2 The Quality Assurance Engineering Supervisor of Auditing shall assign qualified Quality Assurance personnel to perform home office audits of Ebasco site activities.

2.3 A committee chaired by the Quality Assurance Consulting Engineer shall conduct audits of the Ebasco Materials Applications and Quality Assurance organizations at the home office.

3.0 GENERAL REQUIREMENTS FOR AUDITS PERFORMED BY THE QUALITY ASSURANCE ORGANIZATION 3.1 Audit Personnel 3.1.1 Audit personnel shall be independent of direct responsibility for performance of the activity being audited.

3.1.2 Audit personnel shall be qualified to perform quality assurance audits based on experience and training as described in Quality Assurance Procedure QA-G.3.

3.2 Training and Orientation 3.2.1 Audit personnel shall have experience and training or orientation to assure their competence for performing audits. The conpetence of personnel to perform audits shall be developed by one or more of the following methodst a) Providing personnel with working knowledge of appropriate regulatory documents, practices, codes, and standards.

I

sios4 stri ves pace 2 o, 8 EsASCO SERVICE 5 NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION me aa a^7c houston UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-9

{ ELECTRIC GENERAT NG STATION UNITS 1 & 2 a t w sio N 5 l R7 I* 7bomicropg6%arv as so u.ca QUALITY ASSURANCE AUDITS omit 7/5/84 b) Training or orientation in general and specialized methods of planning and performing audits.

c) On-the-job training under direct supervision of a Lead Auditor.

3.2.2 The requirements for training and orientation of auditors shall be in accordance with Quality Assurance procedures.

3.3 Proficiency of Lead Auditors l lR7 3.3.1 Lead Auditors performing audits shall maintain their l proficiency through one or more of the following methods:

a) Regular, active participation in the audit process.

b) Review and study of codes, staadards, and procedures related to Quality Assurance Programs and program auditing.

c) Participation in orientation or training programs.

3.3.2 The Director Quality Assurance or his designee shall evaluate l Lead Auditors in accordance with Quality Assurance Procedure QA-G.3 lR7 to assure that the Lead Auditors are maintaining their proficiency. l 3.4 Scheduling of Audito 3.4.1 Audits shall be initiated as early in the life of the project or activity as practicable in order to assure timely implementation of the applicable Quality Assurance Program requirements, and to assure effective quality assurance during construction activities.

3.4.2 Audits shall be regularly scheduled on the basis of the status and safety importance of the activities to assure conformance to the Ebasco Nuclear Quality Assurance Program. Applicable elements of the Quality Assurance Program shall be audited at least annually or once within the life of the activity, whichever is shorter.

3.4.3 Supplenental audits shall be conducted whent a) Significant changes in the Quality Assurance Program are made.

4 s toe s < sten s.e4 nace 3 or 8 EsAsco stavicts NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN

'NCoaaoa"TEo HoWSTON LIGHTING AND POWER cow #ANY SOUTH TEXA5 PROJECT QA-III-9

, { ELECTRIC GENERATING STATION UNITS 1 & 2

,,y,,,, 5 [

[M QUALITY ASSURANCE AUDITS care 7/5/84 R7 Eatcrong auty assunanct

)

1 F b) There is evidence of significant noncompliance to the Quality Assurance Program.

i c) An assessment of the effectiveness of the Quality Assurance Progran is. requested.

1 d) It is necessary to verify implementation of corrective action.

l- e) It is considered necessary by the Quality Program Site j Manager.

1 3.5 Planning of Audits

! Preparation for audits shall include the development of a written

{ sudit plan of standard format which shall include or identify the j followingt a) Audit scope, t

l b) Requirements and applicable documents.

j c) Activities to be audited.

i i j d) Organization to be audited.

, e) Tentative audit schedule.

j f) Approved written procedures and/or checklists which assure that the organization will be audited to the extent necessary. These

! procedures and/or checklists shall provide for verifying i corrective action of deficiencies identified in previous audits. Audit procedures and/or checklists may be developed as part of a general audit program and need not be unique for each 4 audit.

l l 3.6 The Audit Team 3.6.1 The audit shall be performed by one or more individuals. A

! qualified Lead Auditor shall be established as the team leader for I

audits when teams are comprised of two or more auditors. When l audits are performed by only one individual, that individual shall lR7 l be a qualified Lead Auditor and considered to be the tesa leader. l' The tesa leader shall be responsible fort

a) Orientation of the team.

I

. g. yn.._..,,.,..pgy9- . ,y,,,.,9,wgy.-

+ _ -, .

y-M ,.p.-- n y- r + - - r-e,, ---,,wm-5 ,.w ,, v,,-wmm-,%,y-yg-y,m,.w,---m-.-,.,,,,y, 94-9_.-,.q.,,.

sics 4 4stei ses pace 4 o, 8 EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL ' $ECTloM INCORPOMATED HOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT -

QA-III-9 i

I ELECT 8!:0 se.nEilAT:!:0 &TATiON UNIT 51 & 2 l

navision 5 l R7

< QUALITY ASSURANCE AUDITS oave 7/5/84 ,

o

.ncro.g.u ry asse . cc

_ g b) Assuring communication between the team and the organization being audited.

c) Coordinating the preparation and issuance of audit reports.

d) Establishing the pace of the audit.

3.6.2 The team leader shall assure that the team is prepared prior to performing the audit. Information such as appropriate procedures, manuals and prior audit reports shall be made available to the team members. Each auditor shall be provided with any appropriate audit plans, procedures, or checklists necessary to performing the audit.

3.7 Audit Notification The organization to be audited shall be notified of a scheduled audit and the scope of the audit. Such notification shall be given a reasonable time before the audit is to be performed.

3.8 Audit Performance 3.8.1 Checklists and/or written procedures prepared during audit planning shall be used to conduct the audit.

3.8.2 An informal pre-audit conference shall be arranged at the audit site in order to confirm audit scope and discuss the audit plan.

3.8.3 A post-audit conference shall be conducted tot a) Inform those audited of the audit results.

b) Assure understanding of audit results.

3.9 Reporting of Audit Results 3.9.1 An audit report shall be compiled and shall be signed by the audit team leader. The audit report shall provides a) Description of the audit scope.

i b) Identification of the auditors.

l

~

s tos.4 istei s-se pace 5 o, 8 EsASCO SERvlCEs NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION

)

INCORPORATFD HOUSTON LIGHTING AND POWER COMPANY SOUTH TEXAS PROJECT QA-III-9

= ELECTRIC GENERATING STATION UNIT 11 & 2

,,,y,,,,, 5 l R7 MN,. .,.u ,, .,,- QUALITY ASSURANCE AUDITS cart 7/5/84

- un

. I c) Persons contacted.

d) A summary of the audit results, including an evaluation statement regarding the effectiveness of the Quality Assurance Program elements which were audited.

e) Detailed description of Quality Assurance Program deficiencies and causes thereof where possible.

f) Recommendations for correcting program deficiencies or improving the Quality Assurance Program, if possible.

