Monthly Operating Repts for Jan 1997 for Calvert Cliffs Nuclear Power Plant Units 1 & 2
ML20134M289
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 01/31/1997
From: Katz P, Olsen H
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9702200175
Download: ML20134M289 (12)


Text

.

in PETE: IL K4rz Baltimore Gas and Electric Company Plant General Manager Calvert Cliffs Nuclear Power Plani Calven Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby. Maryland 20657 410 495-4101 February 14,1997 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & 50-318 January 1997 Operating Data Reoorts The subject reports are being sent to you as required by Technical Specification 6.6.4.

Should you have any questions, please contact Mr. Kenneth Greene at (410) 495-4385.

Very truly yours, hwfod PCK-PEK/IIOO/bjd Attachments cc:

D. A. Brune, Esquhe R. A. Ilartfield, NRC J. E. Silberg, Esquire R.1. McLean, DNR Director, Project Directorate I-1, NRC J.11. Walter, PSC A. W. Dromerick, NRC P. Lewis, INPO

11. J. Miller, NRC K. N. Larson, ANI Resident inspector, NRC

,t 9702200175 970131 h

g PDR ADOCK 05000317 R

PDR 200072

4 i

UNIT 1 OPERATING DATA REPORT Docket-No. 50-317 February 14, 1997 Prepared by Herman O. Olsen Telephone : (410) 4 95-6734 l

OPERATING STATUS l

l 1.

UNIT NAME Calvert Cliffs Unit 1 l

2. REPORTING PERIOD JANUARY 1997 3.

LICENSED THERMAL POWER (MWT) 2700 l

4. NAMEPLATE RATING (GROSS MWe) 918
5. DESIGN ELECTRICAL RATING (NET MWe) 845 6.. MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 865 7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 835 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A Year-Cumulative This month to-Date to Date l
11. HOURS IN REPORTING PERIOD 744 744 190,549
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 138,039.5
13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
14. HOURS GENERATOR ON LINE 744.0 744.0 135,230.9
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
16. GROSS THERMAL ENERGY GENERATED (MWH) 2,000,798 2,000,798 344,729,117
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 670,104 670,104 114,435,466
18.. NET ELECTRICAL ENERGY GENERATED (MWH) 643,930 643,930 108,992,122
19. UNIT SERVICE FACTOR 100.0 100.0 71.0
20. UNIT AVAILABILITY FACTOR 100.0 100.0 71.0
21. UNIT CAPACITY FACTOR (USING MDC NET) 103.7 103.7 69.2
22. UNIT CAPACITY FACTOR (USING DER NET) 102.4 102.4 67.7
23. UNIT FORCED OUTAGE RATE 0.0 0.0 8.4
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):

N/A

25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

l N/A i

3 l

l i

..-=.-

UNIT SHUTDOWNS AND POWER REDUCTIONS

~

DOCKET NO.

50-317 UNIT NAME Calvert Cliffs-UI DATE February 14,1997 -

COMPLETED BY Herman O. Olsen TELEPilONE (410)495-6734 REPORT MONTH January 1997 l

l METIIOD OF j

=

SIIUITING LICENSEE l

CAUSE & CORRECTIVE l

DURATION l DOWN i

EVENT SYSTEM COMPONENT ACTION TO i

NO.

I DATE I TYPEI (IIOURS) i REASON 2! REAC10R3 i REPORT #

CODE 4 CODE 5 PREVENT RECURRENCE i

l j

There were no significant power reductions for this l

l I

month.

i i

i i

1 l

l j

t I

j i

i l

i 1

I I

I 3

i l

i i

i i

i 1

1 i

j l

I l

l l

l i

s I F: Forced 2 Reason:

3 Method:

4 IEEE Standard 805-1984 S: Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.

C - Refueling 3 - Automatic Scram.

5 IEEE Standard 803A-1983 D - Regulatory Restriction 4 - Continued l

E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9 - Other G - Operational Error I

11 - Other i

1

.~

...m...

m

m....

..-....---,r

. - _ _ - -. = -. _.

i I

REFUELING INFORMATION REOUEST l.

Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No.1.

2.

Scheduled date for next refueling shutdown: March 1998 j

3.

Scheduled date for restart following refueling: May 1998 l

1 4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license e.Ter.d.r.cr.t?

