Text
,
SIEMENS i
(..
October 28,1996 JBE:96:097 U.S. Nuclear Regulatory Commission Attn.: Mr. Robert C. Pierson, Chief Licensing Branch Division of Industrial & Medical Nuclear Safety, NMSS Washington, DC 20555 i
Dear Mr. Pierson:
References:
- 1. Memorandum, M. Adamt
... C. Pierson, " Meeting Summary, September 4,1996, With Jim Edgar of Siemens Pow. Corporation", dated September 19,1996.
j 1
- 2. Letter, R. C. Pierson to L. J. Maas, " Possession of Uranium Enriched to Greater Than 5 i
Weight Percent in U 235 (TAC No. L21656)", dated September 16,1996.
- 3. Letter, R. C. Pierson to L. J. Maas, "SNM-1227 License Section 3.2.3", dated September 11,1996.
Per recent conversations between M. T. Adams of your staff and myself and as described in Reference 1, enclosed are two copies of a reprinted license application dated October 28,1996 on all pages. With the exception of the changes described below, the application is simply a recompilation changing the various page dates to a common one so that a single application date can be referenced in the license.
The changes to the license conditions in Part I are, with the exception of a correction to a regulatory reference and an oversight, those requested by the NRC. They are.
Chapter 1
- Removal of >5%
19.99% enriched uranium in Section 1.4.1 (except for 350 grams of assy enrichment) and Table 1-1.1 as specified in Reference 2.
Revision of the first paragraph of Section 1.6.1 so that the exemption for criticality detection monitoring of the lagoon applies only to SNM under water.
Removal of the subsequent paragraphs of Section 1.6.1 which, through oversight, had been submitted with the renewal application after having been removed from the existing licen on March 25
,992, 9611080076 961028 PDft ADOCK 07001257 B
PDR,
Siemens Power Corporation 1
Nuclear Duision 2101 Horn Rapids Road Tel. (509)375-8100 hgf,#,
e r
I Engineenng & Manufacturing P.O. Box 130 Fax: (509)375-8402 Jj Richland. WA 993524130 7
ir Mr. R:but C. Pi:rson JBE:96:097 October 28,1996 Page 2 Chapter 3 i
Removal of the ninth paragraph of Section 3.2.3 which allowed DAC adjustments based on e
model changes, as requested in Reference 3.
_ Correction of regulatory reference from "10 CFR 20.205" to "10 CFR 20.1906"in e
paragraph 3 of Section 3.2.6.2.
1 The changes in Part 11 are:
Chapter 9 l
Replacement of the 1991 Siemens Annual Report in Appendix A with that of 1995.
Chapter 10 Update of the emergency power description in Section 10.2.1.2.
)
Addition of the description of electrical power to the Dry Conversion (DC) Building in Section e
10.2.1.5.
Addition of descriptive information on the Solids Processing Facility (SPF) to Sections 10.4.4, Table 11-10.2, Figure ll-10.27b (new), and Figures ll-10.30 and 11-10.31 (revised).
Note: SPC has not yet been authorized by License Amendment (application dated July 30, 1996), so no Part i SPF information has been included.
Addition of Figures ll-10.33 through ll-10.37 to describe the DC Building layout and process (SPC letter of August 29,1996). Figures ll-10.33 through 11-10.36 are proprietary to SPC i
and an affidavit to that effect was submitted with that letter.
Replacement of the 1992 fire inspection report in Appendix A with a 1996 report, including SPC's response.
Chapter 11 Replacement of R. E. Coen's education and experience statement in Section 11.3.19 with e
that of J. M. Deist.
l l
Chapter 12 l
i Replacement of the 1991 ALARA Report in Appendix A with that of 1995. Note: The 1995 e
ALARA Report is proprietary to SPC and an affidavit attesting to that fact is enclosed.
i a
l
3 T
i Mr. Rob:rt C. Pirrson JBE:96:097 j
. October 28,1996 Page 3 Chapter 15 1
i Left spaces for pages 15-52 through 15-79 to accommodate safety analysis descriptions for e
' UO process systems not yet discussed, 2
if you have questions regarding the information presented, please call me at 509-375-8663.
Very truly yours, a es B. Edgar Staff Engineer, Licensing csk Enclosures cc: C. A. Hooker, NRC Region IV WCFO i
I
~
Affidavit of Raymond E. Vaughan I, Raymond E. Vaughan, being first duly sworn, depose and say:
- 1. I am Manager, Safety, Security & Licensing of Siemens Power Corporation -
Nuclear Division, a corporation duly organized and existing under and by virtue of the laws of the State of Deleware, with offices at 2101 Horn Rapids Road, City of Richland, County of Benton, State of Washington, and on whose behalf I make this affidavit.
- 2. I am fanjliar with the contents of Siemens Power Corporation document EMF-96 050 (P), "The ALARA Report." Information in this document: (i) has been held in confidence by Siemens Power Corporation-Nuclear Division pursuant to its internal policies, (ii) is presented to the U.S. Nuclear Regulatory commission in confidence, and (iii) is not available from public sources.
I am authorized to make the statements that are set forth herein on behalf of Siemens Power Corporation - Nuclear Division and the statements made in this affidavit are, to the best of my knowledge, information and belief, truthful and complete.
[
Siemens Power Corporatiori-Nuclear Division By:
h-T
,m R yrfio E.Vaughan Man.
r-afety, SecuntvJk Lice.ina k 42.9, I d C Date State of Washington SS County of Benton Raymond E. Vaughan personally appeared before me known or proved to me to be the same person who executed the foregoing instrument and to be the Manager, Safety, Security & Licensing of Siemens Power Corporat!on - Nuclear Division and acknowledged to me that he executed the same as his free act and deed and the j
free act and deed of Siemens Power Corporation - Nuclear Division.
Subscribed and sworn to before me this c7 F day of OdodfA 1996.
LT U Of Ed ackie J. Ogden y
Notary Public 3l0ll92 My Commission Expires i