3.9.2 The audit report shall be issued in a timely manner as defined in the applicable Quality Assurance procedure, but shall lR7 not exceed 30 days from the post-audit conference. l 3.10 Audit Follow-Up 3.10.1 A response to the audit report shall be prepared by the responsible individual and submitted within the required time period as established in the audit report, but shall not exceed 30 lR7 days. The response shall state the corrective action taken or to l be taken, and the date of completion. The audit team leader or another qualified Lead Auditor shall review the response for acceptance. As necessary, subsequent responses may be required to verify completion of corrective action.

3.10.2 Follow-up action shall be performed by a qualified Lead Auditor tot a) Assure that the written reply to the audit report is received.

b) Assure that corrective action is identified and scheduled for each program deficiency.

c) Confirm that deficiencies are resolved and corrective action, when necessary, is accomplished.

3.10.3 Follow-up action may be accomplished through written 1

communication, re-audit, or other appropriate means.

3.10.4 Follow-up action tsken shall be documented on the audit

report.

l l

l l

- j s tos4 isTel ves ,4cg 6 or 8 EsASCo SERVICE 5 NUCLEAR QUAUTY A55URANCE PROGRAM MANUAL SECTION eNcommonarto HOUSTON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-9 f ELECTRIC GENERATING STATION UNIT 51 & 2

, , y, , 5 l I* 8M o micron yu rv assonanct QUALITY ASSURANCE AUDITS oarc 7/5/84 R7 3.11 Trend Analysis of Audit Reports The Quality Assurance Engineering Supervisor of Auditing shall make an analysis of the available data (such as the audit reports lR7 mentioned above) with respect to quality trends, and report the result of the analysis. Distribution of the trend analysis reports shall be made in accordance with the requirements of Quality Assurance Procedure QA-D.3.

4.0 SPECIFIC AUDIT REQUIREMENTS 4.1 Management Audits 4.1.1 A committee chaired by the Quality Assurance Consulting Engineer is responsible for conducting audits of Ebasco Materials Applications and Quality Assurance functions to determine compliance with the Ebasco Quality Assurance Program requirements.

This committee is made up of personnel not in the Quality Assurance organization and who are qualified in accordance with criteria denoted in Ebasco Nuclear Procedure N-24. These audits will also include evaluating quality assurance policy effectiveness and assuring that appropriate implemeating procedures are available and are being complied with.

4.1.2 This auditing shall be accomplished on an annual basis in accordance with the requirements of Ebasco Nuclear Procedure N-24.

The management audit committee shall be comprised of at least two qualified representatives from either Ebasco Constructors Inc or l Engineering, and the QA Consulting Engineer. Each committee IR7 representative shall be appointed by the respective group l l

Vice President; however, no committee member can be directly engaged in any policy-making or administrative phase of the Ebasco Quality Assurance Program, but shall be knowledgeable in the general area of quality assurance. The committee shall be directly responsible to the Vice President Corporate Quality Programs. lR7 4.1.3 The committee shall prepare an audit report for each audit performed. This report shall be submitted directly to the Vice President Corporate Quality Programs, with copies to other lR7 appropriate parties.

l

sics.s estet s-se sace 7 or 8 EsASCo 5ERVICEs HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION tNcompomatto NOU$ TON UGHTING AND POWER COMPANY gg,777,9 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 n t v, s,o,, $

R A QUALITY ASSURANCE AUDITS o rc 7/5/84

.. . u y . . .. .. .. . .. m I

4.1.4 The Vice President Corporate Quality Programs shall be lR7 responsible for informing the concerned Ebasco management of the results of the audits performed by the committee. He shall also be responsible'for initiating the implementation of any changes or corrective action deemed necessary to improve the effectiveness of the Ebasco Nuclear Quality Assurance Program.

4.2 Audits by the Quality Assurance Oraanization 4.2.1 Site Quality Assurance shall audit the various quality-related activities performed by Ebasco organizations on the construction site in accordance with the requirements of this Section and applicable Site Quality Assurance procedures and instructions.

4.2.2 Training and qualification records for Site Quality control personnel shall be audited in accordance with Section QA-I-3, Paragraph 8.0, of this Manual.

4.2.3 Quality Assurance auditors shall have the authority to reject itens, services, or work for nonconformance to the specification, drawing, or quality control requirements.

4.2.4 Home office Quality Assurance Engineering will conduct periodic audits and evaluations of the construction site annually in IR7 accordance with this Manual and Quality Assurance Procedure QA-D.5.2.

5.0 AUDIT RECORDS 5.1 Records generated during audit preparation, performance, or follow-up shall be retained for all audits in accordance with the applicable requirements of Section QA-I-6 of this Manual and/or approved Quality Assurance procedures. Such records shall includes a) Audit plans and checklists.

b) Audit reports.

c) Written replies to audit reports.

d) Status of required corrective action.

e) Other docume:2ts which support audit findings and corrective action as appropriate.

r

~

sios e estas i.e4 nace 8 o, 8 EaASCO SERVICE 5 NUCLEAR QUALITY A$$URANCE PROGRAM MANUAL SECTION incompoastto NOU5 TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-9 d ELECTRIC GENERATING STATION UNIT 51 & 2

> ae visio 5 l R7 QUALITY ASSURANCE AUDITS cart 7/5/84

. .a u ,.g . .. .. ... .. a 5.2 Records of training and experience of auditors shall be maintained for all personnel who are performing audits or who have previously performed audits. These shall be retained for the same period of time as required for the audit reports with which the auditors are associated.

Maintenance and retention shall be in accordance with Quality Assurance Procedure QA-G.3.

l

r s tos4 tsTri s-se pact 1 or 3 EsASCO SERylCE5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION iNcompomATEo HOUSTON LIGHTING AND POWER COMPANY QA-III-10 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 3 l R

IDENTIFICATION AND CONTROL OF ITDiS cart 7/5/84

< oinacto= ovfp rv ssuaa.ca

_ g 1.0 SCOPE 1.1 This Section establishes the requirements for the identification and control of safety-related items at the construction site.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.

2.0 RESPONSIBILITIES 2.1 Site Quality Control shall be responsible to perform the following functions in accordance with written procedures:

a) Assure that items received from the Client or his designee at the construction site are properly identified and are accompanied by appropriate documentation traceable to the items.

b) Assure that all items shall be physically identified in accordance with Paragraph 3.0 of this Section of the Manual, and IR7 appropriate written procedures.

c) Assure that identification of items shall be transferred to inspection and test records and as-built documents in a manner sufficient to provide the required traceability.

d) Assure that items are handled and stored in cccordance with the requirements of Section QA-III-14 of this Manual so as to maintain identification.

2.2 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to assure compliance to the requirements of this Section.