4 I

N/A l

I 5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

f N/A i

6.

Important licensing considerations associated with the refueling.

j N/A J

j 7.

The number of fuel assemblics (a) in the core and (b) in the spent fuel storage pool.

l (a) 217 (b) 1402 (Note 2)

{

\\

Spent fuel pools are common to Units 1 and 2.

8.

(a) 'Ihe present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.

(a) 4710 (Note 1)

(b)0 9,

The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.

March 2007 NOTE 1:

4710 total licensed site storage capacity.

(1830 pool + 2880 ISFSI)

NOTE 2:

360 Spent Fuel Assemblies in the ISFSt.

l i

.i

(

AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-317 Calvert Cliffs Unit No. 1 February 14, 1997 Prepared by Herman O. Olsen Telephone: (410) 495-6734 JANUARY 1997 Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 869 17 869 2

869 18 869 3

865 19 869 4

868 20 868 5

869 21 866 6

869 22 868 i

7 867 23 869 8

869 24 869 9

869 25 787 10 869 26 864 l

11 869 27 867 12 870 28 867 13 869 29 868 14 869 30 868 15 867 31 868 16 868 l

I l

l l

1 i

UNIT 2 OPERATING DATA REPORT j

Docket No. 50-318 February 14, 1997 Prepared by Herman O. Olsen Telephone : (410) 4 95-6734 OPERATING STATUS

~~~~____________

1.

UNIT NAME Calvert Cliffs Unit 2 2.

REPORTING PERIOD JANUARY 1997

3. LICENSED THERMAL POWER (MWT) 2700
4. NAMEPLATE RATING (GROSS MWe) 911 5.

DESIGN ELECTRICAL RATING (NET MWe) 845 6.

MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 870 7.

MAXIMUM DEPENDABLE CAP'Y (NET MWe) 840 8.

CHANGE IN CAPACITY RATINGS NONE 9.

POWER LEVEL TO WHICH RESTRICTED N/A

10. REASONS FOR RESTRICTIONS N/A i

Year-Cumulative This month to-Date to Date

11. HOURS IN REPORTING PERIOD 744 744 173,904 j
12. NUMBER OF HOURS REACTOR WAS CRITICAL 744.0 744.0 130,586.4
13. REACTOR RESERVE S3UTDOWN HOURS 0.0 0.0 1,296.6
14. HOURS GENERATOR ON LINE 744.0 744.0 128,879.0
15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0 l
16. GROSS THERMAL ENERGY GENERATED (MWH) 1,978,113 1,978,113 331,072,497
17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 662,564 662,564 109,399,978 l
18. NET ELECTRICAL ENERGY GENERATED (MWH) 636,876 636,876 104,614,059
19. UNIT SERVICE FACTOR 100.0 100.0 74.1
20. UNIT AVAILABILITY FACTOR 100.0 100.0 74.1
21. UNIT CAPACITY FACTOR (USING MDC NET) 101.9 101.9 72.7
22. UNIT CAPACITY FACTOR (USING DER NET) 101.3 101.3 71.2
23. UNIT FORCED OUTAGE RATE 0.0 0.0 5.3
24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION) :

Refueling 03/14/97 46 days

25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:

N/A

i DOCKET NO. 50-317 CALVERT CLIFFS - UNIT 1 Feburary 14,1997

SUMMARY

OF OPERATING EXPERIENCE January 1997 The unit began the month at 100% power.

On 01/25/97 at 0940 power was reduced to 85% to perform Main Turbine Control Valve testing. At the completion of the required testing, power was raised to 97% at 1935 to allow for waterbox cleaning and

{

heater drain tank maintenance. Power was returned to 100% on 01/26/97 at 0150.

The unit operated at 100% for the remainder of the month.

l 1

i

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO 50-318-UNIT NAME Calvert Clifts-U2 -

DATE February 14,1997 COMPLETED BY lierman O. Olsen TELEPilONE (4101495-6734 REPORT MONTH January 1997 l

i ML'TilOD OF

[

l SilOTTING LICENSEE l

CAUSE & CORRECTIVE l

. DURATION !

DOWN EVENT 1 SYSTEM COMPONENT ACTION TO NO.

t DATE TYPEI ! (llOURS)

REASON 2} REACTOR 3 REPORT #

CODE 4 CODE 5 PREVENT RECURRENCE i

l l

There were no significant power reductions for this

=

i l

l month.

i j

I j

t i

l 1

t 4

I i

I l

l I

I l

1 I

I i

l l

I i

i t

t i

