Forwards Revised Request for Approval to Utilize ASME Code Cases N-411 & N-397 in Piping Sys Analysis.Rev Corrects Inadvertent Errors in 850805 Request.Util Proposes Utilizing Developments Reported in Future Dynamic Analyses
ML20134D458
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/13/1985
From: Domer J
TENNESSEE VALLEY AUTHORITY
To: Adensam E
Office of Nuclear Reactor Regulation
References
NUDOCS 8508190231
Download: ML20134D458 (4)


Text

TENNESSEE VALLEY AUTHORITY CHATTANOOGA. TENNESSEE 374o1 400 Chestnut Street Tower II August 13, 1985 Director of Nuclear Reactor Regulation Attention:

Ms. E. Adensam, Chief Licensing Branch No. 4 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Ms. Adensam:

In the Matter of the

)

Docket Nos. 50-327 Tennessee Valley Authority

)

50-328 By my letter dated August 5, 1985, TVA transmitted a request for approval to utilize ASME Code Cases N-411 and N-397 in the analysis of piping systems.

Enclosed is a revision to the request which corrects inadvertent errors.

If you have any questions concerning this matter, please get in touch with Jerry Wills at FTS 858-2683.

Very truly yours, TENNESSEE VALLEY AUTHORITY

/.

  1. Mid J. A. Domer, Chief Nuclear Licensing Branch Sworn po a d subsce before me thi 4

day of

/C 1985 b

w INotarfPublic

/gf My Conunission Expires

,/ {6 Enclosure cc:

See page 2 gB190231850813 p

ADOCK 05000327 PDR 0

Y l

An Equal Opportunity Employer

o

. Director of Nuclear Reactor Regulation August 13, 1985 cc (Enclosure):

U.S. Nuclear Regulatory Commission Region II Attn:

Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Mr. Carl Stahle Sequoyah Project Manager U.S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20814

1

~

~

ENCLOSURE SEQUOYAH NUCLEAR PLANT REQUEST FOR NRC APPROVAL FOR USE OF HIGHER VARIABLE DAMPING VALUE FOR THE DYNAMIC ANALYSIS OF PIPING SYSTEMS The current piping analysis techniques used by TVA in the analysis of the piping at SQN are conservative in the area of dynamic analysia. TVA proposes to utilize the following two developments reported by the Pressure Vessel Research Committee (PVRC) in any future dynamic analysis of the analyzed piping at SQN. These developments by PVRC (with TVA participating) have been submitted by PVRC to NRC for their approval.

Variable Damoint Values for Piping Analysis In the dynamic analysis of class 1, 2, and 3 piping systems, the value of the damping used in the spectral analysis method are 0.5 percent for operating base earthquake, 1 percent for safe shutdown earthquake, and 2 percent for the dynamic loads resulting from the design basis accident.

These damping values are very conservative and result in the overdesign of pipe supports. The cost of design and fabrication of these supports add to the plant cost overruns.

The Task Group on Damping Values of the PVRC Technical Committee on Piping Systems has recently completed a review of a significant data base of damping tests. The results of the review clearly indicate the justification for increasing the present damping values for dynamic design of nuclear power plant piping above those in use at SQN. Based upon their evaluations, the current recommendation of the Task Group members is that damping of 5 percent is acceptable to 10 Hz linearly decreasing to 2 percent.at 20 Hz and held constant at 2 percent to 33 Hz.

Recommendations are independent of pipe diameter.

These higher recommended damping values, also described in ASNE Code Case N-411, can translate into substantial savings in time, effort, and cost towards the requalification of the existing piping systems or in the design of new piping systems.

If, as a result of using the damping values in ASME Code Case N-411, piping supports are moved, modified or eliminated, the expected increased piping displacements due to greater piping flexibility will be checked to assure that they can be accommodated and that there will be no adverse

~

interaction with adjacent structures, components and equipment.

Spectra Shiftina Regulatory Guide 1.122 recommends that the calculated dominant peaks of the floor response spectra be broadened to account for uncertainties in the structural frequencies owing to uncertainties in the material properties of the structure and soil and to approximations in the modeling techniques.

This method of peak broadening is very conservative. An alternative method of broadening of the structural pesks as described in Code Case N-397 can be based on a probabilistic approach.

In the particular case where there is more than one piping frequency located within the frequency range of a 024194.03 s

PT

~

2 widened spectrum peak, the floor spectrum curve may be more realistically applied in accordance with this code case.

It is obvious that the analysis utilizing spectra peak shif ting becomes cumbersome and less efficient for multiple support motion (multiple zones) and if there is more than one peak within a defined frequency range of interest. It is TVA's intent to use spectra peak shifting technique only if relief is required on a particular pipe support or where substantial redesign is required.

Recomunendations The proposed recommendations have been accepted by the PVRC Task Group on Damping, the Technical Committee on Piping Systems, and the Steering Committee on Piping Systa.ms. The proposals have been forwarded to NRC (reference 1) and considered by ASME (reference 2) for review and approval on a generic basis. NRG was represented on the PVRC committees.

Dr. S. N. Hou and Dr. W. F. Anderson were on the Technical Committtee on Piping Systems, Task Group on Damping, and R. J. Bosnak participated on the Steering Committee on Piping Systems. The response spectra peak shifting method has been accepted by NRC for inclusion in Standard Review Plan 3.9.2.

NRC has accepted the use of higher damping values in Southern California Edison's San Onofre Nuclear Plant unit I seismic reevaluation program (reference 3).

We feel that the changes proposed by PVRC for higher damping values and for an alternative to peak broadening are more realistic and constitute a conservative design.

Such findings were substantiated by the Lawrence Livermore National Laboratory on three piping systems at Zion Nuclear Plant (reference 4).

TVA proposes that these two techniques be used in future i

analysis offorts at SQN for the requalification of existing design and in the analysis of new systems. Use of these methods could result in more flexible piping systems which, according to current industry thinking, would resnit in more reliable systems.

References 1.

Letter from L. J. Chockie, Chairman of PVRC, to N. J. Palladino, Chairman of NRC, dated June 9, 1983.

2.

Minutes of the Special Working Group on Dynamic Analysis of ASME Section III, February 6, 1984.

3.

Letter from Harold R. Denton, Director of the Office of Nuclear l

Reactor Regulation, to K. Baskin, Vice President Nuclear Engineering l

Licensing and Safety Department of Southern California Edison Company, l

dated February 8, 1984.

4.

" Impact of Changes in Damping and Spectrum Peak Broadening on the Seismic Response of Piping Systems," NUREG/CR-3526, December 1983.

024194.03

,