3.0 GENERAL 3.1 Documented Quality control procedures require that items shall be physically identified by the following means, as applicable: lR7 a) Stenciled or etched markings b) Strip markings

stosa tsTri H e pact 2 o, 3 EBASCO SERVICE 5 HUCLEAR QUALITY A55URANCE PROGRAM MANUAL SECTION INCORPORATED MOU5 TON UGHTING AND POWER COMPANY QA-III-10 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNIT 51 & 2 3 l R7 b

osaacron gun assuna ca IDENTIFICATION AND CONTROL OF ITEMS oATE 7/5/84 V

c) Imprinted tape d) Tagging e) Stamping f) Color-coding g) Records traceable to the items h) Procedural control

1) Other appropriate means in accordance with approved Site Quality Control procedures 3.2 When it is impractical to physically identify individual small items, these may be identified as to heat numbers, batch, lot, or specification by applying markings to bags, bins, tanks, or other suitable containers.

3.3 Identification of items shall provida the required degree of traceability to pertinent documents.

3.4 All markings shal2 be clear, unambiguous, and indelible and shall not affect the function of the item when applied.

3.5 When an item is subdivided, markings shall be transferred to each part of the item.

3.6 Markings shall nc,t be obliterated or hidden by surface treatment or coatings unless other means of identification is substituted.

3.7 All safety related items and materials shall be controlled by one or I more of the following; l l

a) Uniquely identifiable and traceable. l I

b) Physically marked items are not traceable but readily retrievable. R7 I

c) Physically identified as to type and users tested l I

d) Identifiable as to type, by some physical characteristic or other I administrative control. l l

I l

s tos-a tsTP) s e4 Pact 3 or 3 EBASCO SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL S ECTION eNCORPORATED MOU$ TON UGHTING AND POWER COMPANY QA-III-10 SOUTH TEXA5 PROJECT j ELECTRIC GENERATING STATION UNIT 31 & 2 RE VISION 3 l R7 4

M DietCTOR @(46177 Assumase CE IDENTIFICATION AND CONTROL OF ITDiS oave 7/5/84 4.0 RICORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

i

l s tosa isTPi kea pact 1 o, 3 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTlON INCompomATED HOUSTON UGHTING AND POWER COMPANY QA-III-ll SOUTH TEXAS PROJECT I ELECTRIC GENERATING STATION UNITS 1 & 2 g aevision 5 l R'

INSPECTION DATE 7/5/84

'oiacion ougry assunance w

l 1.0 SCOPE This Section establishes the requirements for the inspection of safety-related items and services at the construction site as necessary to assure compliance with documented instructions, procedures, specifications, drawings, codes, and regulatory requirements.

2.0 RESPONSIBILITIES 2.1 Site Quality Control shall be responsible for the following:

a) Development of written procedures for the inspection of safety-related items and services which list the required inspection activities when existing inspection documents such as standard specifications and drawings do not provide an adequate basis for inspection.

b) Submittal of inspection procedures to Ebasco Site Quality Assurance for review and acceptance in accordance with Section QA-III-l of this Manual.

c) Preparation of reports for all inspections made.

d) Approval processing of inspection procedures and revisions thereto.

2.2 Site Quality Control shall be responsible for performing inspection activities in accordance with appropriate inspection documents.

2.3 Qualification of inspection personnel shall be in accordance with applicable Quality Assurance procedures and Paragraph 4.0 of this Section lR7 of the Manual. l

. 2.4 The Quality Assurance Site Supervisor or his designee from the Site

! Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance with the requirements of this Section.

3.0 GENERAL l 3.1 Inspection documents shall be prepared based upon the quality l

requirements contained in specifications, quality control documents and procedures, and applicable codes and standards.

I

sies-s estet s-se pace 2 o, 3 EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INComeomATEo HOU5 TON UGHTING AND POWER CoNPANY QA-III-11 SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNIT 51 & 2 5 l E

lR7 I* MM oinscrom Airy assunam et INSPECTION carc 7/5/84 g 3.2 If mandatory inspection hold points are required, the specific hold points shall be indicated on the inspection documents.

3.3 Inspection documents shall specify or reference as a minimum the activities to be performed, acceptance criteria, by whom activities are i performed, and the sequence in which the activities are to be performed.

3.4 Where mandatory inspection hold points are indicated on inspection documents or procedures, work may continue beyond a hold point only with the written approval of the Quality Control Site Supervisor or his qualified designee.

3.5 Inspection reports shall indicate the acceptability status of the items or services inspected with respect to meeting the applicable quality requirements.

3.6 When inspections are to be performed by use of a sampling program (ie, to determine the acceptability of a group of like-items based upon the results of an inspection of a representative number of items from the group), the sample size shall be identified on the inspection documents.

Justification for this sampling shall be based upon recognized standard construction practices and successful past experience, as well as the complexity and function of the activity, item, or service to be inspected.

4.0 TRAINING AND QUALIFICATION OF INSPECTION PERSONNEL 4.1 Inspection personnel shall have experience and training to assure their competence for performing inspection. The competence of personnel i to perform inspections shall be developed by one or more of the following methods:

a) Providing personnel with working knowledge of appropriate regulatory documents, practices, codes, and standards.

b) Training or orientation in general and specialized methods of planning and performing inspections, i c) On-the-job training under direct supervision of an experienced, l qualified inspector.

l l

sios.seste> >e4 pace 3 or 3 EBA5CO 5ERVICE5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION incommonareo MOU$ TON UGHTING AND POWER COMPANY QA-III-ll SOUTH TEXA5 PROJECT j ELECTRIC GENERATING STATION UNITS 1 & 2

,, o, 5 l

/dsd$k?*7w INSPECTION oatt 7/5/84 oiaccro ggurv assu==cs 4.2 The requirements for training and qualification of inspectors shall be in accordance with applicable Quality Assurance procedures, and qualification of inspectors shall be based upon consideration of the following:

a) Records of education and experience.

b) Test results, where applicable.

c) Results of capability determination.

4.3 Site Quality Control shall be responsible for scheduling and coordinating training for quality control personnel in advance of implementatica of the applicable inspection documents. This training shall be conducted in sufficient detail and with sufficient frequency to assure that the personnel responsible for the inspection fully understand the requirements contained in the applicable inspection documents.

4.4 Inspectors performing inspections shall maintain their proficiency through one or more of the following methods:

a) Regular, active participation in the inspection process.

b) Review and study of codes, standards, and procedures related to Quality Assurance Programs and program inspection.

4.5 The Director Quality Assurance or his designee shall periodically lR7 evaluate inspectors in accordance with applicable Quality Assurance procedures to assure that the inspectors are maintaining their proficiency.

5.0 RECORDS 5.1 All inspection documents shall be maintained in accordance with Section QA-I-6 of this Manual.

5.2 Records of training, experience, and certification of inspectors I shall be maintained for all personnel who are performing inspection or who have previously performed inspections. These records shall be retained for the same period of time as required for the inspection reports with which the inspectors are associated.

