Amend 220 to License DPR-53 Concerning Provisions at Plant for Receiving,Possessing & Using Byproduct,Source & Special Nuclear Matl
ML20134N695
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 02/19/1997
From: Bajwa S
NRC (Affiliation Not Assigned)
To:
Shared Package
ML20134N697 List:
References
NUDOCS 9702240371
Download: ML20134N695 (5)


Text

_

p* Cthq p

1 UNITED STATES g

j NUCLEAR REGULATORY COMMISSION o

e WASHINGTON, D.C. 30666 4001

  1. '+9*****,o BALTIMORE GAS AND ELECTRIC COMPANY DOCKET NO. 50-317 CALVERT CLIFFS NUCLEAR POWER PLANT. UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No.220 License No. DPR-53 1.

The Nuclear Regulatory Comission (the Comission) has found that:

A.

The application for amendment by Baltimore Gas and Electric Company (the licensee) dated October 3, 1996, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Comission's rules and regulations set forth in 10 CFR Chapter 1; B.

The facility will operate in conformity with the application,.

the provisions of the Act, and the rules ar.d regulations of the Comission; There is reasonable assu' ance (i) that the activities authorized C.

r by this amendiaent can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Comission's regulations; i

D.

The issuance of this amendment will not be inimical to the comon defense and security or to the health and safet.y of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Comission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, paragraph 2.B.3 and 2.B.4, Page 3, of Facility Operating License No. DPR-53 is hereby amended to read as follows:

3.

Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; 9702240371 970219 PDR ADOCK 05000317 p

PDR

J i

2 3.

This license amendment is effective as of the date of its issuance to be implemented within 30 days.

FOR THE NUCLEAR REGU ATO COMISSION du h

S.

inghBajwa,ActingDirecht Proj ct Dire ^torate I-1 j

Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Attachment:

Page 3 of License I

Date of Issuance:

February 19, 1997 1

i

b e

1 ATTACHMENT TO LICENSE AMENDMENTS AMENDMENT NO.220 FACILITY OPERATING LICENSE NO. DPR-53 DOCKET NO. 50-317 l

l Revise License DPR-53 as follows:*

]

Remove Paaes Insert Paaes 3

3 4

4*

5 i

)

  • Indicates Rollover Page t

0 h

1 I

i 1

i 1

1

-)

i d

3.

Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; 4.

Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C.

This license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Se:tions 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

1.

Maximum Power Level The licensee is authorized to operate the facility at steady state reactor core power levels not in excess of 2700 megawatts (thennal).

2.

Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.

are hereby incorporated in the license. The W e,nsee shall operate the facility in accordance with the Technical Specifications.

1 3.

The licensee is required to implement and maintain the administrative controls identified in Section 6 of the NRC's Fire Protection Safety Evaluation on the facility dated September 14, 1979.

4.

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Consiission-approved physical security, guard training and qualification, and safeguards contingency plans including amendment:

made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authorityof10CFR50.90and10CFR50.54(p). The plans, which contain Safeguards Infonnation protected under 10 CFR 73.21, are entitled:

"Calvert Cliffs Nuclear Power Plant Physical Security Plan," with revisions submitted through February 17, 1988; Amenchnent No. 3,11,15,1."",220

i "Calvert Cliffs Nuclear Power Plant Guard Training and Qualification Plan," with revisions submitted through November 1,1985; and "Calvert Cliffs Nuclear Power Plant Safeguards Contingency Plan," with revisions submitted February 9,1988. Changes made in i

)

accordance with 10 CFR 73.55 shall be imslemented in accordance with the schedule set forth tierein.

s 1

5.

Secondary Water Chemist?y Monitorino Proaram The licensee shall implement a secondary water i

chemistry monitoring program to inhibit steam generator tube degradation. This program shall include:

4 t

a.

Identification of a sampling schedule for the critical parametets and control points for these parameters.

b.

Identification of the procedures used to i

quantify parameters that are critical to control points.

l c.

Identification of prccess sampling points.

j d.

Procedure for recording and management of data.

e.

Procedures defining corrective actions for off

}

control point chemistry conditions; and 4

f.

A procedure identifying the authority responsible for the interpretation of the data and the sequence and timing of administrative events required to initiate corrective action.

D.

This license is effective as of the date of issuance and shall expire at midnight July 31, 2014.

FOR THE ATOMIC ENERGY COW 41SSION Original Signed by Roger S. Boyd A. Giambusso, Deputy Director -

~

for Reactor Projects Directorate of Licensing

Attachment:

Appendices A & B -

Technical Specifications Date of Issuance:

July 31,1974

. Amen &nent No. 11,15,50,13,100,220l