Revised Monthly Operating Rept for June 1996 for Wolf Creek
ML20134C132
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 06/30/1996
From:
WOLF CREEK NUCLEAR OPERATING CORP.
To:
Shared Package
ML20134C128 List:
References
WO-96-0134, WO-96-134, NUDOCS 9609250271
Download: ML20134C132 (1)


Text

Attachmant 2 to WO 96-0134 Page 1 of 2 OPERATING DATA REPORT DOCKET NO. 50-482 WOLF CREEK GENERATING STATION WOLF CREEK NUCLEAR OPERATING CORPORATION

~

DATE 7-8-96 TELEPHONE 316-364-8831 OPERATING STATUS

1. Reporting Period: June, 1996 Gross Hours in Reporting Period 720 [
2. Currently Authorized Power Level (MWt): 3565 Max. Depend. Capacity (MWe-Net) : 1163 l

Design Electrical Rating (MWe-Net) : 1170 I

3. Power Level to Which Restricted (If Any) (MWe-Net) : N/A
4. Reasons for Restriction (If Any): N/A This Month Yr. to Date Cumulative
5. Number of Hours Reactor was Critical 680.7 2,718.2 77,334.9
6. Reactor Reserve Shutdown Hours 0.0 0.0 339.8
7. Houre Generator on Line 671.0 2,663.3 76,443.0
8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
9. Gross Thermal Energy Generated (MWh) 2,349,911 9,237,833 254,579,503
10. Gross Electrical Energy Generated (MWh) 804,513.0 3,191,319 88,450,239 I
11. Net Electrical Energy Generated (MWh) 769,603.0 3,022,669 84,459,520
12. Reactor Service Factor 94.5% 62.2% 81.5%

I

13. Reactor Availability Factor 94.5% 62.2% 81.9%  ;
14. Unit Service Factor 93.2% 61.0% 80.6%
15. Unit Availability Factor 93.2% 61.0% 80.6%
16. Unit Capacity Factor (Using MDC) 91.9% 59.3% 78.2%

l

17. Unit Capacity Factor (Using Design MWe) 91.4% 59.2% 76.1%
18. Unit Forced Outage Rate 6.8% 5.6% 4.8%
19. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of each):

None

20. If Shut Down at End of Report Period, Estimate Date of Startup: N/A Wolf Creek Generating Station Monthly Operating Report June, 1996 Page 3 of 6 r

9609250271 960913 PDR ADOCK 05000482 R PDR .