1

~

stos4<sreive4 ,,cc o, 2 EBASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCOR* ORATED MOU5 TON UmfTING AND POWER COMPANY QA-Ill-12 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l R7

/dbbd $56# - TEST CONTROL oave 7/5/84

< oian:ro grian issu===ct g

1.0 SCOPE

{

l.1 This Section describes the system employed at the construction site which assures that tests required to demonstrate that items will perform satisfactorily in service are identified and documented. The requirements of this Section apply to all phases of the testing program at the construction site, including, but not limited to: functional testing, proof testing, acceptance testing, and operational testing.

1.2 These tests shall be performed in accordance with written test procedures which include or reference the requirements and acceptance limits contained in applicable design documents.

2.0 RESPONSIBILITIES 2.1 Site Quality Control procedures shall provide for the following:

a) Assuring that all prerequisites for the given test have been met.

-b) Use of trained personnel to witness tests.

c) Identification of test equipment and the item to be tested.

d) Checking the condition of test equipment and the item to be

tested.

e) Use of devices calibrated in accordance with Section QA-III-13 of this Manual for the performance of tests.

f) Performance of tests under proper environmental conditions;

. eg, cleanliness.

g) Documentation of test results.

b) Acceptance criteria for test requirements.

2.2 Site Quality Assurance shall review and comment on the written procedures for tests covered by this Section. All comments shall be

, resolved prior to implementation of the procedures. These test i procedures shall be reviewed in accordance with Site Quality Assurance procedures and/or instructions for the inclusion of:

a) Provisions for assuring that all test prerequisites have been met, b) Identification of items to be. tested.

sics.4 istei s.e4 pace 2 ,, 2 ESASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION eNcompomatto HOUSTON UGHTING AND POWER COMPANY QA-III-12 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l lR#

h N TEST CONTROL care 7/5/84 g

< oi ccro. iry assv=uice g

c) Identification of calibrated devices or equipment to be used during testing.

d) Provisions for checking condition of test equipment and item to be tested.

e) Proper environmental conditions under which test is to be performed.

f) Test methods.

g) Operations to be performed, h) Inclusion of, or reference to, acceptance criteria.

1) Data to be recorded.

j) Requirements for qualified and/or certified personnel.

2.3 Test reports shall be reviewed and signed-off by Ebasco Quality Control in accordance with written procedure requirements to assure that lR7 test requirements have been satisfied.

2.4 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

3.0 RECORDS All records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

1 i

I l

. i 8109-4 ($TPI 5 84 PAGE 1 OF 3  !

ESASCO SERVICES NUCLEAR QUALITY AS5URANCE PROGRAM MANUAL SECTION sNcomPomarzo MOU$ TON UGHTING AND POWER COMPANY gg.III_13 SOUTH TEXAS PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2 4 g

! CONTROL OF MEASURING 7/5/84 lR7 I oracerongaurv assuaaace AND TESTING EQUIPMENT o.,

1.0 SCOPE  !

1.1 This Section describes the requirements for control, calibration, adjustment, and maintenance of measuring and testing devices used at the construction site for performing tests and inspections of safety-related items. These devices shall be calibrated and adjusted at specified, predetermined intervals using equipment having known valid relationships to nationally recognized standards.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-l of this Manual.

2.0 RESPONSIBILITIES Site Quality Control shall be responsible for performance of the following:

l 2.1 Establish a list which includes the measuring and testing devices to

' he calibrated and the frequency of calibration of these devices. The 1

method and interval of calibration shall be based on the type of device,

stability characteristics, required accuracy, and other conditions affecting measurement control.

2.2 Assure that the measuring and testing devices used are of the proper range, type, and accuracy to verify conformance to established requirements, i 2.3 Maintain a master calibration file for each measuring and testing i

device which includes at least the following information:

a) Name of device.

b) Device serial and/or identification number.

f c) Frequency of calibration.

d) Date of last calibration.

e) Name of party performing last calibration.

i f) Due date for next calibration.

sion tsven we pace 2 o, 3 ESASCO SERVICES HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORPORATED HOU5 TON LIGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-13

{ ELECTRIC GENERATING STATION UNITS 1 & 2 4 l

[ g CONTROL OF MEASURING 7/5/84 lR; I o. ccron w in m unu.ca AND TESTING EQUIPMENT D"E l

y I g) Condition of device at time of calibration and results of calibration.

h) Standard used for calibration.

1) Applicable calibration procedure.

2.4 Assure that all measuring and testing devices are marked with the identification number and when possible with calibration due dates. When this marking is not possible, alternative methods of tracing the device to its calibration due date (such as color-coding) shall be employed.

2.5 Assure that all measuring and testing devices are calibrated in accordance with the requirements of this Section and that the required documentation is provided.

2.6 Develop and maintain a system for issuance, collection, and return of all measuring and testing devices. This system shall provide for the identification of personnel withdrawing devices, methods for issuing devices, and methods for the collection and/or return of devices at prescribed calibration times or as otherwise required.

3.0 GENERAL 3.1 The standard of calibration shall be traceable to the National 'R7 Bureau of Standards (NBS) or a nationally recognized standard. If no national standards exist, the basis for calibration shall be documented and traceable to the equipment mat.ufacturer's recommended standards.

3.2 Measuring and test equipment (M&TE) shall be calibrated against working standards having tolerances not greater than one fourth (1/4) the tolerance of the M&TE. Tolerances greater than one fourth (1/4) shall be acceptable when limited by the state of the art. Reference standards shall be calibrated against higher-level standards of closer tolerance.

lR7 3.3 Methods shall be employed to assure proper handling, storage, and care of the M&TE in order to maintain its required accuracy.

l

l l

. 1 siou <stp> wa ..oc 3 or 3 EsA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomATEo HOU$ ton UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-13 f ELECTRIC GENERATING STATION UNITS 1 & 2 4 g

! g CONTROL OF MEASURING

"'E 7/5/84 lR7' I oincrongt.ury asmance AND TESTING EQUIPMENT l 3.4 Any M&TE found to be out-of-calibration shall be recalibrated. When M&TE is found to be out-of-calibration, damaged, lost, or stolen, an evaluation shall be made to ascertain the validity of previous inspection or test results and the acceptability of components inspected and/or tested since the last calibration check. When it is necessary to assure the acceptability of suspect items, the original required inspections and/or tests shall be repeated using properly calibrated equipment.

Suspect items on which a questionable device was used shall be listed on the Nonconformance Report (NCR) or Deficiency Notice (DN), as applicable.

3.5 If any of the M&TE is consistently found to be out-of-calibration, it shall be repaiyed or replaced.

3.6 Inspection and test reports shall include identification of M&TE used to perform the inspections and/or tests.

3.7 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance with the requirements of this Section.

