Forwards Request for Addl Info NRC Requires to Prepare Final Draft of Tech Specs.Info Requested within 7 Days from Date of Ltr
ML20134B813
Person / Time
Site: Millstone Dominion icon.png
Issue date: 08/13/1985
From: Youngblood B
Office of Nuclear Reactor Regulation
To: Opeka J
NORTHEAST NUCLEAR ENERGY CO.
References
NUDOCS 8508160086
Download: ML20134B813 (5)


Text

.

Docket No.: 50-423 AUG 13 1985 Mr. John F. Opeka Senior Vice President Nuclear Engineering and Operations Northeast Nuclear Energy Company P. O. Box 270 Hartford, Connecticut 06141-0270 Daar ". Opera:

Subject:

Request for Additional Information for Millstone Nuclear Power Station, Unit No. 3 Enclosed is a list of information the staff requires to prepare the Final Draft of the Millstone 3 Technical Specifications.

Since this review is ongoing additional information may be required in the future.

Please submit the information requested by this letter within 7 days from the date of this letter.

For further infomation or clarification, please contact the Licensing Pro-ject Manager, Elizabeth L. Doolittle at (301) 492-4911.

Sincerely.

ORIGINAL sic:a n i B. J. Youngblood, Chief Licensing Branch No. 1 Division of Licensing

Enclosure:

As stated cc: See next page DISTRTBilTION:

N oolittle LPDR ACRS (16)

NSIC EJordan PRC System

-JPartlow LBf1 R/F BGrimes MRushbrook RPerch 9

LB TSRB:

L L r ED le:kab RPerch lood 08/13/85 08/ g3 /85 5

~

8508160086 850013 PDR ADOCK 05000423 A

PM

F Mr. J. F. Opeka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. 3 cc:

Gerald Garfield, Esq.

Day, Berry & Howard City Place Hartford, Connecticut 06103-3499 Mr. Maurice R. Scully, Executive Director Connecticut Municipal Electric Energy Cooperative 268 Thomas Road Groton, Connecticut 06340 Robert W. Bishop, Esq.

Corporate Secretary Northeast Utilities

' Post Office Box 270 Hartford, Connecticut 06141 Mr. T. Rebelowski Senior Resident Inspector Office U. S. Nuclear Regulatory Commission Millstone III P. O. Box 615 Waterford, Connecticut 06385 Mr. Michael L. Jones, Manager Project Management Department Massachusetts Municipal Wholesale Electric Company Post Office Box 426 Ludlow, Massachusetts 01056 Regional Administrator U. S. NRC, Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 Mr. Karl Abraham Public Affairs Office U. S. Nuclear Regulatory Conmission, Region I King of Prussia, Pennsylvania 19406

. ' ~~'.

ENCLOSURE Additional Information Required from Millstone 3 1.

Based on discussions with Fire Protection reviewer, NU to propost new wording for Fire System Operational Test definition.

2.

Table 2.2-1: Values for trip setpoints/ allowable values are preliminary values.

NU needs to provide final values and setpoint methodology analysis report to finalize table.

3.

NU needs to provide additional information to justify change of wording from STS for T/S 3.1.2.1.a.

4.

hU needs to provide additional information to justify change of wording from STS for T/S 3.1.2.2.a.

Sa. T/S 3.1.1.1 Need SHUTDOWN MARGIN value.

6.

T/S 3.1.2.5 Need minimum borated water volume (gallons) for the Boric

.. Acid Storage System and the RWST.

7.

T/S 3.1.2.6 Need minimum borated water volume (gallons) for the Boric i

Acid Storage System.

8.

T/S 3.1.3.4 Need RATED THERMAL POWER value for ACTION b.

9.

Figure 3.1-1 Need new figure of good quality that is reproducible.

10.

Figure 3.1-2 Need new figure of good quality that is reproducible.

~~

11. Figure 3.2-la Need new figure of good quality that is reproducible.

12.

Figure 3.2-lb Need new figure of good quality that is reproducible.

13.

Figure 3.2-2a Need new figure of good quality with grid background that is reproducible.

14.

Figure 3.2-2b Need new figure of good quality with a grid background that is reproducible.

15. Table 3.3-4 Item 8 Need trip setpoint and allowable values.

16.

Table 3.3-5 Item 15 Need response times.

17. T/S 4.3.3.2 Need justification for change in wording from STS.
18. Table 3.3 '1 Need updated no. of detectors to reflect total number of each functional type in each area.
19. T/S 4.4.5.4a.6) Need value for tube plugging limit.

20.

Figures 3.4-2 and 3.4-3 Provide figures.

21.

T/S 3.4.9.2 Need value for spray water AT.

3

. 22.

T/S 3.4.9.3 Need value for RCS vent size (square inches).

23.

T/S 3.5.1 Need borated water volume values.

24.

T/S 4.5.2.f(4) Need value for containment recirculation pump differential pressure.

25. T/S 4.5.2.h.1)b) and 2)b) Need value for total pump flow rate.

26.

T/S 4.6.1.2.e Need value for combined bypass leakage rate.

27.

Table 3.6-1 Provide bypass leakage paths.

28. T/S 4.6.1.3.b 2) Need submittal of Appendix J exemption to have provision remain in technical specifications.

29.

Figure 3.6-1 Provide new figure of good quality that is reproducible.

30.' T/S 4.6.1.3.a Provide justification for change in method from STS Rev. 5.

31. T/S 4.6.1.5 Provide air temperature measurement locations.

32.

iis *.o.e.1 b) Provide value for pump differential pressure.

33.

T/S 4.6.2.2 b) Provide value for pump differential pressure..

34.

T/S 4.6.2.3 d Provide method to verify flow path open.

35. Table 3.6-2 Provide complete listing of values that correspond to penetrations listed in FSAR Table 6.2-65.
36. T/S 3.6.5 2 Provide justification to delete specification.
37. T/S 3.J.6 Provide new T/S wording using Rev. 5 STS.
38. T/S 4.7.12.1 Millstone to propose additional T/S to test dampers on 18-month basis.

39.

T/S 3.8.1.1.b 1) Provide minimum day tank volume.

40.

T/S 3.8.1.1.b 2) Provide minimum fuel storage system volume.

41 4.

1 2 a 5) Provide justification for acceptability of 4160 42.

T/S 3.8.1.2 b 1) Provide minimum day tank volume.

43.

T/S 3.8.1.2.b 2) Provide minimum fuel storage system volume.

l

Y 3-44.

T/S 3.8.2.1 Provide detailed justification for proposed changes.,

i

45. Tables 3.8-2a and 3.8-2b Provide value listings.

~

46.

Table 3.8-1 Provide complete listing of protective devices.

47. T/S 3.9.6 Millstone to provide new submittal.

48.

Figures 5.1-1, 5.1-2, 5.1-3 Provide figures.

49.

Figures 6.2-1, 6.2-2 Provide figures.

  • =.