i 1

1 l

i i.

i l

i i

i i

i l

l t

'i l

i i

l 1

i l

i l

l t

i i F: Forced 2 Reason:

3 Method:

4 IEEE Standard 805-1984 S: Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 - Manual Scram.

C - Refueling 3 - Automatic Scram.

5 IEEE Standard 803A-1983 D - Regulatory Restriction 4 - Continued E - Operator Training & License Examination 5 - Reduced Load F-Administrative 9 - Other G - Operational Error 11 - Other

REFUELING INFORMATION REOUEST t

l.

Name of facility: Calvert Cliffs Nuclear Power Plant, f ' nit No. 2 2.

Scheduled date for next refueling shutdown: March 14,1997 3.

Scheduled date for restart following refueling: April 30,1997

  • 4.

Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment?

Yes.

I License Amendment to adopt the requirements of Appendix J, Option B for Type B a.

and C testing.

b.

License Amendment to allow the substitution of a blind flange for the outside purge valve pressure boundary in Modes 1-4.

c.

Deleted.

  • d.

License Amendment to lower the reactor coolant flow which supports an increased number of steam generator tubes plugged.

e.

Deleted.

  • f.

License Amendment to allow electrosleeving as a repair method for steam generator tubes.

i 5.

Scheduled date(s) for submitting proposed licensing action and supporting information.

a.

November 26,1996 b.

August 1,1996 c.

Deleted

  • l d.

January 31,1997

  • e.

Deleted a f.

July 26,1986 6.

Important licensing considerations associated with the refueling Noce.

7.

The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.

(a) 217 (b) 1402 (Note 2)

Spent fuel pools are common to Units 1 and 2.

8.

(a) 'Ihe present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblics.

1 (a) 4710 (Note 1)

(b) 0 l

9.

The projected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining space for one full core off-load.

March 2007 1

NOTE 1:

4710 total licensed site storage capacity.

(1830 pool + 2880 ISFSI) i 1

NOTE 2:

360 Spent Fuel Assemblies in the ISFSI.

Entry has changed since last reported.

J

)

AVERAGE DAILY UNIT POWER LEVEL

)

Docket No. 50-318 Calvert Cliffs Unit No. 2 February 14, 1997 Prepared by Herman O.

Olsen Telephone: (410) 495-6734 JANUARY 1997 Average Daily Power Level Average Daily Power Level Day (MWe-Net)

Day (MWe-Net) 1 841 17 864 2

855 18 862 1

3 839 19 862 4

823 20 863 5

822 21 864 j

6 843 22 855 7

863 23 840 8

861 24 862 9

861 25 847 10 862 26 861 11 862 27 862 12 863 28 856 13 864 29 863 14 864 30 863 15 864 31 863 I

16 864 l

l

~ =.. - - _.

i DOCKET NO. 50-318 CALVERT CLIFFS - UNIT 2 i

Feburary 14,1997

SUMMARY

OF OPERATING EXPERIENCE January 1997 t

The unit began the month at 95% power. The unit was operating at less than 100% as a conservative measure, due to a reduction in the cooling capacity of the main power output transformer (U-220000-22).

l Power was returned to 100% on 01/01/97 at 1420.

i Due to the reduced cooling capacity of the main power output transformer (U-22000-22) power was i

reduced periodically throughout the month, as indicated below, based on the outside ambient j

temperature.

On 01/02/97 at 1325 power was reduced to 97%. Power was further reduced to 95% on 01/03/97 at 1340. Power was returned to 100% on 01/06/97 at 2230.

On 01/22/97 at 1325 power was reduced to 97%. Power was further reduced to 95% on 01/23/97 at 1450. Power was returned to 100% on 01/23/97 at 2320.

i I

On 01/23/97 at 2350 power was reduced to 97%. Power was returned to 100% on 01/25/97 at 2030.

j On 01/28/97 at 0830 power was reduced to 97%. Power was returned to 100% on 01/28/97 at 1620.

The unit operated at 100% power for the remainder of the month.