4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

- -ea

k 1 5 a1o94 tsTP) 5-44 paor or ESA5c0 SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INeomponAvro MOU$ TON UGHTING AND POWER COMPANY SOUTH TEXA5 PROJECT QA-III-14 f ELECTRIC GENERATING STATION UNITS 1 & 2

,, y, ,, o , 5 l

! CONTROL OF RECEIVING, o.ve 7/5/84 I ocaceton pgurv assuaaac, HANDLING, AND STORAGE I w

l 1.0 SCOPE 1.1 This Section describes the methods employed during receiving, handling, storage, and installatioa to assure that all safety-related items received by Ebasco at the construction site will be usable when needed. These requirement? spply to both items received by Ebasco from the Client or his designee and Ebasco site-fabricated subassemblies which require temporary storage before assembly or installation. They also apply to both on-site and off-site facilities which are used for the storage of items under control of the construction forces.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.

1.3 The storage of safety-related items maintained in facilities under the direct control of the Client or his designee is excluded from the scope of this Manual.

2.0 RESPONSIBILITIES 2.1 The Ebasco Construction organization shall be responsible for the following:

a) Performance of receiving, handling, storage, maintenance, and cleaning activities in accordance with specifications provided by the Client or his designee and/or code requirements, b) Development of methods for special handling (off-loading) in accordance with manufacturer's recommendations and/or specifications provided by the Client or his designee.

c) Establishing storage areas to meet levels as briefly described below:

1) Level A - Indoor, controlled environment.
2) Level B - Indoor, heated and ventilation controlled.
3) Level C - Indoor or equivalent, ventilation controlled.
4) Level D - Outdoor.

l sics.s is *> s.e4 p.oc _2_.o r 5 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTlON eNeonnonareo Hou$ TON UGHTING AND POWER COMPANY SOUTH TEXAS PROJECT OA-III-14 I ELECTRIC GENERATING STATION UNIT 31 & 2

> ne vissoN 5 l i

j

! gg CONTROL OF RECEIVING, omic 7/5/84 lR7)

I arecron giu rv .s so. 4,. c . HANDLING, AND STORAGE l u I d) Development of general storage plana which list types of items and their intended storage locations and levels. Such plans shall be prepared prior to receipt of items from the Client or his designee.

! 2.2 Ebasco Site Quality Control shall be responsible for the following:

a) Qualification of personnel performing inspection functions applicable to receiving, handling, and storage, b) Assigning qualified quality control personnel for performance of inspection and/or surveillance of receiving, handling, storage, maintenance, and cleaning activities.

c) Performing and documenting inspection and/or surveillance activities in accordance with approved checklists to verify that receiving, handling, storage, maintenance, and cleaning activities, as described in Paragraph 2.1 of this Section, are lR7 performed in accordance with project requirements, d) Establishing and implementing methods for rejection of nonconforming items which provide adequate means of identifying the item as nonconforming and physically segregating the item where practical. When segregation is not practical, a status type indicator shall be used. Application and removal of status type indicators shall be by quality control personnel only.

2.3 Ebasco Site Quality Assurance shall be responsible for the performance of audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

2.4 The Client or his designee is responsible for procurement and initial receiving inspection of all safety-related items. However, if requested in writing by the Client or his designee to perform initial receiving inspection of safety-related items upon their arrival at the job site, Ebasco will conduct a complete program that covers the full parameters of this Section. Otherwise, Ebasco shall conduct a receiving inspection program as is applicable and in accordance with approved site procedures.

l l

sice-s isre> s se , ace 3 o, 5 EBA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomATED HOU$ TON UGHTING AND POWER COMPANY QA-III-14 SOUTH TEXAS PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

,,y,, 5 l

[ CONTROL OF RECEIVING, HANDLING, AND STORAGE D'78 7/5/84 lR7 I

weetonpjun asma.cz v

3.0 RECEIVING INSPECTION 3.1 Safety-related items utilized for fabrication, erection, installation, or modification shall be subjected to receiving inspection to assure conformance to the requirements of the applicable drawings, specifications, and other documents as required. Where source inspection is not performed, receiving inspection at site for acceptability will be performed.

3.2 Inspection Requirements Receiving inspection procedures shall be prepared by the Quality Control Site Supervisor or his designee in accordance with the requirements of this Manual. These procedures shall provide instructions and checklists for performing receiving inspection and shall include at least the following activities:

a) Documentation review to assure that the documentation package has been received and that a signed " Release for Shipment" form accompanies the items received, when applicable, b) Visual examination.

c) Marking and tagging for traceability.

d) Testing when specified.

i

e) Preparation for storage.

4.0 HANDLING 4.1 Randling practices applied to safety-related items shall assure minimum possibility for damage or loss of environmental protection.

4.2 Inspection Requirements Site Quality Control procedures shall provide for at least the following:

a) Review of handling requirements for safety-related items, b) Performance of appropriate inspections to assure that handling operations have not jeopardized item integrity.

6109-6 ($TP) F84 PAGE OF EBA5CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTloN mco=Pon Av eo Houston UGHTING AND POWER COMPANY QA-III-14 SOUTH TEXAS PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

,, 5 l E CONTROL OF RECEIVING, lR7 7/5/84

<*' HANDLING, AND STORAGE D^TE l u rv anu===cs oinc: rom 99r

[

5.0 STORAGE AND IN-PLACE PROTECTION 5.1 All safety-related items shall be stored in locations and storage levels as outlined below except for those items released from storage and placed in their permanent locations which shall be cared for, maintained, and inspected in accordance with design specifications and the applicable approved procedures. In place protection in permanent location is permitted for large items such as equipment, provided that the permanent location is ready for the item installation. If the permanent location does not afford the required level of protection, additional protection shall be provided to prevent degradation of the item. For in-place protection purposes, a permanent location shall be considered to be within the room and/or immediate vicinity in which the item is to be permanently installed.

5.2 Inspection Requirements Site Quality Control procedures shall provide for at least the following:

a) Monitoring of the storage levels listed below:

1) Level A - Indoor, controlled environment.
2) Level B - Indoor, heated and ventilation controlled.
3) Level C - Indoor or equivalent, ventilation controlled.
4) Level D - Outdoor.

b) Monitoring maintenance of storage areas to control such items as the following:

1) Physical condition of storage area.
2) Access to storage area.
3) Fire protection.
4) Prohibited materials.

I _ . -

. l sios-s (svot s e4 pace 5 o, 5 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INcompomarzo MOU$ TON UGHTING AND POWER COMPANY QA-III-14 SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2

,, , , 5 l E CONTROL OF RECEIVING, lR7 a A HANDLING, AND STORAGE 0^7C 7/5/84

  • l oat ton gy6tv assonanct g

c) Inspection of stored items and items protected in place to assure their integrity.

d) Verification of general storage plans which list types of items and their intended storage locations and levels.

e) Monitoring of storage areas to maintain proper segregation of materials. Items shall retain an appropriate identification for retrievability and inventory control, as applicable to the nature and use of the material, f) Monitoring of provisions for preservation of items, as required by special conditions.

g) Verification that the withdrawal of any component, assembly, system, or materials from the Client's or his designee's warehouse or storage areas shall be by the Requisition for Stored Items completed by the responsible supervisor or his designated representative. The request shall identify the material and applicable references to a drawing or specification.

