Corrected Monthly Operating Repts for Aug 1996 for Zion,Units 1 & 2
ML20134K749
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 08/31/1996
From: Cygan J
COMMONWEALTH EDISON CO.
To:
Shared Package
ML20134K748 List:
References
NUDOCS 9611200016
Download: ML20134K749 (2)


Text

'

CORRECTED PAGE OPERATING DATA REPORT DOCKET NO. 50-295 l DATE 09/13/96 COMPLETED BY J CYGAN TELEPHONE (847)746-2084 -

X3169 l

l OPERATING STATUS

1. Unit Name: Zion Unit 1
2. Reporting Period: 0000 080196 to 2400 083196 Notes ,
3. Licensed Thermal Power (MWt): 3250 i
4. Nameplate Rating (Gross MWe): 1085 l
5. Design Electrical Rating (Net MWe): 1040
6. Maximum Dependable Capacity (Gross MWe): 1085
7. Maximum Dependable Capacity (Net MWe): 1040
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.

Give Reasons: N/A l

9. Power Level To Which Restricted, if Any (Net MWe): N/A
10. Reasons For Restrictions, If Any: N/A This Month Yr-to-Date Cumulative
11. Hours in Reporting Period 744.0 _

5.855.0 198.719.0

12. Number Of Hours Reactor Was Critical 558.3 4.930.0 134.968.9
13. Reactor Reserve Shutdown Hours 0.0 0.0 2.612.8
14. Hours Generator On-Line 548.3 4.649.3 131.046.5
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1.712.955.0 14.820.234.0 386.515.831
17. Gross Electrical Energy Generated (MWH) 570.882.0 4.949.730.0 125.855.803
18. Net Electrical Energy Ge W ed (MWH) 546.460.0 4.749.655.0* 119.912.607*
19. Unit Service Factor 73.7 79 4 65.9
20. Unit Availability Factor 73.7 79.4 65.9
21. Unit Capacity Factor (Using t!CC Net) 70.6 78.0 58.0
22. Unit Capacity Factor (Using DER Net) 70.6 78.0 58.0
23. Unit Forced Outecp Rate 26.3 lu.8 16.0
24. Shutdowns Schedwi Over Next 6 Months (Type. Date, and Duration of Each):
25. If Shut Down At End Of Report Period. Estimated Date of Startup: 9/17/96
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
  • Corrected numbers 9611200016 961113 PDR R

ADOCK 05000295 pg

^

CORRECTED PAGE OPERATING DATA REPORT DOCKET N0. 50-304 DATE 09/13/96 COMPLETED BY J. CYGAN TELEPHONE (847)746-2084 X3169 OPERATING STATUS

1. Unit Name: Zion Unit 2
2. Reporting Period: 0000 080196 to 2400 083196 Notes
3. Licensed Thermal Power (MWt): 3250
4. Nameplate Rating (Gross MWe): 1085
5. Design Electrical Rating (Net MWe): 1040
6. Maximum Dependable Capacity (Gross MWe): 1085
7. Maximum Dependable Capacity (Net MWe): 1040
8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power ievel To Which Restricted, If Any (Net MWe): N/A
10. Reasons For Restrictions, If Any: N/A

! This Month Yr-to-Date Cumulative 1

11. Hours In Reporting PerioG 744.0 5.855.0 192.432.0-
12. Number Of Hours Reactor Was Critical 744.0 5.413 9 13/.946.2
13. Reactor Reserve Shutdown Hours 0.0 0.0 226.1
14. Hours Generator On-Line 744.0 5.256.1 134.666.3
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0 16, Gross Thermal Energy Generated (MWH) 2.397.323.0 16.244.302.0* 401.260.213*
17. Gross Electrical Energy Generated (MWH) 797.214.0 5.393.245.0 129.649.549
18. Net Electrical Energy Generated (MWH) 764.435.0 5.180.674.0* 123.657.404*
19. Unit Service Factor 100.0 89.8 70.0
20. Unit Availability Factor 100.0 89.8 70.0
21. Unit Capacity Factor (Using MDC Net) 98.8 85.0* 61.8 i 22. Unit Capacity Factor (Using DER Net) 98.8 85.0* 61.8
23. Unit Forced Outage Rate 00.0 1.6 13.7
24. Shutdowns Scheduled Over Next 6 Months (Type. Date, and Duration of Each):

Refuelino Outaae (Z2R14) Startina Seotember 19. 1996 and Lastina 58 days.

25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units In Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
  • Corrected numbers i