5.3 The Client or his designee shall be responsible for the '

establishment of storage levels, maintenance, and any other applicable handling and storage requirements. The Ebasco Construction organization is responsible for developing and implementing procedures addressing these requirements.

6.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

r

sics.s isTP) s s4 Pact 1 o, 2 ESASCO SERVICE 5 NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION eNCoRPoRATED HOUSTON UGHTING AND POWER COhPANY SOUTH TEXA5 PROJECT QA-III-15 f ELECTRIC GENERATING STATION UNITS 1 & 2

,, g v, ,, o 3 g R7

< INSPECTION, TEST, AND OPERATING STATUS o*Te 7/5/84 oincnoy9eatav sso...cc 1.0 SCOPE 1.1 This Section establishes requirements for identifying and documenting the status of inspections and tests performed on safety-related items at the construction site and the status of the readiness of these items for initial operation.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual. Procedures and instructions shall include identification and authority of the individuals or groups responsible for application and removal of status indicators.

2.0 RESPONSIBILITIES Site Quality Control shall be responsible for the following:

2.1 Develop and implement a system for maintaining the status of safety-related items through the use of status indicators such as physical location and tags, markings, work travelers, stamps, or inspection records. This system shall provide for the identification and maintenance of the status of inspections and tests performed on these items throughout fabrication, installation, and erection. This system shall provide methods which assure that only items that have passed the required inspections and tests are used, installed, or operated. Where physical tagging is either impractical or insufficient, procedural control or ccher appropriate means for maintaining item status shall be employed.

2.2 Contro) and maintain a log of the issuance and removal of status indicators such as tags.

2.3 Develop and implement plans for the witnessing and documenting the results of inspections and tests.

2.4 Provide methods for assuring that all required inspections and tests are performed (checklists, travelers, etc).

l 2.5 Develop and implement a system for marking and tagging to indicate the initial operating status of safety-related items which are in test, rework, or other initial operating status, so as to prevent inadvertent operation.

.. . . . =- - --. . . _ _ .. - . . . - - . .

f *

. I

~

sios.4tsTP: we paog 2 or 2 EsASCO SERVICES NUCLEAR QUAUTY AS$URANCE PROGRAM MANUAL SECTION INCORPo4ATED NOU$ TON UGHTING AND P0eER COMPANY SDUTH TEXA5 PROJECT QA-III-15

{ ELECTRIC GENERATING STATION UNITS 1 & 2 3 g R7;

  • INSPECTION, TEST, AND OPERATING STATUS oats 7/5/84 ointeroyEaurv assumuct 2.6 Develop and implement a system for marking and tagging of all safety-related items during preoperational testing. This system shall ,

l provide for maintaining records of status indicators placed on boundaries or within systems turned over to the Client or his designee.

2.7 Maintain a log containing entries of all systems turned over from construction forces for preoperational testing. This log shall be maintained for quality status reference.

3.0 GENERAL 4 3.1 Quality Control procedures shall require that inspection and test status be maintained by the use of status indicators such as tags, markings, travelers, stamps, inspection records, work sequence plans, or other appropriate means.

3.2 The progress of fabrication, installation, erection, inspection, and

,, test shall be entered on appropriate documents. Provisions shall be made

for updating these documents to reflect current conditions.

i

! 3.3 Nonconforming safety-related items shall be clearly identified and i

marked and shall be processed in accordance with Section QA-III-6 of this Manual.

3.4 Records of . tests and inspection results shall be prepared and maintained in an orderly and systematic manner.

3.5 The Quality Assurance Site Supervisor or his designee frem the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

l 4.0 RECORDS

) Records pertaining to this Section shall be maintained in accordance with i Section QA-I-6 of this Manual. ,

f l

i

\

61o94 ISTPl F84 PAGE OF ESA$CO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCoRPORATEo HOUSTON UGHTING AND POWER COMPANY Appendix I SOUTH TEXA5 PROJECT

{ ELECTRIC GENERATING STATION UNITS 1 & 2 3 l R7 a

M4'A oinEcton gpun ASSURANCE TERMS AND DEFINITIONS car, 7/5/84 This Appendix contains certain terms and their definitions used in this Manual that are important to the uniform understanding of the Manual and its application. Where a term is used to convey a different intent than that related herein, clarification must be provided at the point of application:

ACTIVITIES AFFECTING QUALITY (Quality-related activities) - Activities affecting the quality of safety-related items, including designing, purchasing, fabricating, handling, shipping, storing, cleaning, erecting, installing, inspecting, and testing.

AUDIT - A planned and documented activity performed in accordance with written procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of a quality assurance program have been developed, documented, and effectively implemented in accordance with applicable regulatory documents, guidelines, or requirements. An audit does not include surveillance or inspection for the purpose of process control or product acceptance.

AUDITS (INTERNAL) - Audits performed by Ebasco personnel on those Ebasco organizations that are governed by the Ebasco Quality Assurance Program.

CLIENT OR HIS DESIGNEE " Client" is defined as Houston Lighting and Power Company and "his designee" as Bechtel Energy Corporation.

CONSTRUCTION OPERATION - Activities related to construction of a nuclear power station.

EBASCO HOME OFFICE - Office where project support and related functions are performed at Ebasco, New York.

INSPECTION - A phase of quality control which by means of examination, observation, or measurement determines the conformance of items or services to predetermined quality requirements.

INSTRUCTIONS - Written descriptions of activities to be performed, including job specifications, work instructions, shop construction drawings, job tickets, planning sheets, operating or procedure manuals, test procedures, or other written forms, to assure that the activity is adequately described.

ITEM - Any level of unit assembly, including structure, system, subsystem, component, part, or material.

stoM tsTP) H4 past 2 or 3 EBASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION mcom pom Atto HOU$ TON LIGHTING AND POWER COMPANY Appendix I SOUTH TEXA5 PROJECT

{o ELECTRIC GENERATING STATION UNITS 1 & i 3 l gR.s

< TERMS AND DEFINITIONS oate 7/5/84 g ose:roppaur,assuauce g

NONCONFORMANCE - A deficiency in characteristic, documentation, or procedure which renders the quality of an item or service unacceptable. Items discovered to be out-of-tolerance of specification at routine checkpoints of an inspection process shall not be considered as a nonconformance, provided:

a) The conditions are corrected prior to acceptance of the work.

b) The work does not proceed beyond the checkpoint until the correction is made.

c) The condition does not affect work previously accepted.

d) No violation of procedure or Code is evident.

QUALITY ASSURANCE (QA) RECORDS - are those records which furnish documentary evidence of the quality of items and of activities affecting quality. A document is considered a quality assurance record when the document has been completed. QA records may be either the original or a reproduced copy.

QA RECORDS (LIFETIME) - are those records which meet one or more of the following criteria:

a) Those which would be a significant value in demonstrating capability for proper functioning of safety-related items.

b) Those which would be of significant value in maintaining, reworking, repairing, replacing, or modifying the item.

c) Those which would be of significant value in determining the cause of an accident or malfunction of an item.

d) Those which provide required baseline data for in-service inspection.

QA RECORDS (NONPERMANENT) - are those records which meet all of the following criteria:

a) Those of no significant value in demonstrating capability for safe operation. ,

b) Those of no significant value in maintaining, reworking, repairing, replacing, or modifying the item.

I esos-s tsic) w4 pace 3 or 3 EBASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCORpOR ATED MOU$ TON UGHTING AND POWER COMPANY Appendix I SOUTH TEXA5 PROJECT f ELECTRIC GENERATING STATION UNITS 1 & 2 3 g R7

< TERMS AND DEFINITIONS oats 7/5/84 oiaccroypuaur, assua ca g

c) Those of no significant value in determining the cause of malfunction of an item.

d) Those which do not provide baseline data for in-service inspection.

QUALITY TREND - A consistent reporting of eaaformance or nonconformance with applicable criteris attributed to a specific organizational unit.

SAFETY-RELATED ITEM - Any item designated by the Client or his designee, in accordance with the guidelines established by the Licensing Department of the Client or his designee, to be Safety Class 1, 2, 3, Seismic Category I, or electrical Class IE and any other items as designated by the Licensing Department and indicated as safety-related in the PSAR or FSAR.

SERVICE - Performance of nuclear safety-related activities such as fabrication, inspection, nondestructive examination, installation, and test.

SPECIAL PROCESS - A special process is a fabrication, testing, or inspection operation whose correct performance is governed by parameters established during qualification testing for the operation, eg, welding and nondestructive testing.

_ _ _ _ . .- .. __ _ _ _ _ _ . . _ _ . __ __ . ~ .

a sio u < sten w e , cc 1 or 6 EsASCo SERVICE 5 HUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTioN INCORPORATED MOUSTON UGHTING AND POWER COMPANY Appendix II

, SOUTH TEXAS PROJECT

< ELECTRIC GENERATING STATION UtelTS 1 & 2 4

l EBASCO EXCEPTIONS TO US NUCLEAR " "

  • 5' " l a

I Mo accron yyun assuna cc REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1 D*TE 7/5/84 lRe EXCEPTIONS TO ANSI N45.2.5-1974:

1. ANSI N45.2.5-1974, Section 4.8, states " Pumped concrete must be sampled  ;

from the pump line discharge." In lieu of this statement, in process .

strength samples of pumped concrete are taken at the delivery point.

Correlation tests of air content, slump, and temperature are performed to verify these plastic properties of the concrete at the placement point in accordance with the following frequency requirements:

A. A minimum of two correlation tests are performed for each pumped placement exceeding 200 cu. yds.

]

l B. Otherwise, a minimum of two correlation tests per week are performed when any individual pumped placement during a week requires delivery of more than one truckload of concrete.

C. . During a week when a pumped placement exceeding 200 cu. yds. is made, the correlation tests performed on that placement will satisfy the weekly requirement for performing two correlation tests as specified in Item B above.

When any of the specified limits and/or tolerances on loss of air lR7 content, slump, or temperature are exceeded at the placement point, 4

correlation tests between the delivery point and placement point will be accomplished for each 100 cu. yds. of concrete placed as long as limits

and tolerances are exceeded. If two consecutive tests are out-of-i tolerance, corrective action will be implemented to adjust the limits for i the concrete entering the pump intake so that no concrete from the subsequent trucks will enter the pump intake as long as the tolerances i

are exceeded.

l

" Correlation Testing," " Delivery Point," and " Placement Point" are as i defined in ANSI N45.2.5-1978, Section 1.4.

2. Samples and frequency for cadweld testing is in accordance with ACI-359-ASME Section III, Division 2, issued for trial use and comment in 1973, including Addenda 1 through 6 (see Sections 3.8.1.6.3 and 3.8.3.6.3 of the South Texas Project Final Safety Analysis Report).

i 1

l

\

i

_ _ , _ - . _ . _ - . _ _ . __ __ _ _ _ ___ _ . _ __ ~_ - -

sios.4 ism w. ..ac 2 o, 6 EsASCO SERVICES NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION l

'"co"* * ^T ro '

NousTON usNTsNG ANo PowtR COMPANY Appendix 11

SOUTH TEXA5 PROJECT ,
ELECTRIC GENERATING STATION UNITS 1 & 2

" " * *

  • 4 '

S ERASCO EXCEPTIONS TO US NUCLEAR t

Mowccroapaun anuamece REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1

'" 7/5/84 IR7-l v i EXCEPTIONS TO ANSI N45.2.1-1973:

3. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will.be reviewed for applicability in each case. Installation plans or procedures-are also limited in scope to those actions or activities which are essential to maintain or achieve required quality. This is consistent with Section 2, Paragraphs 2 and 3, of ANSI N45.2-1971 which provides for examination, measurement, or testing to assure quality or indirect control by monitoring of processing methods. However, final cleaning or flushing activities will be performed in accordance with procedures specific to the system.

4. Section 4,' Pre-Installation Cleanness. This section states, " Items should not be delivered to the point of installation site sooner than necessary unless the installation location is considered a better storage i area." As an alternate to this requirement items may be delivered to the installation site sooner then absolutely necessary when determined to be advantageous for other considerations, for example, reduced handling or easier access, thereby reducing susceptibility to handling damage. In all such cases, equipment stored in place will be protected in accordance with Section 5 of ANSI N45.2.1-1973.

5.

Section 3.1.2, Cleanness Classifications - Class B. Ebasco interprets i

the lighting level of 100 footeandles to be guidance. It is Ebasco's normal practice that the lighting level for determining " metal clean" of

accessible surfaces of piping and components is determined by the l inspector. Typically he uses a standard two-cell flashlight supplemented by other lighting as he deems necessary.

EXCEPTIONS TO ANSI N45.2.2-1972:

6. Section 2.7, C1sssification of Itess. The four-level classification system may not be used explicitly. However, the specific requirements for each classification as specified in the standard will be applied to the items suggested in each classification and for similar items.

Classification differing from Section 2.7 will be considered acceptable provided no degradation is assured; for example, electric motors designed for outside service may be stored in Level C area rather than a Level B.

l

4 sios.e isrei we ,,cc 3 o, 6

- EsA5CO SERvlCE5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION incompoa^7ED Appendix II NOUSTON UGHTING AND POWER COMPANY

, SOUTH TEXA5 PROJECT

'j < ELECTRIC GENERATING STATION UNITS 1 & 2 4 l l

l g t

EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS "E v' 5' 0" 7/5/84 l R..

I INDICATED IN SECTION QA-I-1 o*TE oinscrogs.un me,u. ca 4

7. Section 6.2, Storage Areas. Paragraph 6.2.1 requires control and limited access to storage areas. In lieu of and to amplify this paragraph, the
following will be applied

" Access to storage areas for Levels A, B, and C will be controlled by the individual (s) responsible for storage. While the above areas will be IR7 j posted to limit access, other positive controls (other than that for the overall site area) or guards may not be provided. Level D areas will be. t posted with the storage level designation only." t

8. Section 5.5, Correction of Nonconformances. This section provides for j " rework" and "use-as-is" dispositions for nonconforming items. As an alternate, the " repair" disposition (as defined in ANSI N45.2.10-1973) will also be used.

l 9. Section 6.2.4, Storage of Food and Associated Items. Controlled areas, within storage areas, will be established for the storage of food, drink,

and salt tablets. These areas will be controlled through normal ,
supervision and inspection.

I

10. In Section 8, the control of documentation and re. cords shall be in i accordance with Section QA-I-6 of the Ebasco Nuclear Quality Assurance IR7 i Program Manual for the South Texas Project.

I j 11. Appendix A3.4.2, Inert Gas Blankets. There may be cases involving large ,

or complex shapes for which an inert or dry air purge flow is provided i

, rather than a static gas blanket in order to provide adequate protection i due to difficulty of providing a leakproof barrier. In these cases a  ;

. positive pressure purge flow may be utilized as an alternative to the leekproof barrier.

f EXCEPTIONS TO ANSI N45.2.3-1973:

12. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard. i Individual plans for each ites or system are not normally prepared unless i the work operations are unique.' However, standard procedures or plans j

! .w ill be reviewed for applicability in each case. Installation plans or l l procedures are also limited in scope to those actions or activities which

are essential to maintain or achieve required quality.

f

l l

em-s esim s.e4 ,,cc 4 y 6 ESASCO SERVICE 5 NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION INCOR, ORATED Appendix II HOU5 TON UGHTING AND POWER COMPANY

, SDUTH TEXA5 PROJECT

  • ELECTRIC GENERATING STATION UNITS 1 & 2 4 "E* SON l o ERASCO EXCEPTIONS TO US NUCLEAR 7/5/84 lRe E

&g, , , , , , , , ,

REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l o*TE l l

13. Alternative equivalent zone designations and requirements may be utilized to cover those situations not included in the subject standard; for example, situations in which shoe covers and/or coveralls are required but material accountability is not. In addition, zones might be combined into the next more restrictive category in order to reduce total number of zones.

EXCEPTIONS TO ANSI N45.2.4-1972:

14. Section 1.2, Applicability. The standard is applied to the items and systems identified in Paragraph 1.1.1 and to additional systems depending on the nature and scope of the work to be performed and the importance of the item or service involved.
15. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspections and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.

EXCEPTIONS TO ANSI N45.2.8-1975:

16. Section 1.1, Scope. The term "important items" will be interpreted to apply to those activities or quality attributes of an item or service that could affect a nuclear safety-related characteristic. For example, if a barrier is required for leakage control, but serves no structural function, the leaktight characteristic would be considered "important,"

but appearance, dimensional requirements, and structural features would not necessarily be considered important; or if a pump casing is required ,

for coolant boundary integrity, but the pump does not have to operate to provide for nuclear safety, those attributes which affect its operation would not be considered important from the standpoint of nuclear safety.

Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required qua*ity.

)

F b

siou ism w4 . cc 5 ,, 6 EBASCO SERVICES NUCLEAR QUAUTY ASSURANCE PROGRAM MANUAL SECTION ewconpomavao Appendix II NOUSTON UGHTING AND POWER C0aPANY

, SOUTH TEXA5 PROJECT l

) < ELECTRIC GENERATING STATION UNITS 1 & 2 '

""**'" 4

! k EBASCO EXCEPTIONS TO US NUCLEAR 4

a I

h REGULATORY GUIDES AND ANSI STANDARDS

[a.accropp urv anua ac, INDICATED IN SECTION QA-I-1 DATE 7/5/84 l R.

l

v I
17. Section 3.3, Processes and Procedures. The terms " installation site,"

. " installation area," and " site" used in this standard shall be interpreted as follows:

{

a) " Installation site" or " site" will be interpreted the same as

" construction site." When applied to documents, these may be at the central office or work area document control station.

i b) Installation area - Immediate proximity of location where work

} is to be performed.

18. .Section 3.5(e), Site conditions. This requirement will be applied only
if subsequent correction of adjacent nonconformances could damage the j item being installed. l i

j Section 4.6, Care of Items. HL&P retains the authority and is the -

" Responsible Organization" for temporary usage'of equipment or facilities

unless specific (ie, on a case-by-case basis) or general authority is
granted in writing to the Construction Manager's organization.

b

} EXCEPTIONS TO ANSI N45.2.9-1974:

i i 19. Section 1.4, Definitions. Quality Assurance Records - A document is .

I considered complete when it has finished full processing and has been l

issued for use in design, procurement,' construction,-or manufacturing. '
20. Section 1.4, Definitions. Authenticated Records - Those records which j are clearly identified as a statement by.the individual or organization holding responsibility. Handwritten signatures are not required if the
document or printout is clearly identified as a statement by the j reporting individual or organization.
21. For Appendix A, an installation shall be considered to.be in an "as constructed" condition if it is installed within the tolerances i established by Project Engineering indicated in the design output l documents.

i o

i s

I

. _ . , . -- m - . . , _ . . _ _ , _ . . _ . . , , - _s,, ,, . .- . . _ ,_

( -

l +

l 1

s tes.4 tsTPI s-a4 pace 6 n, 6 E8ASCO $ERVICEs NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL SECTION

'Ncoa*oa*Tro HOU$ TON UGHTING AND PorER COMPANY Appendix II

, SOUTH TEXA5 PROJECT

< ELECTRIC GENERATING STATION UNITS 1 & 2 4 g la EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS "E V' 5'0" 7/5/84 lR7 I /g g 7urv assuna ca o.accro w . INDICATED IN SECTION QA-I-l DaTE l

. I EXCEPTIONS TO ANSI N45.2.12-1977:

22. ANSI N45.2.12-1977, Section 4.5.1, states, "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed." This implies that the audited organization must provide the auditing organization with written notification detailing what corrective action was taken and when the corrective action was completed.

In actual practice, the audited organization will provide the auditing organization with documented corrective action including the date when the corrective action will be completed. The auditing organization will evaluate the corrective action response to determine if corrective action verification is necessary. If verification is necessary, the corrective action verification will be performed after the scheduled completion date and the result of the verification will be documented.

x a

I i

1

. . _ . __ _ . _ _ _ _ _ __ _